Last visit was: 20 Apr 2026, 22:40 It is currently 20 Apr 2026, 22:40
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 20 Apr 2026
Posts: 109,715
Own Kudos:
Given Kudos: 105,795
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,715
Kudos: 810,309
 [20]
6
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 20 Apr 2026
Posts: 109,715
Own Kudos:
810,309
 [4]
Given Kudos: 105,795
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,715
Kudos: 810,309
 [4]
2
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
User avatar
paragw
Joined: 17 May 2024
Last visit: 16 Apr 2026
Posts: 189
Own Kudos:
193
 [2]
Given Kudos: 38
Posts: 189
Kudos: 193
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
luisdicampo
Joined: 10 Feb 2025
Last visit: 19 Apr 2026
Posts: 480
Own Kudos:
Given Kudos: 328
Products:
Posts: 480
Kudos: 73
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
Deconstructing the Question
We have 4 workers with individual rates to complete a task.
Task completion times:
Alex (A): 8 hours
Beth (B): 20 hours
Charles (C): 40 hours
Dana (D): 80 hours

The work is done in a repeating 4-person cycle (1 hour each).
Goal: Find the Minimum and Maximum total hours to complete the task.

Step 1: Calculate Hourly Work Units
Let the Total Work be the LCM of (8, 20, 40, 80) = 80 units.
Efficiencies (units per hour):

\(R_A = 80/8 = 10\) units/hr

\(R_B = 80/20 = 4\) units/hr

\(R_C = 80/40 = 2\) units/hr

\(R_D = 80/80 = 1\) unit/hr

Step 2: Analyze Full Cycles

One full cycle consists of 4 hours (one hour per person).
Work done in 1 cycle = \(10 + 4 + 2 + 1 = 17\) units.
Total work needed: 80 units. Number of full cycles = \(80 / 17 \approx 4.7\).

So, we have 4 full cycles.

Time elapsed: \(4 \times 4 = 16\) hours.
Work completed: \(4 \times 17 = 68\) units.
Remaining Work: \(80 - 68 = 12\) units.

Step 3: Calculate Minimum Time
To minimize time, the fastest workers must perform the remaining work first.
Sequence: A \(\rightarrow\) B \(\rightarrow\) C \(\rightarrow\) D.
Remaining: 12 units.
Hour 17 (A works): Completes 10 units. (Remaining: \(12 - 10 = 2\)).
Hour 18 (B works): Rate is 4 units/hr. Needs to complete 2 units.

Time taken = \(2 / 4 = 0.5\) hours.

Total Min Time = \(16 + 1 + 0.5 = 17.5\) hours.

Step 4: Calculate Maximum Time
To maximize time, the slowest workers must perform the remaining work first.
Sequence: D \(\rightarrow\) C \(\rightarrow\) B \(\rightarrow\) A.
Remaining: 12 units.
Hour 17 (D works): Completes 1 unit. (Remaining: 11).
Hour 18 (C works): Completes 2 units. (Remaining: 9).
Hour 19 (B works): Completes 4 units. (Remaining: 5).
Hour 20 (A works): Rate is 10 units/hr. Needs to complete 5 units.

Time taken = \(5 / 10 = 0.5\) hours.

Total Max Time = \(16 + 1 + 1 + 1 + 0.5 = 19.5\) hours.

Answer Selection:
Minimum: 17.5
Maximum: 19.5
User avatar
laborumplaceat
Joined: 06 Dec 2025
Last visit: 19 Apr 2026
Posts: 124
Own Kudos:
63
 [2]
Given Kudos: 3
Products:
Posts: 124
Kudos: 63
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let rate of:
A = 10
B = 4
C = 2
D = 1

Total work = 80
In 4 hours: 68 units of work done.

Additional time for maximum time:
D works -> 1 unit in 1 hour
then C works -> 2 units in 1 hour
then B works -> 4 units in 1 hour
then A works -> 5 unit in 0.5 hour - So total max time = 19.5 hours

Additional time for minimum time:
A works -> 10 units in 1 hour
then B works -> 2 units in 0.5 hour
So minimum total time = 17.5 hours
User avatar
sitrem
Joined: 19 Nov 2025
Last visit: 24 Feb 2026
Posts: 91
Own Kudos:
84
 [1]
Given Kudos: 238
Posts: 91
Kudos: 84
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate of each worker (fraction of the total work done in 1h)
To make calculations easier assume that the work consists of 80 units (lcm of 8,20,40,80)
A 10 units each hour = 80 / 8 h
B 4
C 2
D 1

To finish in the minimum time, put the workers in order of speed (from fastest to slowest -> A, B, C, D).
In each cycle they make 10+4+2+1=17 units of work.
They will need 4 full cycles to get to 68, each cycle is 4 hours.
To get to 80, A works 1h and does 10 units and B works for half an hour to do the remaining 2.
68 units in 16 h (4 cycles) + 10 in 1 h + 2 in 0.5 h = 80 in 17.5 h

To finish in the maximum time use the opposite order (slowest to fastest).
They will still do 4 full cycles to get to 68 units in 16h.
Then D does 1 unit in 1h, C does 2 in 1h, B does 4 in 1h, A does the remaining 5 in half an hour.
68 units in 16h + 1 in 1h + 2 in 1h + 4 in 1h + 5 in 0.5h = 80 in 19.5h

Minimum 17.5
Maximum 19.5
User avatar
JiriNovacek
Joined: 14 Dec 2025
Last visit: 07 Feb 2026
Posts: 17
Own Kudos:
9
 [1]
Posts: 17
Kudos: 9
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Minimum is 17,5 hours, the fastest worker begins (Alex, 8 hours), he does in the first cycle in the hour 1/8 of the work, then works Beth (1/20 of work during one hour), etc. In the sum, they can do 17/80 per cycle of the work. It means 4 cycles (16hours) and 0.15 of the work still remains. Alex makes pro hour as the firs worker of the 5.cycle 0.125 of the work (1/8) and Beth 0,025 of the remaining work do for 0.5 hour (so overall minimum 17.5 hours)

Maximum:19.5 hours
remaining rest of the work after 4 cycles (16 hours) is again 0.15 (15%). But this time the Dana begins (as the slowest worker). Then the same logic as above.
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 20 Apr 2026
Posts: 5,985
Own Kudos:
5,855
 [1]
Given Kudos: 163
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,985
Kudos: 5,855
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The fraction of the work done by Alex, Beth, Charles & Dana in an hour is 1/8, 1/20, 1/40 & 1/80 respectively.

For minimum number of hours, we assign the work to most productive workers first.

Hour 1: Alex : Work done = 1/8 = 12.5%
Hour 2: Beth : Work done = 1/20 = 5% : Cumulative work done = 1/8 + 1/20 = 17.5%
Hour 3: Charles: Work done = 1/40 = 2.5%: Cumulative work done = 17.5% + 2.5% = 20%
Hour 4: Dana: Work done = 1/80 = 1.25%: Cumulative work done = 21.25%
Hours 5-8: Cumulative work done = 21.25% + 21.25% = 42.5%
Hours 9-12: Cumulative work done = 42.5% + 21.25% = 63.75%
Hours 13-16: Cumulative work done = 63.75% + 21.25% = 85%
Hour 17: Alex : Work done = 1/8 = 12.5% : Cumulative work done = 85% + 12.5% = 97.5%
Remaining work = 100% - 97.5% = 2.5%
Beth can do the remaining work in 2.5%/5% = .5 hours

Minimum hours required for the task to be completed = 17.5 hours

For maximum number of hours, we assign the work to the least productive workers first.

Hours 1-4: Cumulative work done = 21.25%
Hours 5-8: Cumulative work done = 42.5%
Hours 9-12: Cumulative work done = 63.75%
Hours 13-16: Cumulative work done = 85%
Hour 17: Dana: Work done = 1/80 = 1.25%: Cumulative work done = 85% + 1.25% = 86.25%
Hour 18: Charles: Work done = 1/40 = 2.5%: Cumulative work done = 86.25% + 2.5% = 88.75%
Hour 19: Beth : Work done = 1/20 = 5%: Cumulative work done = 88.75% +5% = 93.75%
Remaining work = 100% - 93.75% = 6.25%
Time taken by Alex to complete the task = 6.25%/12.5% = .5 Hours

Maximum number of hours to complete the task = 19.5 hours

Minimum 17.5
Maximum19.5
User avatar
Archit3110
User avatar
Major Poster
Joined: 18 Aug 2017
Last visit: 20 Apr 2026
Posts: 8,625
Own Kudos:
5,190
 [1]
Given Kudos: 243
Status:You learn more from failure than from success.
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1: 545 Q79 V79 DI73
GMAT Focus 2: 645 Q83 V82 DI81
GPA: 4
WE:Marketing (Energy)
Products:
GMAT Focus 2: 645 Q83 V82 DI81
Posts: 8,625
Kudos: 5,190
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.

Rate of A 1/8
B 1/20
c 1/40
d 1/80
net rate
1/8 +1/20 + 1/40+ 1/80 = 10+4+2+1 /80 = 17/80

4 person cycle repeating , 1 hour each
4 * 17/ 80 = 17/20
work left 1-17/20 = 3/20
this way work gets done in 17.5 hours
maximum time will be when work is done in order of DCBA ; work done in full hours by DCB and A completes half work
19.5hours
17.5 ; 19.5
avatar
ManifestDreamMBA
Joined: 17 Sep 2024
Last visit: 21 Feb 2026
Posts: 1,387
Own Kudos:
897
 [1]
Given Kudos: 243
Posts: 1,387
Kudos: 897
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Since they work in 4 person cycle, every 4 hours, they complete
1/8 +1/20+1/40+1/80 = 17/80

To reach 100%, they will need to run 80/17 = 4 complete cycles and 1 partial cycle = So time required = 4*4 = 16 + time for partial cycle

Work remaining after 4 cycles = 1 - 4*17/80 = 1 - 68/80 = 1 - 17/20 = 3/20

To minimise time, we start with fastest person
Speed A>B>C>D
Contribution
A: Rate * Time = 1/8 * 1
Remaining = 3/20 - 1/8 = 1/40

Note 1/40 <1/20, so whole hour is not required
B: Rate * Time = 1/20 * t
1/40 = 1/20 * t => t = 0.5

Min time = 16 + 1 + 0.5 = 17.5

To maximise time, we start with slowest person
Contriution
D: rate * Time = 1/80 * 1
Remaining = 3/20 - 1/80 = 11/80

C = rate * time = 1/40 * 1
Remaining = 11/80 - 1/40 = 9/80

B = rate * Time = 1/20 * 1
Remaining = 9/80 - 1/20 = 5/80

Note 5/80 < 1/8, so whole hour is not required
A = rate * time = 1/8 * t = 5/80
t=0.5
Max time = 16 + 1 + 1 + 1 + 0.5 = 19.5


Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
Ayeka
Joined: 26 May 2024
Last visit: 18 Apr 2026
Posts: 528
Own Kudos:
402
 [1]
Given Kudos: 158
Location: India
Schools: ISB
GMAT Focus 1: 645 Q82 V83 DI80
GPA: 4.2
Schools: ISB
GMAT Focus 1: 645 Q82 V83 DI80
Posts: 528
Kudos: 402
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A= 8 hrs
B= 20 hrs
C= 40 hrs
D= 80 hrs
Work done in first 4 hours regardless of order = (1/8)+(1/20)+(1/40)+(1/80)=(10+4+2+1)/80=17/80;
Work don in 8 hours = 2*(17/80)=34/80
Work done in 12 hours = 3*(17/80) =51/80
Work done in 16 hours =4*(17/80)=68/80
Remaining work to be done =1-(68/80)=12/80

In order to minimize the time taken to complete the task, the fastest person (Alex and Beth) will do the work ahead in the 4 hour cycle.
Hour 17, Alex works at (1/8) rate.
Work remaining after Alex shift = (12/80)-(10/80)=2/80
Hour 18, Beth works at (1/20) rate. Beth rate is (1/20) or (4/80), it means she will finish the job before the hour ends.
Time taken by Beth = (2/80)/(4/80)=0.5 hours
Minimum time taken to complete the task = 16+1+0.5=17.5 hours.

In order to maximize the time, slowest persons (Dana and Charles) will work ahead in the cycle.
Hour 17, Dana works (1/80) rate
Work remainjng after Dana shift = (12/80)-(1/80) =11/80
Hour 18, Charles works at (2/80) rate and remaining work after his shift = (11/80)-(2/80)=9/80
Hour 19, Beth works at (4/80) rate and remaining work after his shift = (9/80)-(4/80)=(5/80)
Hour 20, Alex works at (1/8) rate and time he needs to complete the remaining task =(5/80)/(1/8)=0.5 hours
Maximum time taken to complete the task =16+1+1+1+0.5=19.5 hours

Minimum =17.5 and Maximum =19.5
User avatar
Chaithanya20
Joined: 15 Dec 2025
Last visit: 26 Dec 2025
Posts: 14
Own Kudos:
12
 [1]
Given Kudos: 1
Posts: 14
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In one 4 hour cycle,
1/8+1/20+1/40+1/80 = (10+4+2+1)/80 = 17/80
After 4 cycles , time = 16 hrs
work = 68/80
Remaining = 12/80
For minimum, Alex starts to work, => 10/80 done in one hr and the rest by Beth at 2/80 in 0.5 hr => Minimum time = 17.5 hours
For maximum, Beth starts at 4/80 in one hr and Charles at 2/ 80 in one hr and Dave at 1/80 in one hr with Alex finishing the remaining 5/80 at 0.5 hr => Maximum time =19.5 hours
User avatar
Rahilgaur
Joined: 24 Jun 2024
Last visit: 26 Jan 2026
Posts: 162
Own Kudos:
125
 [1]
Given Kudos: 47
GMAT Focus 1: 575 Q81 V82 DI72
Products:
GMAT Focus 1: 575 Q81 V82 DI72
Posts: 162
Kudos: 125
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
Let Total work be = 80x

Efficiency of A, B, C & D respectively will be = 10x, 4x, 2x, and x hours

To get minimum time --> A will start the work followed by b, c & D is respective orders

--> in 16 hours, 4 cycle will be completed and 4*17x = 68 x work will be completed and A will do additional 10x work in 1 hour and B will complete the remaining 2x works in 0.5 hrs

---> Total time taken is 17.5 hours

To get maximum time ---> D will start the work followed by C, B and A respectively

68x works will be completed in 4 cycles and 16 hours --> D, C and B will complete 7x works in next 3 hours ---> Remaining work = 5x will be completed by A in 0.5 hours --> Total time taken = 19.5 Hours
User avatar
gchandana
Joined: 16 May 2024
Last visit: 20 Apr 2026
Posts: 191
Own Kudos:
139
 [1]
Given Kudos: 169
Location: India
Products:
Posts: 191
Kudos: 139
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In one 4-person cycle, 17/80 th work is completed. (LCM of 1/8, 1/20, 1/40, 1/80)
So in 4 such cycles, 62/80 th work gets completed.
For sure, we need 16 hours.

We focus on the 12/80 th work remaining.
Next, for the minimum time required, we will make higher-rate people work.
Let's start with Alex. Alex completes 1/8 th work in 1 hour, so the work left 2/80 th.
Then Beth takes 30 minutes to complete the remaining ((2/80) * 20).
A total of 1.5 hrs, which gives 16+1.5 = 17.5 hrs.

For the maximum, we will make lower-rate people work.
Let's start with Dana. Dana completes 1/80 th. Remaining 11/80 th.
Charles completes 1/40 th of it. Remaining 9/80 th.
Beth completes 1/20 th of it. Remaining 5/80 th.
Now, Alex takes 30 minutes to complete the remaining. ((5/80) * 8)
A total of 3.5 hrs, which gives 16+3.5 = 19.5 hrs.
Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
prepapr
Joined: 06 Jan 2025
Last visit: 01 Apr 2026
Posts: 90
Own Kudos:
82
 [1]
Given Kudos: 3
GMAT Focus 1: 615 Q85 V80 DI77
GMAT Focus 1: 615 Q85 V80 DI77
Posts: 90
Kudos: 82
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let the work completed by Alex, Beth, Charles and Dana in one hour be denoted as A,B,C,D.
So, this gives
A=1/8
B=1/20
C=1/40
D=1/80
Bringing to common denominator,
A=10/80
B=4/80
C=2/80
D=1/80
Consider one cycle giving one hour each to all 4 of them. At the end of this cycle, (10+4+2+1)/80 work would be done
Simplifying and analysing
17/80 in one cycle - 4 hours completed
34/80 by second cycle - 8 hours completed
51/80 by third cycle - 12 hours completed
68/80 by fourth cycle - 16 hours completed

Now we have 12/80 work pending. Assigning the order of A,B,C,D would decide the minimum and maximum number of hours taken
Since the efficiency is in the order A>B>C>D

For minimum, we take them in the order ABCD
Calculating minimum, A does 10/80 in another hour, B does the remaining 2/80 in half an hour totaling to 80/80 of work.
Total time taken= 16+1+0.5=17.5 hours

For maximum, we take them in the order DCBA
Calculating maximum, D does 1/80 in one hour, C does 2/80 in another hour, B does 4/80 in another hour, A does the remaining 5/80 in half an hour totalling to 80/80 of work
Total time taken = 16+1+1+1+0.5 = 19.5hours

Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
namna
Joined: 31 Jul 2014
Last visit: 15 Apr 2026
Posts: 13
Own Kudos:
16
 [1]
Concentration: Finance, Other
GPA: 3.3
WE:Engineering (Non-Profit and Government)
Posts: 13
Kudos: 16
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rates per hour:

A = 1/8
B = 1/20
C = 1/40
D = 1/80

Each works alone for exactly one hour in a four hour repeating cycle. Minimum Time/Max Time depends on who finishes the work last.

Min Time: finished by the fastest worker, so, the cycle goes ABCD | ABCD | ABCD ..
Max Time: finished by slowest worker DCBA | DCBA | DCBA ...

One full cycle = 4 hours and completes (1/8 + 1/20 + 1/40 + 1/80) of the task
So, 4 hours <=> 17/80 of the task

How many cycles are need to get the entire task done:

After 4 cycle (=16 hours), 4 * 17/80 = 68/80 of the task.
After 5 cycles (=20 hours), 5 * 17/80 = 85/80 >1

So the task is completed between 16 and 20 hours.

Minimum Time (Alex 1/8 finishes it):
After 16 hours, the remaining work = 1 - 68/80 = 12/80
Alex rate = 1/8 per hour

Time for Alex to finish 12/80 of the task = (12/80) / (1/8) = 1.2 hours

Total Minimum Time = 16 + 1.2 = 17.2 hours ~ 17.5 hours (closest to option)

Maximum Time (D finishes it):
The DCBA cycle also takes 4 cycles = 16 hours to finish 68/80 of the task

Since the cycles are strictly in one hour only, task completed by Dana in the first hour of the 5th cycle = 1/80 (+1 hour)
Remaining task for the next person C = 1 - (68/80 + 1/80) = 11/80 (+1 hour)
C complete 2/80 task in the next hour, leaving for B = 1- (69/80 + 2/80) = 9/80 (+1 hour)
B completes 4/80 task, remaining for A = 5/80
A complete 5/80 task at the rate of 1/8 (=10/80) in 0.5 minutes

Total Maximum Time = 16 +1 + 1 + 1 + 0.5 = 19.5 hours

Final answers:
Min = 17.5 hrs
Max = 19.5 hrs
User avatar
harishg
Joined: 18 Dec 2018
Last visit: 09 Apr 2026
Posts: 176
Own Kudos:
174
 [1]
Given Kudos: 31
GMAT Focus 1: 695 Q88 V84 DI81
Products:
GMAT Focus 1: 695 Q88 V84 DI81
Posts: 176
Kudos: 174
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A, B, C and D work at the rate of 10, 4, 2, and 1 units per hour respectively if total work is considered as 80.

For minimum time, we take the highest efficiency performing individuals first.

10+4+2+1 =17 units of work is done every 4 hrs

17*4+ 10+ 2 units of work is to be done which will take 16+1+1/2 =17.5 hrs

For maximum time, we take the slowest efficiency performing individuals first.

1+2+4+10

17*4+1+4+2+5 gives a time of 16+1+1+1+1/2 =19.5

Therefore, Minimum = 17.5 and Maximum = 19.5
User avatar
Swanoff
Joined: 04 Aug 2021
Last visit: 07 Apr 2026
Posts: 27
Own Kudos:
32
 [1]
Given Kudos: 92
Location: Uzbekistan
Concentration: Strategy, General Management
Schools: Olin
WE:Education (Non-Profit)
Products:
Schools: Olin
Posts: 27
Kudos: 32
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Easy question
First 16 hours clear because 1/80+1/40+1/20+1/8 = 17/80

4 times 4 hour cycle then 4*17/80= 68/80
then plus fastest rates 1/8+1/20
16+1+0.5=17.5


Second case is the same four cycles with the same time but
with smaller values at start like that

68/80+1/80+1/40+1/20 + (1/8 - > half of it)= 19.5

Bunuel
Gift
12 Days of Christmas Competition
This question is part of our holiday event
Win $40,000 in prizes: courses, tests, and more


Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.

Select for Minimum the minimum number of hours required for the task to be completed, and select for Maximum the maximum number of hours required for the task to be completed. Make only two selections, one in each column.
User avatar
fugaquasi
Joined: 28 Aug 2025
Last visit: 07 Apr 2026
Posts: 24
Own Kudos:
19
 [1]
Given Kudos: 34
Posts: 24
Kudos: 19
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
took me two tries, im too rusty ;-;

lets say total work is 80 units, each persons rate can be as follows then:

A - 10
B - 4
C - 2
D - 1

Now upto the 16th hour the ordering dosent really matter considering no matter what you do the same amount of time will be taken

at 16 hours work done = 68
now assinging A at 17 hours would mean 78 work done
and then B at the 18th hour would lead to about half an hour hence, 17.5 hrs

Now for maximum:

same upto 16th hour, following which instead of assinging a lets assign the slowest worker D.
Now at 17th hour work done = 69
18 = 71
19 = 75
19.5 = 80

Hence maximum = 19.5
User avatar
linnet
Joined: 11 Dec 2025
Last visit: 22 Jan 2026
Posts: 81
Own Kudos:
Given Kudos: 1
Posts: 81
Kudos: 42
Kudos
Add Kudos
Bookmarks
Bookmark this Post
the maximum time is19.5 ad the minimum time is 18
 1   2   3   4   
Moderators:
Math Expert
109715 posts
498 posts
210 posts