For me, easiest way to do work/ rate problems is by taking the LCM or multiple of all the given numbers in a question and assume it to be total number of units of work to be done. This eliminates the chances of making error while doing calculation with fractions.
In this question, we are given 3 numbers, 10, 3 and 4. Let's say total units of work to be done is 60 (60 is a multiple of 10, 3 and 4).
Mr. Verma will do 6 units per day (Mr Verma's rate of work) to do the given task in 10 days.
He works for 3 days alone so he'll do 18 units of work. Then helper joins. Work to be done is 60-18 = 42 units.
Both complete the remaining job in 4 days so combined rate is 10.5 units per day.
Work rate of helper will be, 10-5-6 = 4.5 units per day.
At this rate if worker has to do 60 units of work alone, he'll take 60/4.5 = 40/3 days or 13 1/3 days.
Option E is correct.