Last visit was: 01 Sep 2026, 12:02 It is currently 01 Sep 2026, 12:02
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
ExpertsGlobal5
User avatar
Experts' Global Representative
Joined: 10 Jul 2017
Last visit: 01 Sep 2026
Posts: 6,485
Own Kudos:
7,068
 [8]
Given Kudos: 64
Location: India
GMAT Date: 11-01-2019
Expert
Expert reply
Posts: 6,485
Kudos: 7,068
 [8]
1
Kudos
Add Kudos
7
Bookmarks
Bookmark this Post
User avatar
AdarshSambare
Joined: 29 Jan 2022
Last visit: 30 Aug 2026
Posts: 312
Own Kudos:
162
 [4]
Given Kudos: 136
Concentration: General Management, Sustainability
GPA: 2
WE:Engineering (Manufacturing)
Posts: 312
Kudos: 162
 [4]
2
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
User avatar
BongBideshini
Joined: 25 May 2021
Last visit: 01 Sep 2026
Posts: 387
Own Kudos:
Given Kudos: 135
Location: India
Concentration: Entrepreneurship, Marketing
GPA: 3.8
WE:Engineering (Government)
Posts: 387
Kudos: 238
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ExpertsGlobal5
User avatar
Experts' Global Representative
Joined: 10 Jul 2017
Last visit: 01 Sep 2026
Posts: 6,485
Own Kudos:
Given Kudos: 64
Location: India
GMAT Date: 11-01-2019
Expert
Expert reply
Posts: 6,485
Kudos: 7,068
Kudos
Add Kudos
Bookmarks
Bookmark this Post
ExpertsGlobal5
40 skilled employees need 60 days to complete a project while working in the normal work schedule of 8 hours a day. They begin working but one month into the project, 30 employees need to shift to a different project. These 30 employees are replaced by 40 new employees who are 50% less productive. How much extra time per day should the new team work to avoid any delay in the completion of the project?

A. 10 hours 40 minutes
B. 10 hours 20 minutes
C. 6 hours 30 minutes
D. 2 hours 40 minutes
E. 2 hours 20 minutes
D is the correct answer choice.

Video explanation:

User avatar
VibhuAnurag
Joined: 29 Aug 2016
Last visit: 01 Sep 2026
Posts: 150
Own Kudos:
300
 [1]
Given Kudos: 7
Posts: 150
Kudos: 300
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total work:
40*60*8 = 19200
After 1 month = 30 days, work done = 40*30*8 = 9600
So, the remaining work = 19200−9600 = 9600

Now, 30 skilled employees leave. So, remaining skilled employees = 10.

They are replaced by 40 new employees who are 50% less productive.
--> 40 new employees = 20 skilled employees.
Therefore, new team’s effective strength = 10 + 20 = 30

They must complete the remaining work in 30 days.

Let required daily hours be h --> 30*30* h = 9600
--> h = 96/9 = 10.67 = 10 hours and 40 minutes

But the question is asking for extra time per day --> Normal work schedule = 8 hours.
--> 10 hours and 40 minutes − 8 hours = 2 hours and 40 minutes

The answer is D.
User avatar
Flyingdutch1307
Joined: 10 Jul 2024
Last visit: 01 Sep 2026
Posts: 13
Own Kudos:
6
 [2]
Given Kudos: 66
Location: India
GMAT Focus 1: 645 Q86 V82 DI77
GMAT Focus 2: 685 Q84 V84 DI84
GPA: 7.5
GMAT Focus 2: 685 Q84 V84 DI84
Posts: 13
Kudos: 6
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
a super easy trick

40 Emp -> 60d

Now, 30 are replaced with 40, who are 50% efficient. --> in simpler terms, we are getting 20 OG people

so basically we have 30 now, instead of 40

Work done by 40 folks : 30 folks => 4:3 (considering same amount of time)

now, if we want to achieve extra hours, to finish, we need to be 4/3 efficient

So => 8 *4/3 hrs = 10.667 (basicaly 2.667 hrs ~2h40m extra)