Last visit was: 22 Apr 2026, 20:08 It is currently 22 Apr 2026, 20:08
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
MANASH94
Joined: 25 Jun 2025
Last visit: 22 Apr 2026
Posts: 89
Own Kudos:
63
 [1]
Given Kudos: 16
Location: India
Schools: IIM IIM ISB
GPA: 2.9
Schools: IIM IIM ISB
Posts: 89
Kudos: 63
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
gemministorm
Joined: 26 May 2025
Last visit: 21 Apr 2026
Posts: 143
Own Kudos:
110
 [1]
Given Kudos: 57
GMAT Focus 1: 565 Q82 V79 DI73
GMAT Focus 2: 605 Q84 V83 DI73
GMAT Focus 2: 605 Q84 V83 DI73
Posts: 143
Kudos: 110
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
vikramadityaa
Joined: 28 Jul 2025
Last visit: 23 Dec 2025
Posts: 55
Own Kudos:
41
 [1]
Given Kudos: 1
Posts: 55
Kudos: 41
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Sakshi1405
Joined: 04 Jul 2021
Last visit: 22 Apr 2026
Posts: 18
Own Kudos:
17
 [1]
Given Kudos: 75
Location: United States
Concentration: Entrepreneurship, Strategy
GMAT Focus 1: 645 Q87 V82 DI77
GPA: 2.88
WE:Supply Chain Management (Retail: E-commerce)
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let suppose each does 80 units of total work (took LCM of all rates), so
Alex - 8 hrs = 10 units/hr
Beth - 20 hrs = 4 units/hr
Charles - 40 hrs = 2 units/hr
Dana - 80 hrs = 1 unit/hr

In 4 hrs = 17 units work done if one person is only working for that hr as assigned by manages
So in 16 hrs = 68 units of work is done and remaining is 12 units, since total is 80 units considered

Now for min time, folks with higher work rates are considered so for 12 units another 1.5 hrs is needed (10 units by alex & 2 units by Beth)
For max time, folks with slower work rates should be consiered, so (1+2+4=7 by Dana,Charles & Beth & 5 units by Alex) adding to 3.5 hrs

So min = 17.5 and max = 19.5
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
chasing725
Joined: 22 Jun 2025
Last visit: 13 Jan 2026
Posts: 176
Own Kudos:
173
 [1]
Given Kudos: 5
Location: United States (OR)
Schools: Stanford
Schools: Stanford
Posts: 176
Kudos: 173
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.

Let's assume the total units of work that needs to be done = 80

A can do 10 units in an hour
B can do 4 units in an hour
C can do 2 units in an hour
D can do 1 unit in an hour

Total in 4 hours they can do 17 units of work

In 4 * 4 hours they can 17 * 4 units of works = 68 units of work

Remaining = 12

Fastest time :
A does 10 units then B does 2 units

16 + 1 + 0.5 = 17.5

Slowest time

D does 1 unit, C does 2 unit, B does 4 unit and A does 5 unit

16 + 1+ 1 + 1 +0.5 = 19.50

Minimum = 17.50
Maximum = 19.50
User avatar
flippedeclipse
Joined: 26 Apr 2025
Last visit: 22 Apr 2026
Posts: 105
Own Kudos:
Given Kudos: 37
GMAT Focus 1: 655 Q80 V87 DI80
Products:
GMAT Focus 1: 655 Q80 V87 DI80
Posts: 105
Kudos: 73
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.

Rates:
\(A=\frac{1}{8}=\frac{10}{80}\)

\(B=\frac{1}{20}=\frac{4}{80}\)

\(C=\frac{1}{40}=\frac{2}{80}\)

\(D=\frac{1}{80}\)

For the fastest rate, we want A to go as often as possible, so we start the cycle from her. \(\frac{17}{80}\) of the work gets done every cycle, and each cycle takes 4 hours. The closest multiple of 17 to 80, without exceeding 80, is \(17*4 = 68\), at which point we've just finished D doing her work, and A is going again. A goes, it's \(\frac{78}{80}\), then B goes, it's \(\frac{82}{80}\), thus complete! That took a total of:

\((4 cycles * 4 hours each)+2=18\)

Minimum time is 18 hours. There's only one option greater than this on the table for maximum hours, so instead of calculating it out, we'll select 19.5.
User avatar
cann2406
Joined: 20 Feb 2025
Last visit: 22 Apr 2026
Posts: 15
Own Kudos:
12
 [1]
Given Kudos: 51
Posts: 15
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Taking LCM of 8, 20, 40 & 80 = 80 which is total work.
Alex work done in 1 hour = 10
Beth work done in 1 hour = 4
Charles work done in 1 hour = 2
Dana work done in 1 hour = 1

For minimum time, person with highest work done will do the work first, then second highest and so on..
So, 10,4,2 & 1 in this pattern all will work till the total work is completed i.e. 80. Total time taken will be 17.5 hours.

Similarly, for maximum time, pattern followed will be slowest first, then second slowest and so on..
It will be 1,2,4 & 10 in this pattern. Total time taken will be 19.5 hours.

Minimum = 17.5 hours
Maximum = 19.5 hours
User avatar
aka007
Joined: 15 Nov 2019
Last visit: 19 Mar 2026
Posts: 42
Own Kudos:
37
 [1]
Given Kudos: 84
Posts: 42
Kudos: 37
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Use the RTW table as all have independent rates.

R T W
A 10. 8. 80
B 4 20 80
C 2 40 80
D 1 80 80

here the rate is in units/ hr.
time is in hours and work is in units. Have taken 80 as it is the LCM of 8,20,40, 80 to ease out calculation of rate.

Total rate in a 4 hour cycle= 17 units per 4 hours.

Hence in 4 such cycles. 17 x 4: 68 units in 16 hours.

To find min. Start with lowest rate. 68+1+2+4+10/2=80 units of work
time is 16 + 1+1+1+1/2=19.5

to find max. Start from highest rate. 68+10+4/2=80 80 units of work
time is 16+1+1/2=17.5.

Hence Max time is 19.5hrs and min time is 17.5 hrs.

Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
Sumimasen
Joined: 21 Jan 2024
Last visit: 22 Apr 2026
Posts: 36
Own Kudos:
33
 [1]
Given Kudos: 11
Products:
Posts: 36
Kudos: 33
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
To solve such problems, consider total work as LCM of hours each person.
Here it will be LCM of (8,20,40,80) will be 80.
So, consider total work = 80 units and solve as explained in image.
Attachments

SolutionPS3.jpg
SolutionPS3.jpg [ 124.96 KiB | Viewed 227 times ]

User avatar
HowCanIDoThis
Joined: 11 Oct 2025
Last visit: 06 Feb 2026
Posts: 19
Own Kudos:
14
 [1]
Given Kudos: 3
Posts: 19
Kudos: 14
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Quote:
Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively
Their work rate per hours equals to 1/8, 1/20, 1/40 & 1/80 of the task per hour, respectively.
Each cycle of each person working on this task per hour therefore would complete 1/8+1/20+1/40+1/80 = 17/80 of the task.
4 cycles will see 68/80 of the work being done. 5 cycles equals to 85/80 of the work, which means the work will be completed within 4 to 5 cycles (16 to 20 hours). This leaves us with 12/80 of the work to be done.
The fastest way to complete the task is to let the individuals with the highest work rate to do it first (Alex -> Beth ->...). After 1 hours of Alex doing the work, there will be 12/80-1/8=1/40 of the task left for Beth to do, which takes her (1/40) / (1/20) = 0.5 hours to complete => The minimum amount of time is 16 + 1 +0.5 = 17.5 hours.
Conversely, to find the maximum amount of time, let those with the lowest work rate do it first. Applying the reversed procedure:
After 1 hours of Dana, there'll be 12/80 - 1/80 = 11/80 of the task left
After 1 hours of Charles, there'll be 11/80 - 1/40 = 9/80 of the task left
After 1 hours of Beth, there'll be 9/80 - 1/20 = 5/80 of the task left
Alex to complete it in (5/80) / (1/8) = 0.5 hours.
The Maximum amount of time is 16+ 1 + 1 + 1 + 0.5 = 19.5 hours
User avatar
jkkamau
Joined: 25 May 2020
Last visit: 22 Apr 2026
Posts: 226
Own Kudos:
190
 [1]
Given Kudos: 142
Location: Kenya
Schools: Haas '25
GMAT 1: 730 Q50 V46
GPA: 3.5
Schools: Haas '25
GMAT 1: 730 Q50 V46
Posts: 226
Kudos: 190
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
To find the amount of work to be done by all find the LCM and add 1/8+1/20+1/40+1/80= 17/80 of work per hour meaning in 4 hours they will have covered 68/80 remaining with 12/80 =0.15
To minimize total work we can redistribute the work starting with Alex who takes the shortest towards Dana until the work ends
After 4x4 hours= 16 hours next we go to Alex (1 hour) so 0.15-1/8 = 0.025. Beth rate is is 0.05 so she will finish the remaining in 0.5 hours
Total minimal time = 16+1+0.5= 17.5 hours
To maximize we do the opposite and start with the slowest person who is Dana and work towards Alex
After 4x4 hours next we go to Dana (1 hour) 0.15-1/80 = 0.1375 then Charles (1 hour) 0.1375-1/40= 0.1125, Beth (1 hour ) 0.1125-1/20= 0.0625, Alex (0.0625/0.125) = O.5 hr
Max time= 16+1+1+1+0.5= 19.5 hours
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
adityamntr
Joined: 15 Jul 2023
Last visit: 21 Feb 2026
Posts: 111
Own Kudos:
81
 [1]
Given Kudos: 13
Location: India
Concentration: General Management, Strategy
Posts: 111
Kudos: 81
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.

calculate task done by person in a hour
A = 1/8 = 0.125
B = 0.05
C = 0.025
D = 0.0125

task done in 4 hours of their work = A + B + C + D = 0.2125
since the task are done in round robin fashion
min time would be when quickest person does the job first
so order will be
A B C D x 4times = 0.85 work done in 16 hours
in next hour A does 0.125 ( total 0.975 in 17 hours)
remaining is 0.025 which B can do in 30 mins

so all work is done in 17.5 hours

max time will be take in opposite order of above
D C B A
same wil continue 4 times
D C B A x 4 times = 0.85 work done in 16 hours
in next 1 hour D does 0.0125 , next 1 hour C does 0.025, next 1 hour B does 0.05
remaining is 0.0625 work, which A can do in 1/2 hour
so total is 16 + 1 + 1 + 1 + 0.5 = 19.5 hours
User avatar
Lizaza
Joined: 16 Jan 2021
Last visit: 29 Mar 2026
Posts: 240
Own Kudos:
282
 [1]
Given Kudos: 7
GMAT 1: 710 Q47 V40
GMAT 1: 710 Q47 V40
Posts: 240
Kudos: 282
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
First, let's denote the respective speeds of workers bringing them to the common denominator of 80:
\(a = 1/8=10/80\)
\(b=1/20=4/80\)
\(c=1/40=2/80\)
\(d=1/80\)
The units of speeds are share of the project per hour.

Now, in one cycle of 4 people we're getting \(\frac{10+4+2+1}{80}=17/80\) of the project done, and this cycle lasts 4 hours.
Once we finish 4 such cycles, we will come as close as possible to the whole project, completing \(17*4/80=68/80\) of the work, and it will take 16 hours.

How there's the slowest and quickest scenario for the remaining \(12/80\):

(1) To cover 12 parts slowly, we need to go in the order of \(d -> c -> b -> 0.5a\), which will take 3.5 hours (and this will be added to the required 16).

(2) To cover 12 parts quickly, we need to start from the fastest: \(a -> 0.5b,\) which will take 1.5 hours.

Therefore, the minimum necessary time is 17.5 hours, and the maximum is 19.5 hours.
User avatar
AviNFC
Joined: 31 May 2023
Last visit: 10 Apr 2026
Posts: 306
Own Kudos:
366
 [1]
Given Kudos: 5
Posts: 306
Kudos: 366
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
LCM (8,20,40,80)=80
So in one set work done = 17
17*4=68 units ..so 4*6=16 hrs.

remaining 12 units.
minimum time if A works full 1 hr & B works half = 1+0.5 = 1.5 hrs
max time if D, C, B works full 1 hr each & A half = 1+1+1+0.5=3.5

Min time = 17.5
Max time = 19.5
User avatar
Dereno
Joined: 22 May 2020
Last visit: 22 Apr 2026
Posts: 1,398
Own Kudos:
1,373
 [1]
Given Kudos: 425
Products:
Posts: 1,398
Kudos: 1,373
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
There are four persons Alex, Beth, Charles and Dana each working alone at their constant rates - they complete their work in hours 8,20,40,80 respectively.

The work is carried out in a REPEATING FOUR PERSON CYCLE (where each work for one hour, once the cycle is completed. Then all again start working in the same cycle).

LCM of hours (8,20,40,80) = 80.

So, the total work is 80 units.

The rates of Alex, Beth, Charles and Dana are found using the formula : Efficiency or Rate = Work/ Time taken.

Efficiency or rate :

Alex = 80/8 = 10 units per hour.

Beth = 80/20 = 4 units per hour.

Charles = 80/40 = 2 units per hour.

Dana = 80/80 = 1 units per hour.

So in order of efficiency: Alex > Beth > Charles > Dana .

To complete the work in minimum time, we need the efficiency order to be the same mentioned above.

Units of work completed in ONE cycle = 10+4+2+1 = 17 units of work.

To complete ONE cycle or 17 units of work, the time taken is 4 hours.

After FOUR cycles, the amount of work completed = 17*4 = 68 units of work.

Remaining work = 80 - 68 = 12 units of work.

4 Cycles = 4*4 = 16 hours have been completed. Work completed is 68 units.

Out of the remaining = 10 units is completed by Alex in 1 hour.

Remaining work = 2 units, which is completed by Beth is half an hour.

Total time taken = 16 hours + 1 hour + 0.5 hours = 17.5 hours.

Minimum time taken = 17.5 hours.

To find the MAXIMUM time taken, we need to reverse the efficiency cycle : Dana <Charles < Beth< Alex.

Till the 4 cycles, the calculation is same.

Out of 80 units of work, 68 units is completed in 16 hours.

Remaining Work = 80-68 = 12 units of work.

Dana completed 1 units in 1 hour. Remaining = 12-1 = 11 units.

Charles competed 2 units of work in 1 hour. Remaining work = 11-2 = 9 units.

Beth completed 4 units of work in 1 hour. Remaining work = 9-4 = 5 units.

Till now the time taken = 16 + 1+1+1 = 19 hours.

Alex competed 5 unit of remaining work in 0.5 hours.

So, Maximum time taken = 19 + 0.5 = 19.5 hours.
User avatar
Natansha
Joined: 13 Jun 2019
Last visit: 11 Mar 2026
Posts: 195
Own Kudos:
65
 [1]
Given Kudos: 84
Posts: 195
Kudos: 65
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rates of A, B, C & D are 1/8 work/hr, 1/20, 1/40, 1/80

which basically means
10/80, 4/80, 2/80, 1/80

used a very different way to calculate, basically in a 4hr circle 17/80 work will be done (with everyone working once)
then saw 16 in the ans opts, so checked in 16hrs circle, 17/80 * 4 = 68/80 work will be done

the ans is more than 16hrs, and the difference comes in the remaining 12/80 work

for the minimum time, we start with the rates from the first person, to complete 12/80 work, A will work an hour completing 10/80 & B will work for half hour completing 2/80. Total 16 + 1.5 = 17.5hrs

for maximum time, we start with the rates from the last person, so 1/80 + 2/80 + 4/80 + 5/80 (A will work only half hour and the rest will work for 1 hr) giving us 3.5hrs, total time = 16 + 3.5 hrs = 19.5hrs

Ans 17.5hrs & 19.5hrs
User avatar
canopyinthecity
Joined: 12 Jul 2025
Last visit: 22 Apr 2026
Posts: 92
Own Kudos:
61
 [1]
Given Kudos: 19
Posts: 92
Kudos: 61
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We need to determine the minimum and maximum number of hours required for the task to be completed.

Work Rates (in tasks per hour):
Alex = 1/8
Beth = 1/20
Charles = 1/40
Dana = 1/80

It is given that task is scheduled in repeating 4-person cycle, with each person works for exactly 1 hour before the next person begins.

Total work in one 4-hour cycle = 1/8+1/20+1/40+1/80 = 17/80

To identify the total cycles needed, find the smallest multiple that reaches or exceeds 1.

Since 17/80*4 = 68/80 and 17/80*5 = 85/80, we can conclude that 4 to 5 cycles are required to complete the task.

To calculate the maximum value, consider after 4 cycles, the order of the work is Alex, Beth, Charles and Dana (fastest to the slowest):

At 16 hours, 68/80 task is completed.
After 1 hour of Alex: 68/80+1/8 = 78/80
At this point, only 2/80 (=1/40) task is remaining.
Beth works at 1/20 per hour. He can complete 1/40 work in half the time i.e. 30 mins.
Hence after 30 mins of Beth: 78/80 + 1/40 = 1 (Task would be completed

Therefore, the minimum time required to complete the task is 17.5 hours.

On similar lines, to calculate the maximum time required, we can consider after 4 cycles, the order of work is Dana, Charles, Beth and Anna (the slowest to the fastest)

At 16 hours, 68/80 task is completed.
After 1 hour of Dana: 68/80 + 1/80 = 69/80
After 1 hour of Charles: 69/80 + 1/40 = 71/80
After 1 hour of Beth: 71/80 + 1/20 = 75/80
At this point, 5/80 (=1/16) task is remaining.
Alex works at 1/8 per hour. He can complete 1/16 task in half the time i.e. 30 mins.

Therefore, the maximum time required to complete the task is 19.5 minutes.
User avatar
Harika2024
Joined: 27 Jul 2024
Last visit: 16 Mar 2026
Posts: 99
Own Kudos:
84
 [1]
Given Kudos: 31
Location: India
Posts: 99
Kudos: 84
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Given that team of 4 people each working alone in a cycle, one hour each.

WorkerHours to completeLCM of(8,20, 40, 80 ) = 80, Total work units = 80 units , now work rate (units per hours)
Alex (A)880/8 = 10
Beth(B)2080/ 20 = 4
Charles(C)4080 / 40 = 2
Dana (D)8080/80 = 1
Total work units in one cycle = 10 + 4 + 2 + 1 = 17

We need to find
1) Minimum number of hours required for the task to be completed
2) Maximum number of hours required for the task to be completed


1) lets calculate minimum time

order : A----> B----> C ----> D

we need 80 units.

for 4 cycles we have, 17*4 = 68 units
time taken = 4 cycles * 4 hrs per cycle = 16 hrs
work remaining = 80 - 68 = 12 units

now lets try finishing remaining work in above order

hour 17 - alex works for 1 hour = 68+ 10 = 78 units (2 units left)
hour 18 - beth works 1 hour but beth rate = 4 units per hr

time needed = 2/4 = 0.5 hr

Therefor minimum time = 17 hrs + 0.5 hr = 17.5 hrs

2) lets calculate maximum time

order : D --> C ---> B --->A [this cycle maximizes the work done by slow workers near the end]

we need 80 units.

hour 17 - dana works 1 hour = 68 + 1 = 69 units (11 units left)
hour 18 - charles works 1 hour = 69 + 2 = 71 units (9 units left)
hour 19 - beth works 1 hour = 71 + 4 = 75 units (5 units left)
hour 20 - alex finish remaining 5 units

time needed = 5/ 10 = 0.5 hrs

Therefor maximum time = 19 hrs + 0.5 hr = 19.5 hrs
User avatar
redandme21
Joined: 14 Dec 2025
Last visit: 05 Jan 2026
Posts: 97
Own Kudos:
87
 [1]
Posts: 97
Kudos: 87
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Alex rate = 1/8
Beth rate = 1/20
Charles rate = 1/40
Dana rate = 1/80

In 4 hours: 1/8+1/20+1/40+1/80=(10+4+2+1)/80=17/80

In 4*4=16 hours: 4*17/80=68/80 -> we need 12/80 to complete the task.


Minimum number of hours if we order people by decreasing rate (Alex, Beth, Charles, Dana): Alex add 10/80 is his hour and Beth add 2/80 in half an hour -> adding 1.5 hours

Maximum number of hours if we order people by increasing rate (Dana, Charles, Beth, Alex): Dana add 1/80 is her hour, Charles add 2/80 is his hour, Beth add 4/80 in her hour and Alex add 5/80 in half an hour -> adding 3.5 hours

Minimum = 16 + 1.5 = 17.5
Maximum = 16 + 3.5 = 19.5
User avatar
geocircle
Joined: 14 Dec 2025
Last visit: 27 Dec 2025
Posts: 90
Own Kudos:
87
 [1]
Posts: 90
Kudos: 87
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
total task = 80 work units

Alex's work units in 1 hour = 10
Beth's work units in 1 hour = 4
Charles's work units in 1 hour = 2
Dana's work units in 1 hour = 1

Every cycle of 4 people: 10+4+2+1=17

quotient of 80/17 is 4 -> 4 complete cycles = 16 hours
remainder of 80/17 is 12

Ordering people from highest rate to lowest rate you obtain the minimum number of hours: 1 hour of Alex (10) and 0.5 hours of Beth (2). 12 work units in 1.5 hours. Total 16+1.5=17.5 hours.
Ordering people from lowest rate to highest rate you obtain the maximum number of hours: 1 hour of Dana (1), 1 hour of Charles (2), 1 hour of Beth (4) and 0.5 hours of Alex (5). 12 work units in 3.5 hours. Total 16+3.5=19.5 hours.

Minimum = 17.5 and Maximum = 19.5
   1   2   3   4   
Moderators:
Math Expert
109754 posts
498 posts
212 posts