mysterymanrog
We can reason our way out of this one:
If the machine doubles each day, then so does the quantity of work done. This implies that, if the work was all done on day 11, then day 10 must be half of the work.
If day 10 is half of the work, then day 9 must have had 1/4 of the work done (1/4 times 2 is 1/2)
If day 9 had 1/4 of the work, then day 8 must have had 1/8 of the work done.
Day 8 is the correct choice, answer choice C.
Hi
The reasoning doesn't work here
Each day, the work done is doubled. However, the work done on any day is not equal to the cumulative work on all provious days combined
The work done series is: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512, 1024 (work on 11th day)
Cumulative work: 1, 3, 7, 15, 31, 63, 127, 255, 511, 1023 (total work in 10 days), 2047 (total work in 11 days) -
Observe that work on the 11th day is not equal to the work done in 10 days; hence 1023 is not half the total workNote: The logic could have worked if the work done series was 1, 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (work on 11th day)
Cumulative work: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (total work in 10 days), 1024 (total work in 11 days) - Observe that work on the 11th day is now equal to the work done in 10 days
The answer should be
Day 9