It is currently 24 Feb 2018, 08:18

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

A certain tailor shop employs 10 workers who can normally complete an

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Intern
Intern
avatar
S
Joined: 12 Oct 2017
Posts: 39
CAT Tests
A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 29 Oct 2017, 20:42
13
This post was
BOOKMARKED
00:00
A
B
C
D
E

Difficulty:

  95% (hard)

Question Stats:

48% (03:06) correct 52% (02:56) wrong based on 126 sessions

HideShow timer Statistics

A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8
[Reveal] Spoiler: OA
3 KUDOS received
DS Forum Moderator
avatar
G
Joined: 21 Aug 2013
Posts: 805
Location: India
Premium Member CAT Tests
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 29 Oct 2017, 20:57
3
This post received
KUDOS
1
This post was
BOOKMARKED
Lets say 1 worker can do 1 unit of work in 1 day. So 10 worker can do 10 units daily, and in 112 days they can do 10*112 = 1120 units. So here we are assuming that the total work to be done is equivalent to 1120 units (with 10 units happening daily as there are 10 workers).

Because of power outages, instead of 61 days, we've had only 56 days worth of work done, which is 56*10 = 560 units.
Remaining work = 1120-560 = 560 units.

To complete this remaining work, company has hired 4 more workers, so now work done daily would be = 10+4 = 14 units.
Going by this, days required to complete = 560/14 = 40 more.

But days actually taken to complete remaining work = 104-61 = 43. That means there have been 3 more power outages.

Total outages = 5 (earlier) + 3 = 8. Hence E answer
Expert Post
1 KUDOS received
Target Test Prep Representative
User avatar
G
Status: Founder & CEO
Affiliations: Target Test Prep
Joined: 14 Oct 2015
Posts: 2192
Location: United States (CA)
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 31 Oct 2017, 15:18
1
This post received
KUDOS
Expert's post
2
This post was
BOOKMARKED
anhht13 wrote:
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8


The rate for the 10 workers is 1/112, so in the first 61 days, considering that they have had 5 power outrages, they complete 1/112 x 56 = 56/112 or 1/2 of the job.

Four new workers are hired, and they work at the same rate as the other workers. The original 10 workers worked at a rate of 1/112, and so the new crew of 14 individuals will work at a rate of n, which is calculated as follows:

10/(1/112) = 14/n

1120 = 14/n

1120n = 14

n = 14/1120 = 7/560 = 1/80

So, if there were no power outages, to complete the remaining half of the job, it would have taken (1/2)/(1/80) = 40 days, or a total of 101 days. However, since it took 104 day,s there must have been 3 additional power outages, bringing the total to 8 power outages.

Answer: E
_________________

Scott Woodbury-Stewart
Founder and CEO

GMAT Quant Self-Study Course
500+ lessons 3000+ practice problems 800+ HD solutions

Senior Manager
Senior Manager
User avatar
G
Joined: 22 Nov 2016
Posts: 251
Location: United States
Concentration: Leadership, Strategy
GPA: 3.4
Reviews Badge
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 10 Nov 2017, 10:22
Even if you are completely bowled over by this question, you are chance of guessing the right answer is 33.33%
The question stem already tells us that there were 5 outages. Hence, the answer is at least 5. Given the tone of the question, if you were to guess, the answer would be more than 5, either D or E.
_________________

Kudosity killed the cat but your kudos can save it.

Director
Director
avatar
G
Joined: 07 Dec 2014
Posts: 907
A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 10 Nov 2017, 12:52
anhht13 wrote:
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8


61 total days-5 outage days=56 work days
56 work days*10 workers*1/(10*112) daily rate per worker=1/2 order completed
104-61=43 total (work+outage) days remaining
let x=outage days remaining
(43-x) days*14 workers*1/(10*112) daily rate per worker=1/2 order remaining
x=3
3+5=8 total outages
E
Manager
Manager
avatar
B
Joined: 20 Feb 2017
Posts: 52
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 19 Nov 2017, 20:49
1
This post was
BOOKMARKED
total work-day units = 112 X 10 = 1120
In 61 days , there is loss of 5 days . So actual work done = 56 X 10 = 560 work-day units.
Remaining work = 1120-560= 560 work-day units
From 62nd day total worker strength is 14. The work is completed in another 104-61 = 43 days.
therefore the total work-units by these 14 workers = 14 X 43 = 602 work -day units. Our requirement is 560, hence there must be additional power cuts during this period.
Difference = 602- 560 = 42 work-day units.
therefore no of days of additional power cut = 42/14 = 3 days
total : 5 days + 3 days = 8 days (must be the answer)
Intern
Intern
avatar
B
Joined: 14 May 2017
Posts: 4
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 04 Dec 2017, 21:20
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8

===========
calculate total work:
total work done by 10 workers in 112 days = 10*112
Actual:
work done by 10 workers in 56 days (61-5(outage)) = 10*56

let number of outage days from 62nd day = x

no of days worked after 62nd day = 104-62+1 = 43

work done starting from 62nd day = 14 * (43-x)

10*112 = 10*56 + 14(43-x)

=> x =3

Total outage days = 3 + 5 = 8
Answer is E.
Director
Director
User avatar
P
Joined: 28 Mar 2017
Posts: 895
CAT Tests
Re: A certain tailor shop employs 10 workers who can normally complete an [#permalink]

Show Tags

New post 27 Dec 2017, 10:48
anhht13 wrote:
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8


Answer: E

10 people take 112 days
1 day work of 10 people=1/112
1 day work of 1 person = 1/1120

10 people work for 56 days first.
total work completed=10/1120 * 56 = 56/112
Remaining work = 1-56/112 = 56/112

14 people 1 day work = 14/1120
total days taken by 14 people to finish remaining work = (56/112)/(14/1120) = 56/112 * 1120/14 = 40

total days on which work actually happened = 40+56=96

work was eompleted in 104 days as per the question. So no work happened on 104-96=8 days
_________________

Kudos if my post helps!

Helpful links:
1. Useful Formulae, Concepts and Tricks-Quant
2. e-GMAT's ALL SC Compilation
3. LSAT RC compilation
4. Actual LSAT CR collection by Broal
5. QOTD RC (Carcass)
6. Challange OG RC

Re: A certain tailor shop employs 10 workers who can normally complete an   [#permalink] 27 Dec 2017, 10:48
Display posts from previous: Sort by

A certain tailor shop employs 10 workers who can normally complete an

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  


cron

GMAT Club MBA Forum Home| About| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.