Last visit was: 10 Jul 2025, 03:44 It is currently 10 Jul 2025, 03:44
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 10 July 2025
Posts: 102,612
Own Kudos:
Given Kudos: 98,069
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 102,612
Kudos: 740,006
 [15]
Kudos
Add Kudos
15
Bookmarks
Bookmark this Post
User avatar
MartyMurray
Joined: 11 Aug 2023
Last visit: 09 Jul 2025
Posts: 1,527
Own Kudos:
4,993
 [1]
Given Kudos: 149
GMAT 1: 800 Q51 V51
Expert
Expert reply
GMAT 1: 800 Q51 V51
Posts: 1,527
Kudos: 4,993
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
gmatophobia
User avatar
Quant Chat Moderator
Joined: 22 Dec 2016
Last visit: 09 Jul 2025
Posts: 3,149
Own Kudos:
8,946
 [3]
Given Kudos: 1,860
Location: India
Concentration: Strategy, Leadership
Products:
Posts: 3,149
Kudos: 8,946
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
mysterymanrog
User avatar
CR Forum Moderator
Joined: 25 Jan 2022
Last visit: 13 Jun 2025
Posts: 799
Own Kudos:
692
 [2]
Given Kudos: 559
Location: Italy
GPA: 3.8
Posts: 799
Kudos: 692
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
We can reason our way out of this one:

If the machine doubles each day, then so does the quantity of work done. This implies that, if the work was all done on day 11, then day 10 must be half of the work.

If day 10 is half of the work, then day 9 must have had 1/4 of the work done (1/4 times 2 is 1/2)
If day 9 had 1/4 of the work, then day 8 must have had 1/8 of the work done.

Day 8 is the correct choice, answer choice C.
User avatar
Adarsh_24
Joined: 06 Jan 2024
Last visit: 03 Apr 2025
Posts: 263
Own Kudos:
Given Kudos: 2,016
Posts: 263
Kudos: 44
Kudos
Add Kudos
Bookmarks
Bookmark this Post
mysterymanrog
We can reason our way out of this one:

If the machine doubles each day, then so does the quantity of work done. This implies that, if the work was all done on day 11, then day 10 must be half of the work.

If day 10 is half of the work, then day 9 must have had 1/4 of the work done (1/4 times 2 is 1/2)
If day 9 had 1/4 of the work, then day 8 must have had 1/8 of the work done.

Day 8 is the correct choice, answer choice C.
Is the high-lighted part really true?

If the first day had "x" amount of work, it will be x,2x,4x,8x,...,512x,1024x
Total work would be 2047x , while on 10th day the work completed is 512x.
User avatar
sujoykrdatta
Joined: 26 Jun 2014
Last visit: 10 Jul 2025
Posts: 539
Own Kudos:
Given Kudos: 13
Status:Mentor & Coach | GMAT Q51 | CAT 99.98
Expert
Expert reply
Posts: 539
Kudos: 1,038
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
In a factory, the number of identical machines working on a task doubles daily. If the task was completed in 11 days, by the end of which day was 1/8 of the task completed?

A. Day 6
B. Day 7
C. Day 8
D. Day 9
E. Day 10
All machines have the same efficiency. Assuming the efficiency as 1 unit per day, the number of units of work done on successive days are: 1 (day 1), 2 (day 2) , 4 (day 3) , 8 (day 4) , 16 (day 5) and so on
Total units of work in 11 days = 1 + 2 + 4 + ... 10^10 = 10^11 - 1 = 2047
One-eighth of the total = 1/8 * 2047 = 255 + 7/8
Cumulative units of work done in successive days:
Day 1 = 1
Day 2 = 1+2 = 3
Day 3 = 1+2+4 = 3+4 = 7
Day 4 = 7+8 = 15
Day 5 = 15+16 = 31
Day 6 = 31+32 = 63
Day 7 = 63+64 = 127
Day 8 = 127+128 = 255 - this is still short
Thus, the required answer is Day 9

Ans D
User avatar
sujoykrdatta
Joined: 26 Jun 2014
Last visit: 10 Jul 2025
Posts: 539
Own Kudos:
Given Kudos: 13
Status:Mentor & Coach | GMAT Q51 | CAT 99.98
Expert
Expert reply
Posts: 539
Kudos: 1,038
Kudos
Add Kudos
Bookmarks
Bookmark this Post
gmatophobia
Bunuel
In a factory, the number of identical machines working on a task doubles daily. If the task was completed in 11 days, by the end of which day was 1/8 of the task completed?

A. Day 6
B. Day 7
C. Day 8
D. Day 9
E. Day 10

1/8th of 100 = 12.5%

If 100% of the task was completed on Day 11 ➔ 50% of the task was completed on Day 10 ➔ 25% of the task was completed on Day 9 ➔ and 12.5% of the task was completed on Day 8.

Hence, \(\frac{1}{8}\)th of the task was completed on Day 8.

Option C
Hi
The reasoning doesn't work here
Each day, the work done is doubled. However, the work done on any day is not equal to the cumulative work on all provious days combined

The work done series is: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512, 1024 (work on 11th day)
Cumulative work: 1, 3, 7, 15, 31, 63, 127, 255, 511, 1023 (total work in 10 days), 2047 (total work in 11 days) - Observe that work on the 11th day is not equal to the work done in 10 days; hence 1023 is not half the total work

Note: The logic could have worked if the work done series was 1, 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (work on 11th day)
Cumulative work: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (total work in 10 days), 1024 (total work in 11 days) - Observe that work on the 11th day is now equal to the work done in 10 days


The answer should be Day 9
User avatar
sujoykrdatta
Joined: 26 Jun 2014
Last visit: 10 Jul 2025
Posts: 539
Own Kudos:
1,038
 [1]
Given Kudos: 13
Status:Mentor & Coach | GMAT Q51 | CAT 99.98
Expert
Expert reply
Posts: 539
Kudos: 1,038
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
mysterymanrog
We can reason our way out of this one:

If the machine doubles each day, then so does the quantity of work done. This implies that, if the work was all done on day 11, then day 10 must be half of the work.

If day 10 is half of the work, then day 9 must have had 1/4 of the work done (1/4 times 2 is 1/2)
If day 9 had 1/4 of the work, then day 8 must have had 1/8 of the work done.

Day 8 is the correct choice, answer choice C.
Hi
The reasoning doesn't work here
Each day, the work done is doubled. However, the work done on any day is not equal to the cumulative work on all provious days combined

The work done series is: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512, 1024 (work on 11th day)
Cumulative work: 1, 3, 7, 15, 31, 63, 127, 255, 511, 1023 (total work in 10 days), 2047 (total work in 11 days) - Observe that work on the 11th day is not equal to the work done in 10 days; hence 1023 is not half the total work

Note: The logic could have worked if the work done series was 1, 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (work on 11th day)
Cumulative work: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512 (total work in 10 days), 1024 (total work in 11 days) - Observe that work on the 11th day is now equal to the work done in 10 days


The answer should be Day 9
User avatar
sujoykrdatta
Joined: 26 Jun 2014
Last visit: 10 Jul 2025
Posts: 539
Own Kudos:
Given Kudos: 13
Status:Mentor & Coach | GMAT Q51 | CAT 99.98
Expert
Expert reply
Posts: 539
Kudos: 1,038
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
In a factory, the number of identical machines working on a task doubles daily. If the task was completed in 11 days, by the end of which day was 1/8 of the task completed?

A. Day 6
B. Day 7
C. Day 8
D. Day 9
E. Day 10
Bunuel
Please check the answer - it should be Day 9 (Option D)
User avatar
MartyMurray
Joined: 11 Aug 2023
Last visit: 09 Jul 2025
Posts: 1,527
Own Kudos:
4,993
 [1]
Given Kudos: 149
GMAT 1: 800 Q51 V51
Expert
Expert reply
GMAT 1: 800 Q51 V51
Posts: 1,527
Kudos: 4,993
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Adarsh_24
mysterymanrog
We can reason our way out of this one:

If the machine doubles each day, then so does the quantity of work done. This implies that, if the work was all done on day 11, then day 10 must be half of the work.

If day 10 is half of the work, then day 9 must have had 1/4 of the work done (1/4 times 2 is 1/2)
If day 9 had 1/4 of the work, then day 8 must have had 1/8 of the work done.

Day 8 is the correct choice, answer choice C.
Is the high-lighted part really true?

If the first day had "x" amount of work, it will be x,2x,4x,8x,...,512x,1024x
Total work would be 2047x , while on 10th day the work completed is 512x.
It's not true.

The correct answer is (D), not (C).
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 10 July 2025
Posts: 102,612
Own Kudos:
Given Kudos: 98,069
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 102,612
Kudos: 740,006
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Fixed the OA. Thank you!
User avatar
Sandeepgurwa
Joined: 11 Nov 2024
Last visit: 09 Jul 2025
Posts: 4
Own Kudos:
Given Kudos: 17
Posts: 4
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The work done series is: 1, 2, 4, 8, 16, 32, 64, 128, 256, 512, 1024 (work on 11th day)
Cumulative work: 1, 3, 7, 15, 31, 63, 127, 255, 511, 1023 (total work in 10 days), 2047 (total work in 11 days) - Observe that work on the 11th day is not equal to the work done in 10 days; hence 1023 is not half the total work.
Therfore, total work is 2047 in total.
To know percentage completion eaxh day:
Day 1. 1/2047 = 0.0488%
Day 2. 3/2047 = 0.146%
Day 3. 7/2047 = 0.342%
Day 4. 15/2047 = 0.732%
Day 5. 31/2047 = 1.51%
Day 6. 63/2047 = 3.07%
Day 7. 127/2047 = 6.2%
Day 8. 255/2047 = 12.457%
Day 9. 511/2047 = 24.96%
Day 10. 1023/2047 = 49.97%
Day 11. 2047/2047 = 100%

On the compeletion of Day 8 Total work done is slightly less than 1/8th of the total work. Therefore, we are choosing day 9 as a answer.
Moderators:
Math Expert
102612 posts
PS Forum Moderator
683 posts