Last visit was: 27 Apr 2024, 13:45 It is currently 27 Apr 2024, 13:45

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
e-GMAT Representative
Joined: 04 Jan 2015
Posts: 3724
Own Kudos [?]: 16861 [32]
Given Kudos: 165
Send PM
Most Helpful Reply
RC & DI Moderator
Joined: 02 Aug 2009
Status:Math and DI Expert
Posts: 11182
Own Kudos [?]: 31992 [6]
Given Kudos: 291
Send PM
General Discussion
User avatar
Intern
Intern
Joined: 29 Oct 2013
Posts: 16
Own Kudos [?]: 49 [0]
Given Kudos: 12
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 18 Aug 2017
Status:You learn more from failure than from success.
Posts: 8021
Own Kudos [?]: 4099 [1]
Given Kudos: 242
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1:
545 Q79 V79 DI73
GPA: 4
WE:Marketing (Energy and Utilities)
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
1
Bookmarks
given a,b,c,d are consective integers
so a=x ,b=x+1, c= x+2, d= x+3
also given
1/a + 1/c>1/2
use hit and trial to see at which value of x we get 1/a + 1/c>1/2
only at a=4 and c=6 we get >1/2
so a=4,b=5,c=6,d=7
working together
1/4+1/5+1/6+1/7 = 5*6*7+4*6*7+4*5*7+4*5*6/ (4*5*6*7 )
solve we get
638/840 ; time 840*60/638 = ~79 mins
IMO E

EgmatQuantExpert wrote:
e-GMAT Question of the Week #43


While working individually, each of A, B, C and D can produce 60 units of a certain item in a, b, c and d hours respectively, where a, b, c, d are consecutive integers in increasing order. If A and C together can produce 60 units in more than 2 hours, then which of the following cannot be the time they will take to produce 60 units, if all are working together?

    A. 28.2 minutes
    B. 46.75 minutes
    C. 60 minutes
    D. 63.15 minutes
    E. 79 minutes

Current Student
Joined: 23 Mar 2013
Posts: 28
Own Kudos [?]: 7 [2]
Given Kudos: 30
Location: United States
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
1
Kudos
1
Bookmarks
a + c > 2 and a<b<c<d,
means, a will take at least 4 hours to complete the work
in an hour, units of work completed,

for A, 60*1/4 = 15
B, 60*1/5 = 12
C, 60*1/6=10
D, 60*1/7 ~ 8

Total work = 15+12+10+8 = 45
remaining work= 60-45= 15 which 4th of total, so would need additional 4th of an hour, i.e. 15mins,

in all the minimum time would be greater than, 60 + 15 = 75, the only answer which is greater than 75, is E

Originally posted by vijay282001 on 12 Apr 2019, 18:56.
Last edited by vijay282001 on 13 Apr 2019, 05:08, edited 1 time in total.
Senior PS Moderator
Joined: 26 Feb 2016
Posts: 2873
Own Kudos [?]: 5206 [1]
Given Kudos: 47
Location: India
GPA: 3.12
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
1
Kudos
EgmatQuantExpert wrote:
While working individually, each of A, B, C and D can produce 60 units of a certain item in a, b, c and d hours respectively, where a, b, c, d are consecutive integers in increasing order. If A and C together can produce 60 units in more than 2 hours, then which of the following cannot be the time they will take to produce 60 units, if all are working together?

    A. 28.2 minutes
    B. 46.75 minutes
    C. 60 minutes
    D. 63.15 minutes
    E. 79 minutes



For work to complete in 2 hours or less, A and C must complete half the work in an hour. The combined rate
of work of A and C cannot be greater than 30 units in an hour. B and D will complete more than 30 units/hr.
With increasing time, the rate at which they individually complete the work decreases.

Let us assume that A completes the work at 15 units/hr. A will take 4 hours (\(\frac{60}{15} = 4\))

Since the time at which they individually complete work is in consecutive order,
B will take 5 hours and the work done by A in an hour is \(\frac{60}{5} = 12\) units.
C will take 6 hours and the work done by A in an hour is \(\frac{60}{6} = 10\) units.
D will take 7 hours and the work done by A in an hour is \(\frac{60}{7} = 8.5\) units. (approximately)
In an hour, they will complete a total of \(15 + 12 + 10 + 8.5 = 45.5\) units.

Therefore, the time take to complete the work is \(\frac{60}{45.5} = 1.32\) hours (or) 79 minutes(Option E)
Manager
Manager
Joined: 09 Nov 2015
Posts: 202
Own Kudos [?]: 320 [0]
Given Kudos: 96
Send PM
Question of the Week - 43 (While working individually, each of A, B) [#permalink]
Because of the structure of the question, we can devise a shortcut to solving this problem – one that takes only a few seconds - by employing a bit of logic:

In solving questions like this we have to fix a minimum or a maximum time for the value to be determined (in this case, the time that all four will take to complete the job). In this particular case, however, we can only fix a minimum time because there is no maximum limit set: A & C could take a 100 or even a million hours to complete the job. It follows that when A, B, C and D all work together there is no maximum time limit and we can only fix a minimum value since there is a fixed relationship between the times that each take to finish the job while working alone.
It stands to reason that the minimum time in which A, B, C and D can complete the work must lie between the highest value (E) and the second highest value (D) thus making E the only possible answer because, if the minimum time is less (i.e. between any two of the lesser answer choices), all the answer choices which are more than the minimum time become possible. For example, if the minimum time is 50 minutes (i.e. between B and C), that would make C, D and E all possible but the question allows for only one correct answer. If the minimum time was more than 79 minutes (E) then the correct answer would have been "None" which is not among the answer choices. So the correct answer can only be E. On the other hand, if the minimum time is less than (A), all the options (A) through (E) could be possible and the correct answer would be "All" which is also not among the given options.
This shortcut could be prevented by changing the structure of the question to allow for more than one correct answer (e.g. D and E, A only, E only, all five, none, etc.).

Originally posted by effatara on 18 Apr 2019, 02:17.
Last edited by effatara on 22 Apr 2019, 01:16, edited 2 times in total.
avatar
Intern
Intern
Joined: 05 Feb 2014
Posts: 9
Own Kudos [?]: [0]
Given Kudos: 0
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
Hi everyone,

I'm a bit confused and I was hoping to get some clarification on this.

I see an answer that states:
(1/a + a/c) > 1/2
Why does a has to be at least 4? If a were to be 1, (1/1 + 1/3) is indeed greater than 1/2.

Another answer states the opposite:
(1/a + 1/c) < 1/2
In this case, I do understand that a must be at least 4, but why are we posing (1/a + 1/c) less than 1/2 when we know that it takes a+c at least 2 hours to build 60 units?

Thanks so much for helping!
Mike
Manager
Manager
Joined: 26 Oct 2021
Posts: 117
Own Kudos [?]: 27 [0]
Given Kudos: 95
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
Hi,

let w,x,y,z be the respective work rates with x=a+1, y=a+2,..., we get from the text:

60/(w+y)>2
30>w+y, because w=60/a and y=60/(a+2) we get
30>60/a+60/(a+2), expanding RHS
30>(120a+120)/(a^2+2a)
30a^2+60a>120a+120, dividing by 30
a^2+2a>4a+4
a^2-2a>4
a(a-2)>4

a is an integer -> a>=4 -> the least possible work rates are w=60/4, x=60/5, ..., so the least time in hours they require to get the job done is given by:

60/(w+x+y+z)=420/319

-> 60*420/319=78.99min -> (E)
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32714
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: Question of the Week - 43 (While working individually, each of A, B) [#permalink]
Moderators:
Math Expert
92959 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne