Because of the structure of the question, we can devise a shortcut to solving this problem – one that takes only a few seconds - by employing a bit of logic:
In solving questions like this we have to fix a minimum or a maximum time for the value to be determined (in this case, the time that all four will take to complete the job). In this particular case, however, we can only fix a minimum time because there is no maximum limit set: A & C could take a 100 or even a million hours to complete the job. It follows that when A, B, C and D all work together there is no maximum time limit and we can only fix a minimum value since there is a fixed relationship between the times that each take to finish the job while working alone.
It stands to reason that the minimum time in which A, B, C and D can complete the work must lie between the highest value (E) and the second highest value (D) thus making E the only possible answer because, if the minimum time is less (i.e. between any two of the lesser answer choices), all the answer choices which are more than the minimum time become possible. For example, if the minimum time is 50 minutes (i.e. between B and C), that would make C, D and E all possible but the question allows for only one correct answer. If the minimum time was more than 79 minutes (E) then the correct answer would have been "None" which is not among the answer choices. So the correct answer can only be E. On the other hand, if the minimum time is less than (A), all the options (A) through (E) could be possible and the correct answer would be "All" which is also not among the given options.
This shortcut could be prevented by changing the structure of the question to allow for more than one correct answer (e.g. D and E, A only, E only, all five, none, etc.).