Last visit was: 22 Apr 2026, 13:25 It is currently 22 Apr 2026, 13:25
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,659
 [141]
7
Kudos
Add Kudos
134
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
BrentGMATPrepNow
User avatar
Major Poster
Joined: 12 Sep 2015
Last visit: 31 Oct 2025
Posts: 6,733
Own Kudos:
36,443
 [43]
Given Kudos: 799
Location: Canada
Expert
Expert reply
Posts: 6,733
Kudos: 36,443
 [43]
29
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
User avatar
anudeep133
Joined: 10 Aug 2015
Last visit: 14 Dec 2018
Posts: 94
Own Kudos:
282
 [39]
Given Kudos: 20
Posts: 94
Kudos: 282
 [39]
25
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
User avatar
Mo2men
Joined: 26 Mar 2013
Last visit: 09 May 2023
Posts: 2,426
Own Kudos:
1,508
 [3]
Given Kudos: 641
Concentration: Operations, Strategy
Schools: Erasmus (II)
Products:
Schools: Erasmus (II)
Posts: 2,426
Kudos: 1,508
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
One woman and one man can build a wall together in two hours, but the woman would need the help of two girls in order to complete the same job in the same amount of time. If one man and one girl worked together, it would take them four hours to build the wall. Assuming that rates for men, women and girls remain constant, how many hours would it take one woman, one man, and one girl, working together, to build the wall?

(A) 5/7
(B) 1
(C) 10/7
(D) 12/7
(E) 22/7

Kudos for a correct solution.

My 2 cents

Consider:
W = the rate for one woman
M = the rate for one man
G = the rate for one girl.

W + M =1/2
W + 2G=1/2
M + G = 1/4

Sum all equations above:

2W + 2M +3G =5/4

take 2 as common factor

2 (W+M+(3/2)G)= 5/4

W+ M+ 1.5G = 5/8.... so

Time taken= 8/5 = 1.6 BUT we need to 1G and we have more 0.5G. Henece we need number around it by decreasing 0.5G which implies that time will be little more than 1.6.

Let's scan answer Choices

Choices A & B is less than 1.6. Eliminate A &B

choice E is more than 2 hrs. Too big and should be logically less than 2 hrs when all of them (woman, man and girl) combined work together. Eliminate E

Choice C =10/7= 1 3/7 which means that it is less than 1.5, which is lower that 1.6

The only correct answer left

Answer: D
General Discussion
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,659
 [19]
8
Kudos
Add Kudos
11
Bookmarks
Bookmark this Post
Bunuel
One woman and one man can build a wall together in two hours, but the woman would need the help of two girls in order to complete the same job in the same amount of time. If one man and one girl worked together, it would take them four hours to build the wall. Assuming that rates for men, women and girls remain constant, how many hours would it take one woman, one man, and one girl, working together, to build the wall?

(A) 5/7
(B) 1
(C) 10/7
(D) 12/7
(E) 22/7

Kudos for a correct solution.

VERITAS PREP OFFICIAL SOLUTION:

This question is certainly quite tricky but if you understand the relation between work and rate, you can still solve this question easily. Mind you, we are using variables here only because I don’t want to write man, woman and girl again and again. Notice that there are no ‘=’ signs i.e. we are not making equations so we are not doing any algebraic manipulations.

The question is long so take one line at a time and analyze it. We will keep condensing the information we get from each sentence and figuring out the implications of new and previous information as we go along.

“One woman and one man can build a wall together in 2 hrs,”
1w + 1m -> 2 hrs ……(I)

“but the woman would need the help of 2 girls in order to complete the same job in the same amount of time.”
1w + 2g -> 2 hrs …..(II)

From (I) and (II), we can say that 1m is equivalent to 2g (i.e. 1 man does the same work as 2 girls do in the same amount of time; 1m ? 2g)

“If 1 man and 1 girl worked together, it would take them four hours to build the wall.”
1m + 1g -> 4hrs (Since 1m ? 2g, we can say that 3g will take 4 hrs to build the wall.)
or 2m + 2g -> 2 hrs …..(III) (If number of workers double, time taken to do the work becomes half)

From (II) and (III), 1w ? 2m (i.e. 1 woman does the same work as 2 men do in the same amount of time)
Hence, 1w ? 2m ? 4g

“Assuming that rates for women, men and girls remain constant, how many hours would it take 1 woman, 1 man and 1 girl working together to build the wall?”
1w + 1m + 1g ? 4g + 2g + 1g ? 7g. Since 3g take 4 hrs to build the wall, 7g will take 3*4/7 = 12/7 hrs to complete the wall.

Answer (D)
User avatar
OreoShake
Joined: 23 Jan 2016
Last visit: 31 Jan 2019
Posts: 136
Own Kudos:
82
 [3]
Given Kudos: 509
Location: India
GPA: 3.2
Posts: 136
Kudos: 82
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
can someone post a solution in 1/m, 1/2g form? I am finding it difficult to understand this. Thank you.
avatar
cbh
Joined: 24 Jun 2017
Last visit: 30 Sep 2019
Posts: 87
Own Kudos:
212
 [2]
Given Kudos: 130
Posts: 87
Kudos: 212
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A - man
B - woman
C - girl
Then piece of work done per hour
1. (a + b) = ½
2. (a+c) = ¼
3. (b+2c) = ½
b=½-a
a=¼ +c
For the third equation, (½-¼+c+2c)=½
¼+3c=½
3c=¼
c=1/12 so one girl's rate is 1/12
Then plug the value of c for others equation and we get a= ⅙ and b = ¼
Then ⅙+ ¼+1/12= 7/12 so get the entire work done then need to work 12/7 hours
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,974
Own Kudos:
8,710
 [17]
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,974
Kudos: 8,710
 [17]
9
Kudos
Add Kudos
8
Bookmarks
Bookmark this Post
Bunuel
One woman and one man can build a wall together in two hours, but the woman would need the help of two girls in order to complete the same job in the same amount of time. If one man and one girl worked together, it would take them four hours to build the wall. Assuming that rates for men, women and girls remain constant, how many hours would it take one woman, one man, and one girl, working together, to build the wall?

(A) 5/7
(B) 1
(C) 10/7
(D) 12/7
(E) 22/7

Kudos for a correct solution.

We can let m = the time is takes the man to build the wall, w = the time it takes the woman to build the wall, and g = the time it takes one girl to build the wall. Looking at the rates of these individuals, we see that one man’s rate is 1/m, one woman’s rate is 1/w, and 1 girl’s rate is 1/g. Thus:

1/m + 1/w = 1/2

and

1/w + 2/g = 1/2

and

1/m + 1/g = 1/4

From the first equation, let’s isolate 1/m:

1/m = 1/2 - 1/w

Let’s substitute this in the equation 1/m + 1/g = 1/4:

1/2 - 1/w + 1/g = 1/4

-1/w + 1/g = -1/4

Adding the equations 1/w + 2/g = 1/2 and -1/w + 1/g = -1/4 together, we obtain:

3/g = 1/4

g = 12

Since it takes a girl 12 hours to finish the job, her rate is 1/12. We are looking for 1/m + 1/w + 1/g; therefore, we add 1/12 to the equation 1/m + 1/w = 1/2:

1/m + 1/w + 1/g = 1/2 + 1/12

1/m + 1/w + 1/g = 7/12

Thus, it will take 1/(7/12) = 12/7 hours for a man, a woman, and a girl to build the wall, working together.

Alternate Solution:

Since the woman can finish the job in the same amount of time with the help of either one man or two girls, the rate of one man is equal to the rate of two girls.

Since one man and one girl can finish the job in 4 hours, and since the rate of one man is equal to the rate of two girls, three girls can finish the job in 4 hours. Since time is inversely proportional to the number of workers, one girl can finish the job in 12 hours.

Since one man and one woman finish the job in two hours, they complete 1/2 of the job in one hour. Since one girl can finish the job in 12 hours, one girl can complete 1/12 of the job in one hour. All working together, they finish 1/2 + 1/12 = 7/12 of the job in one hour. If 7/12 of the job gets done in one hour, then the entire job will get done in 1/(7/12) = 12/7 hours.

Answer: D
User avatar
hellosanthosh2k2
Joined: 02 Apr 2014
Last visit: 07 Dec 2020
Posts: 360
Own Kudos:
618
 [8]
Given Kudos: 1,227
Location: India
Schools: XLRI"20
GMAT 1: 700 Q50 V34
GPA: 3.5
Schools: XLRI"20
GMAT 1: 700 Q50 V34
Posts: 360
Kudos: 618
 [8]
6
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
M + W = 1/2 (men and women combined rate) ---------(1)
W + 2G = 1/2 (women and 2 girls combined rate) ------- (2)
M + G = 1/4 (men and girl combined rate) ------ (3)

-----(1) multiply by 2 and add with equations (2) and (3)
we get 3(M+W+G) = 1 + 1/2 + 1/4
M +W + G = 7/12
so M + W +G will take 12/7 days to the job
User avatar
danielarasan
Joined: 15 Sep 2017
Last visit: 22 Feb 2019
Posts: 19
Own Kudos:
18
 [4]
Given Kudos: 15
GMAT 1: 750 Q50 V42
GPA: 3.5
GMAT 1: 750 Q50 V42
Posts: 19
Kudos: 18
 [4]
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
1) W + M = 2h
2) W + 2G = 2h
3) M + G = 4h

From 2) - 1) we learn that M = 2G
In 3), M + G = 3G; 3G = 4h
If we double the number in 3), we know that 6G = 2h
From 1) we know that W + 2G = 2h; therefore, W = 4G

So if we transform all in G, we need 4G + 2G + G = 7 Girls!

If 3G = 4h, G = 12h.
7G = 12h/7 to finish the job!
User avatar
GMATGuruNY
Joined: 04 Aug 2010
Last visit: 02 Apr 2026
Posts: 1,347
Own Kudos:
3,904
 [1]
Given Kudos: 9
Schools:Dartmouth College
Expert
Expert reply
Posts: 1,347
Kudos: 3,904
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
One woman and one man can build a wall together in two hours, but the woman would need the help of two girls in order to complete the same job in the same amount of time. If one man and one girl worked together, it would take them four hours to build the wall. Assuming that rates for men, women and girls remain constant, how many hours would it take one woman, one man, and one girl, working together, to build the wall?

(A) 5/7
(B) 1
(C) 10/7
(D) 12/7
(E) 22/7

One woman and one man can build a wall together in two hours, but the woman would need the help of two girls in order to complete the same job in the same amount of time.
Since replacing 1 man with 2 girls does not change the amount of time required to complete the job, 1 man is the equivalent of 2 girls:
M = 2G.

Let G = 1 unit per hour, implying that M = 2 units per hour.

If one man and one girl worked together, it would take them four hours to build the wall.
Since M+G = 2+1 = 3 units per hour, the resulting wall produced in 4 hours = 3*4 = 12 units.

One woman and one man can build a wall together in two hours.
Since the 12-unit wall is built in 2 hours, we get:
W+M = 12/2 = 6 units per hour.
Since M = 2 units per hour, W = 4 units per hour.

How many hours would it take one woman, one man, and one girl, working together, to build the wall?
Since W+M+G = 4+2+1 = 7 units per hour, the time to build the 12-unit wall = 12/7 hours.

User avatar
fskilnik
Joined: 12 Oct 2010
Last visit: 03 Jan 2025
Posts: 883
Own Kudos:
1,880
 [1]
Given Kudos: 57
Status:GMATH founder
Expert
Expert reply
Posts: 883
Kudos: 1,880
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
My solution is in the image attached.
Attachments

23Ago18_11h.gif
23Ago18_11h.gif [ 40.9 KiB | Viewed 28067 times ]

avatar
hkkat
Joined: 07 Oct 2020
Last visit: 16 Jan 2021
Posts: 31
Own Kudos:
Given Kudos: 97
Posts: 31
Kudos: 20
Kudos
Add Kudos
Bookmarks
Bookmark this Post
danielarasan
1) W + M = 2h
2) W + 2G = 2h
3) M + G = 4h

From 2) - 1) we learn that M = 2G
In 3), M + G = 3G; 3G = 4h
If we double the number in 3), we know that 6G = 2h
From 1) we know that W + 2G = 2h; therefore, W = 4G

So if we transform all in G, we need 4G + 2G + G = 7 Girls!

If 3G = 4h, G = 12h.
7G = 12h/7 to finish the job!

May I know how did you come up with 12hr here?
I understood the well, but not this one.

TIA!
User avatar
chloee.11
Joined: 10 Sep 2021
Last visit: 05 Nov 2025
Posts: 5
Own Kudos:
Given Kudos: 146
Location: Viet Nam
Posts: 5
Kudos: 2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate of M,W, G are: rM, rW, rG
Work = 1 (1 wall)
1. rM + rW = 1/2
2. rM=2rG
3. rM + rG = 1/4

=> rG= 1/12
rM=1/6
rW=1/3

Time taken when W, M, G work together = work/ total rate = 1 / (1/3+1/6+1/12) = 12/7

=> Answer D
User avatar
sid_the_kid
Joined: 22 Oct 2023
Last visit: 02 Jan 2024
Posts: 1
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I solved this by three equations for three variables using substitution.
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,968
Own Kudos:
Posts: 38,968
Kudos: 1,117
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.

This post was generated automatically.
Moderators:
Math Expert
109754 posts
Tuck School Moderator
853 posts