Last visit was: 06 Sep 2026, 13:27 It is currently 06 Sep 2026, 13:27
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 06 Sep 2026
Posts: 113,166
Own Kudos:
Given Kudos: 111,337
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 113,166
Kudos: 839,562
 [19]
2
Kudos
Add Kudos
17
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
CrackverbalGMAT
User avatar
Major Poster
Joined: 03 Oct 2013
Last visit: 06 Sep 2026
Posts: 4,849
Own Kudos:
9,364
 [6]
Given Kudos: 230
Affiliations: CrackVerbal
Location: India
Expert
Expert reply
Posts: 4,849
Kudos: 9,364
 [6]
2
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
General Discussion
User avatar
ShankSouljaBoi
Joined: 21 Jun 2017
Last visit: 12 Aug 2026
Posts: 593
Own Kudos:
620
 [3]
Given Kudos: 4,089
Location: India
Concentration: Finance, Economics
GMAT 1: 660 Q49 V31
GMAT 2: 620 Q47 V30
GMAT 3: 650 Q48 V31
GPA: 3.1
WE:Corporate Finance (Non-Profit and Government)
Products:
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
ShankSouljaBoi
Joined: 21 Jun 2017
Last visit: 12 Aug 2026
Posts: 593
Own Kudos:
620
 [1]
Given Kudos: 4,089
Location: India
Concentration: Finance, Economics
GMAT 1: 660 Q49 V31
GMAT 2: 620 Q47 V30
GMAT 3: 650 Q48 V31
GPA: 3.1
WE:Corporate Finance (Non-Profit and Government)
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take?

(A) 8
(B) 9
(C) 10
(D) 12
(E) 13

Hi Bunuel, I feel the question is asking " how many days the work was completed after the rate of output was increased ". Hence, I went with B. Could you please point out the flaw in my approach?
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 06 Sep 2026
Posts: 113,166
Own Kudos:
839,562
 [1]
Given Kudos: 111,337
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 113,166
Kudos: 839,562
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
ShankSouljaBoi
Bunuel
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take?

(A) 8
(B) 9
(C) 10
(D) 12
(E) 13

Hi Bunuel, I feel the question is asking " how many days the work was completed after the rate of output was increased ". Hence, I went with B. Could you please point out the flaw in my approach?

Agree, the wording could have been better. Edited the question. Hope now it's better.
User avatar
MV94
User avatar
Current Student
Joined: 15 Aug 2020
Last visit: 15 Dec 2022
Posts: 53
Own Kudos:
84
 [2]
Given Kudos: 286
Location: United States (OR)
Concentration: Finance, Organizational Behavior
GMAT 1: 770 Q50 V46
GPA: 3.73
WE:Analyst (Mutual Funds and Brokerage)
GMAT 1: 770 Q50 V46
Posts: 53
Kudos: 84
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
This seems like an easy one to do trial and error with the answers:

A) 360/8 = 45 units per day
B) 360/9 = 40 units per day
C) 360/10 = 36 units per day
D) 360/12 = 30 units per day
E) 360/13 = 27ish or 28ish units per day

Notice the difference between B & C is 4 units per day, hence B must be the +4 unit rate and C must be the original rate, hence C is the answer. Good strategy for plugging answers is to start with C, so if you were lucky enough to start with C and go up this took very little math.
User avatar
LL132
Joined: 01 Nov 2024
Last visit: 12 Aug 2026
Posts: 13
Own Kudos:
Given Kudos: 27
Posts: 13
Kudos: 2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
in 360 units of work in X days
so i one day he does 360/x units of work

4 more pieces than planned=360/x+4 and this is completed in X-1 days

Work=Rate*time

360 units=(360/x+4)*(X-1)days

360=360x-360+(4x)2-4x

4x2-4x-360=0

x2-x-90=0

X=10,-9

therefore X=10 days -Option C
Bunuel
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. If the team were to make four more pieces per day than was planned, they would complete the job a day ahead of the schedule. How many days did the team take to complete the job at the original rate?

(A) 8
(B) 9
(C) 10
(D) 12
(E) 13
Moderator:
Math Expert
113166 posts