Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more
Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.
Select for
Minimum the minimum number of hours required for the task to be completed, and select for
Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
There are four persons Alex, Beth, Charles and Dana each working alone at their constant rates - they complete their work in hours 8,20,40,80 respectively.
The work is carried out in a REPEATING FOUR PERSON CYCLE (where each work for one hour, once the cycle is completed. Then all again start working in the same cycle).
LCM of hours (8,20,40,80) = 80.
So, the total work is 80 units.
The rates of Alex, Beth, Charles and Dana are found using the formula : Efficiency or Rate = Work/ Time taken.
Efficiency or rate :
Alex = 80/8 = 10 units per hour.
Beth = 80/20 = 4 units per hour.
Charles = 80/40 = 2 units per hour.
Dana = 80/80 = 1 units per hour.
So in order of efficiency:
Alex > Beth > Charles > Dana .
To complete the work in
minimum time, we need the efficiency order to be the same mentioned above.
Units of work completed in ONE cycle = 10+4+2+1 = 17 units of work.
To complete ONE cycle or 17 units of work, the time taken is
4 hours.
After
FOUR cycles, the amount of work completed = 17*4 = 68 units of work.
Remaining work = 80 - 68 =
12 units of work.
4 Cycles = 4*4 = 16 hours have been completed. Work completed is 68 units.
Out of the remaining = 10 units is completed by Alex in 1 hour.
Remaining work = 2 units, which is completed by Beth is half an hour.
Total time taken = 16 hours + 1 hour + 0.5 hours = 17.5 hours.
Minimum time taken = 17.5 hours. To find the
MAXIMUM time taken, we need to reverse the efficiency cycle :
Dana <Charles < Beth< Alex. Till the 4 cycles, the calculation is same.
Out of 80 units of work, 68 units is completed in 16 hours.
Remaining Work = 80-68 = 12 units of work.
Dana completed 1 units in 1 hour. Remaining = 12-1 = 11 units.
Charles competed 2 units of work in 1 hour. Remaining work = 11-2 = 9 units.
Beth completed 4 units of work in 1 hour. Remaining work = 9-4 = 5 units.
Till now the time taken = 16 + 1+1+1 = 19 hours.
Alex competed 5 unit of remaining work in 0.5 hours.
So,
Maximum time taken = 19 + 0.5 = 19.5 hours.