aadikamagic
A contractor hires 100 men to finish a job in 50 days. After 14 days, n men leave. After some more days, the contractor hires 2n more men to complete the job on time. For how many days did these 2n men work?
A. 20
B. 18
C. 16
D. 12
E. 8
We are given that 100 men will finish a job in 50 days; thus, the rate of the 100 men is 1/50 and the rate of each man is (1/50)/100 = 1/5000.
This is what we know:
The 100 men work for the first 14 days. Then n men leave and the (100 - n) men work for some number of days. Then 2n men join in (so now there are 100 - n + 2n = 100 + n men) and they all work for the remaining days and complete the job on time, in 50 days.
If we let x = the number of days the (100 - n) men work (after the first 14 days but before the 2n men join in), then (100 + 2n) men (after the 2n men join in) work for (36 - x) days, since the total number of days for the job is still 50. Thus, we can create the following equation:
100(1/5000)(14) + (100 - n)(1/5000)(x) + (100 + n)(1/5000)(36 - x) = 1
The 1 on the right-hand side of the equation represents the complete job and each of the addends on the left-hand side represents the fraction of the job the 100 men, (100 - n) men, and (100 + n) men contribute at different stages of the job, respectively.
Multiplying the equation by 5000, we have:
100(14) + (100 - n)(x) + (100 + n)(36 - x) = 5000
1400 + 100x - nx + 3600 - 100x + 36n - nx = 5000
5000 + 36n - 2nx = 5000
36n = 2nx
36 = 2x
18 = x
Since the extra 2n men actually work (36 - x) days, they work 36 - 18 = 18 days.
Answer: B