Last visit was: 29 Apr 2026, 19:26 It is currently 29 Apr 2026, 19:26
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
mbafinhopeful
Joined: 31 Dec 2017
Last visit: 15 Dec 2019
Posts: 22
Own Kudos:
29
 [1]
Given Kudos: 64
Concentration: Finance
Posts: 22
Kudos: 29
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
avatar
Varun121595
Joined: 23 Jun 2017
Last visit: 16 Feb 2018
Posts: 8
Own Kudos:
Given Kudos: 130
Posts: 8
Kudos: 8
Kudos
Add Kudos
Bookmarks
Bookmark this Post
avatar
mdali01825
Joined: 27 Nov 2017
Last visit: 03 Apr 2018
Posts: 1
Given Kudos: 1
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
fskilnik
Joined: 12 Oct 2010
Last visit: 03 Jan 2025
Posts: 883
Own Kudos:
Given Kudos: 57
Status:GMATH founder
Expert
Expert reply
Posts: 883
Kudos: 1,889
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

Nice problem!

Let´s suppose each man does 1 task/day , and each woman does k tasks/day (where k>0, not necessarily an integer).

By the question stem, we know that:

> 24 men do 1 work in 16 days, hence 1 work = 24*16 tasks (1)
> 32 women do 1 work in 24 days, hence 1 work = 32*24*k tasks implies, by (1) above, that k = 1/2

> 16 men and 16 women will do in 12 days exactly 16*12*1 + 16*12*1/2 = 24*12 tasks, therefore by (1) we have still 24*(16-12) = 24*4 tasks to be done.

> If x is the number of men to be added (our FOCUS), we have a group of (16+x) men and 16 women performing (16+x)*1 + 16*1/2 = (24+x) tasks/day,
and the final touch is done with UNITS CONTROL, one of our method´s most powerful tools:

\(24 \cdot 4\,\,\,{\text{tasks}}\,\,\, = \,\,2\,\,days\,\,\left( {\frac{{24 + x\,\,\,{\text{tasks}}}}{{1\,\,\,{\text{day}}}}\,\,\,\begin{array}{*{20}{c}}\\
\nearrow \\ \\
\nearrow \\
\end{array}} \right)\,\,\,\,\,\, \Rightarrow \,\,\,\,\,24 + x = 24 \cdot 2\,\,\,\,\, \Rightarrow \,\,\,\,\,\,? = x = 24\)

Obs.: arrows indicate licit converters.

(If you realize this solution is absolutely clear and safe, you are the perfect candidate for our method... try our free and super-complete test drive!)


This solution follows the notations and rationale taught in the GMATH method.

Regards,
fskilnik.
avatar
Manick9
Joined: 25 May 2016
Last visit: 07 Jan 2025
Posts: 78
Own Kudos:
Given Kudos: 497
Location: Singapore
Concentration: Finance, General Management
GMAT 1: 620 Q46 V30
GMAT 1: 620 Q46 V30
Posts: 78
Kudos: 85
Kudos
Add Kudos
Bookmarks
Bookmark this Post
24 men will take 16 days.
1 man will take 384 days.
32 women will take 24 days.
1 women will take 768 days.

Therefore, 1 women's work rate is equal to 0.5 man.

16 man + 16 women = 24 man.
So, they will require 4 more days with the same manpower. If they double the manpower they can complete the work in 2 days.

Therefore, another 24 men are required.
User avatar
Shef08
Joined: 01 Jan 2019
Last visit: 01 Apr 2025
Posts: 81
Own Kudos:
Given Kudos: 111
Location: Canada
Concentration: Finance, Entrepreneurship
GPA: 3.24
Posts: 81
Kudos: 34
Kudos
Add Kudos
Bookmarks
Bookmark this Post
ScottTargetTestPrep
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

We are given that the rate of 24 men is 1/16, so the rate of each man is (1/16)/24 = 1/(16 x 24). Similarly, we are given that the rate of 32 women is 1/24, so the rate of each woman is (1/24)/(32) = 1/(24 x 32). Now we can find the fraction of the job that is completed by 16 men and 16 women in one day.

16 x 1/(16 x 24) + 16 x 1/(24 x 32)

1/24 + 1/(24 x 2)

2/48 + 1/48

3/48 = 1/16

We see that 16 men and 16 women can complete 1/16 of the job in one day, so they can complete 12 x 1/16 = 12/16 = 3/4 of the job in 12 days.

We can let m be the number of additional men who must be added to complete the job in two more days. Since we have 1 - 3/4 = 1/4 of the job left and it needs to be completed in two2 more days, each day they need to complete (1/4)/2 = 1/8 of the job. Thus, we can create the following equation to solve for m:

(16 + m) x 1/(16 x 24) + 16 x 1/(24 x 32) = 1/8

1/24 + m/(16 x 24) + 1/48 = 1/8

Multiplying the above equation by 48, we have:

2 + m/8 + 1 = 6

m/8 = 3

m = 24

Answer: B


Hi ScottTargetTestPrep

Thank you for this detailed equation, I need u to correct me where did I go wrong.

So I found the rate of man and woman, as derived by you. But the final equation which I formed was:

16+x/16*24 + 16/24*36= 1/14

Where x is the additional men required to complete the work in 2 more days which makes it 12 days + 2 more days

Posted from my mobile device
User avatar
minustark
Joined: 14 Jul 2019
Last visit: 01 Apr 2021
Posts: 465
Own Kudos:
Given Kudos: 52
Status:Student
Location: United States
Concentration: Accounting, Finance
GMAT 1: 650 Q45 V35
GPA: 3.9
WE:Education (Accounting)
Products:
GMAT 1: 650 Q45 V35
Posts: 465
Kudos: 402
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

24 man can complete in 16 days
16 man can complete in 24/16 * 16 days or, 24 days

32 women >>>> 24 days
16 women>>>> 48 days

So, in 12 days work completed by 16 men and 16 women = (1/24+1/48)*12= 12*3/48= 3/4
For remaining 1/4 work, it would have take 12/3 = 4 days in current setting.
Since 1 man = 2 women...we can say, 16 + 8 = 24 men need 4 days to finish the 1/4 part of work.

4 days>>>> 24 men
2 days >>>>>24 * 2 men
There is already 24 men, so we need 24 more.
User avatar
SVaidyaraman
Joined: 17 Dec 2012
Last visit: 11 Jul 2025
Posts: 566
Own Kudos:
1,835
 [1]
Given Kudos: 20
Location: India
Expert
Expert reply
Posts: 566
Kudos: 1,835
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

time taken by 16 men=24 days
time taken by 16 women = 48 days

Proportion of work completed by 16 men and 16 women in 12 days= 12 /24 +12/48

In 14 days work is complete

(12+2)/24 + (12+2) /48 + 2/(16*24)/x =1 ( 16 men take 24 days . So x men take 16*24/x days. proportion of work completed by the additional men in 2 days = 2/ (16*24)/x )

7/8 + x/192 =1

x=24
avatar
indugopal1991
Joined: 24 Oct 2019
Last visit: 30 Oct 2025
Posts: 8
Own Kudos:
Given Kudos: 17
Posts: 8
Kudos: 4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
24 Men can do the work in 16 days. ie; 24*16 man-day work
32 Women can do the work in 24 days. ie; 32*24 women-day work.

comparing first two lines, 1M-work=2W-work.

16 Men and 16 Women have done the work for 12. So we can say 24 men have done the work for 12 days.

So total amount of work done, 24*12 Man-day work. So, remaining work 24*4 Man-day work.

So, to complete the remaining work in 2 days we need (24*4)/2=48 Men.

We have already 24 Men equivalence, we need another 48-24= 24 days.

I hope this works.
avatar
Vichitra
avatar
Current Student
Joined: 28 Oct 2015
Last visit: 22 Nov 2022
Posts: 9
Own Kudos:
Given Kudos: 23
Location: India
Schools: IESE'23 (A)
GMAT 1: 630 Q49 V27
GMAT 2: 690 Q50 V33
GMAT 3: 720 Q50 V39
Products:
Schools: IESE'23 (A)
GMAT 3: 720 Q50 V39
Posts: 9
Kudos: 4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

I like to approach work problems with the LCM method-
24M-16 Days
32W- 24 Days

Looking at the numbers, lets say 96 jobs is the amount of work to be done. (For easy divisibility)
24 M work at a rate of 6 jobs per day (96/16)
32 W work at a rate of 4 jobs per day (96/24)

16 M work at a rate of 4 jobs per day [(6/24)X16]
16 W work at a rate of 2 jobs per day

Working together they work 6 jobs per day so in 12 days they complete 72 jobs.
in the next 2 days they will complete 12 jobs more adding up to 84 Jobs.

Now we just need to find the Men required to do the balance job i.e. 12 jobs (96-84) in 2 days.
We already know that 24 M work at a rate of 6 jobs per day.

Hence 24 men will do 12 jobs in 2 days which is our answer.
User avatar
Fdambro294
Joined: 10 Jul 2019
Last visit: 20 Aug 2025
Posts: 1,331
Own Kudos:
Given Kudos: 1,656
Posts: 1,331
Kudos: 772
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Crazy Numbers, but one little trick I've seen followed by the Top Contributors......don't Multiply trough Crazy Numbers Until you Absolute have to!



(1st) Find the Rate of 1 MAN and the Rate of 1 WOMAN


Rate of 24 Men = 1 job / 16 Days

Rate of 1 Man = 1 job / (16 * 24) Days


Rate of 32 Women = 1 job / 24 Days

Rate of 1 Woman = 1 job / (24 * 32) Days




(2nd) Find out How much Work is REMAINING after 16 Women and 16 Men work for ---- 14 DAYS, not 12 Days

*Let me explain: No matter how many more Men we hire, these 16 Women and 16 Men who started are going to be contributing their work in the Extra 2 Days that we need to Finish the Work. So, we need to figure out how much Work Remains after:

(1)Both groups work for 12 days together

and

(2)Both groups work with the X - NEW MEN for 2 more Days


Since there are NO Economies of Scale and Each participant adds their own work Independently, we can find the amount of work that the 2 Groups contribute throughout these 18 Days.

The Extra MEN we will need will have to complete the REMAINING Work in 2 Days given the Rate per 1 MAN we found above.



Using the Following Matrix

# of Men/Women * (Rate per 1 Man OR Rate per 1 Woman) * (Time working) = WORK Contributed

(16 Men) * (1 / 24*16) * (14 Days) = A

(16 Woman) * (1 / 24*32) * (14 Days) = B


A Work contributed by the 16 Men = 28/48 of Job

B Work Contributed by the 16 Women = 14/48 of Job

Total Work COMPLETED before we hire MORE Men = 42/48 = 7/8


Work REMAINING for the MORE Men we hire = 1 Job - (7/8 Completed) = 1/8 of Job



(3rd) Determine How many More MEN we need to hire when the Rate of 1 MAN = 1 / (24 * 16) (job/per day)


Let the # of Men we need = M


M * (Rate of 1 Man) * (2 Days Deadline) = 1/8 of Job Remaining to be Completed

M * (1 / 24*16) * (2) = 1/8

2M / 24*16 = 1/8

---cross-multiplying-----

16M = (24) * (16)


M = 24 Men needed to finish the work in 2 Days


-B-
User avatar
arbazfatmi1994
Joined: 05 Jul 2022
Last visit: 16 Jan 2024
Posts: 102
Own Kudos:
Given Kudos: 31
Location: India
WE:Advertising (Healthcare/Pharmaceuticals)
Products:
Posts: 102
Kudos: 18
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Not to sound misogynistic, but let's convert everything to MAN-DAYS.
User avatar
BinodBhai
Joined: 19 Feb 2025
Last visit: 15 Oct 2025
Posts: 107
Own Kudos:
Given Kudos: 252
Posts: 107
Kudos: 31
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let total work be LCM of 16 and 24 which is 48 units

so 24M rate is 1/16 so they can do 48/16 i.e. 3 units of work per day (this is for 24 men)
same way rate if 32W rate is 1/24, so they can do 48/24 i.e. 2 units of work per day

now we have 16M + 16W .. their combined rate is:
24M is 3 Units
so 16 men is 16x3/24 i.e. 2 units

so combined rate is 2+1 is 3 units

now in 12 days they will do 3x12 i.e. 36 units of work.
Work left 48 - 36 i.e. 12

now these people will only be able to do half of the work in 2 days (3x2)
But we need more men to complete 3 units of work per day for next 2 days to complete 6 units of work left
so 3 units we already know is 24 .. so we need 24 extra Men .. B
User avatar
patpathaha
Joined: 28 May 2025
Last visit: 09 Mar 2026
Posts: 7
Own Kudos:
Given Kudos: 16
Posts: 7
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
24 men x 16 days = 1 work
=> 1 men x 1 day = 1/(24*16) work (1)

32 women x 24 days = 1 work
=> 1 women x 1 day = 1/(32*24) work (2)

From (1) => 16 men x 12 days did (16*12)/(24*16) = 1/2 work
From (2) => 16 women x 12 days did (16*12)/(32*24) = 1/4 work
After 12 days, 16 men + 16 women did 3/4 work

For the next 2 days, WITHOUT any additional men, 16 men + 16 women did an additional 3/4 / 12 * 2 = 1/8 work
So the work left for addional men to work is 1 - 3/4 - 1/8 = 1/8 work in 2 days
So the work left for additional men to work in 1 day is 1/16 work
1 men in 1 day did 1/(24*16) work, so we would need 24 men to do 1/16 work
=> 24 men

Hope this helps :)
User avatar
Siddharth17
Joined: 04 Dec 2025
Last visit: 29 Apr 2026
Posts: 15
Own Kudos:
Given Kudos: 9
Location: India
GMAT 1: 670 Q60 V53
GPA: 8.02
WE:Information Technology (Finance: Investment Banking)
GMAT 1: 670 Q60 V53
Posts: 15
Kudos: 5
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

let work done per day by one man = M, work done per day by on woman = W

that total work = 24 * M * 16 = 32 * W * 24 => 384 M
=> M = 2 * W

Work completed in 12 days = (16 * M + 16 * W) * 12 = (16 * M + (8 * M )) * 12 = 288 M
Work remained = 96 M

let x be additional men required to complete work in 2 days.

96 M = (16 + x + 8) M * 2
x = 24
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 29 Apr 2026
Posts: 5,989
Own Kudos:
Given Kudos: 163
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,989
Kudos: 5,863
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.

How many more men are to be added to complete the work remaining work in 2 days?

Man-days required to complete the work = 24*16 = 384 man-days
Women-days required to complete the work = 32*24 = 768 women-days

384 man-days = 768 women-days
1 man-day = 2 women-day

Sixteen men and sixteen women started working for twelve days.
Man-days = 16*12 + 16*12/2 = 288 man-days

Remaining Man-days = 384 - 288 = 96 man-days
Days = 2
Men required = 96/2 = 48 men
Existing men equivalent = 16 + 16/2 = 24 men
Men to be added = 48 - 24 = 24 men

IMO B
   1   2 
Moderators:
Math Expert
109975 posts
Tuck School Moderator
852 posts