Last visit was: 24 Apr 2026, 15:45 It is currently 24 Apr 2026, 15:45
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 24 Apr 2026
Posts: 109,818
Own Kudos:
811,075
 [2]
Given Kudos: 105,873
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,818
Kudos: 811,075
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
Ertucinar
Joined: 16 Jul 2024
Last visit: 21 Apr 2026
Posts: 55
Own Kudos:
49
 [1]
Given Kudos: 15
Concentration: Entrepreneurship, Technology
Posts: 55
Kudos: 49
 [1]
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
AVMachine
Joined: 03 May 2024
Last visit: 26 Mar 2026
Posts: 190
Own Kudos:
Given Kudos: 40
Posts: 190
Kudos: 154
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
GMATinsight
User avatar
Major Poster
Joined: 08 Jul 2010
Last visit: 24 Apr 2026
Posts: 6,977
Own Kudos:
Given Kudos: 128
Status:GMAT/GRE Tutor l Admission Consultant l On-Demand Course creator
Location: India
GMAT: QUANT+DI EXPERT
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
WE:Education (Education)
Products:
Expert
Expert reply
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
Posts: 6,977
Kudos: 16,914
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
If five average workers in a workshop take 24 minutes to string 80 violins, how long will it take twelve average workers to string 720 violins?

A. 80 minutes
B. 90 minutes
C. 100 minutes
D. 120 minutes
E. 180 minutes


\(\frac{W}{M*T} = Constant\)

\(\frac{80}{5*24} = \frac{720}{12*T}\)

T = 90 minutes

Answer: Option B


Related CONCEPT Video:
User avatar
Dereno
Joined: 22 May 2020
Last visit: 24 Apr 2026
Posts: 1,398
Own Kudos:
Given Kudos: 425
Products:
Posts: 1,398
Kudos: 1,374
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
If five average workers in a workshop take 24 minutes to string 80 violins, how long will it take twelve average workers to string 720 violins?

A. 80 minutes
B. 90 minutes
C. 100 minutes
D. 120 minutes
E. 180 minutes


­

Total Work = man * days * hour (or) mins

Given: 80 violins = 5*24

720 = 12* t

80/720 = (5*24)/(12*t)

12*t = (5*24*720)/80

t = 90 mins

Option B