Last visit was: 24 Apr 2026, 09:00 It is currently 24 Apr 2026, 09:00
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 24 Apr 2026
Posts: 109,814
Own Kudos:
811,028
 [1]
Given Kudos: 105,871
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,814
Kudos: 811,028
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Skywalker18
User avatar
Retired Moderator
Joined: 08 Dec 2013
Last visit: 15 Nov 2023
Posts: 1,973
Own Kudos:
10,169
 [1]
Given Kudos: 171
Status:Greatness begins beyond your comfort zone
Location: India
Concentration: General Management, Strategy
GPA: 3.2
WE:Information Technology (Consulting)
Products:
Posts: 1,973
Kudos: 10,169
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Abhishek009
User avatar
Board of Directors
Joined: 11 Jun 2011
Last visit: 17 Dec 2025
Posts: 5,903
Own Kudos:
5,454
 [1]
Given Kudos: 463
Status:QA & VA Forum Moderator
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Posts: 5,903
Kudos: 5,454
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Ram, who is half as efficient as Krish, will take 24 days to complete a task if he worked alone. If Ram and Krish worked together, how long will they take to complete the task?

A. 16 days
B. 12 days
C. 8 days
D. 6 days
E. 18 days

Let time taken by Krish be 12 days
So, Time taken by Ram will be 24 days

Let total work be 24

Thus, individual efficiencies of Ram and Krish are 1 unit/day & 2 Units / day

SO, Time taken to complete the work togather will be 24/3 = 8 days, Answer msut be (C)
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 24 Apr 2026
Posts: 22,283
Own Kudos:
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,283
Kudos: 26,534
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Ram, who is half as efficient as Krish, will take 24 days to complete a task if he worked alone. If Ram and Krish worked together, how long will they take to complete the task?

A. 16 days
B. 12 days
C. 8 days
D. 6 days
E. 18 days
Solution:

We see that Ram’s rate is 1/24, and since Krish is twice as efficient as Ram, Krish’s rate is 1/12. Therefore, their combined rate is 1/24 + 1/12 = 3/24 = 1/8. Since rate is the inverse of time, it will take them 1/(1/8) = 8 days to complete the task when they are working together.

Answer: C