Last visit was: 18 Nov 2025, 18:38 It is currently 18 Nov 2025, 18:38
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Chemerical71
Joined: 09 Jan 2016
Last visit: 01 Sep 2020
Posts: 76
Own Kudos:
468
 [157]
Given Kudos: 61
GPA: 3.4
WE:General Management (Human Resources)
Posts: 76
Kudos: 468
 [157]
16
Kudos
Add Kudos
141
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,265
Own Kudos:
76,982
 [65]
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,265
Kudos: 76,982
 [65]
40
Kudos
Add Kudos
24
Bookmarks
Bookmark this Post
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 18 Nov 2025
Posts: 21,712
Own Kudos:
26,990
 [19]
Given Kudos: 300
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 21,712
Kudos: 26,990
 [19]
11
Kudos
Add Kudos
8
Bookmarks
Bookmark this Post
General Discussion
User avatar
saswata4s
User avatar
Current Student
Joined: 28 May 2014
Last visit: 11 Apr 2023
Posts: 413
Own Kudos:
1,251
 [15]
Given Kudos: 103
GMAT 1: 730 Q49 V41
GMAT 1: 730 Q49 V41
Posts: 413
Kudos: 1,251
 [15]
6
Kudos
Add Kudos
9
Bookmarks
Bookmark this Post
24 men ----------- 16 days ------------ 1 complete work
1 man ------------ 1 day ------------1/(24*16) portion work

32 women ----------- 24 days ------------ 1 complete work
1 woman ------------ 1 day ------------1/(32*24) portion work

Hence,
1 man &1 woman ------------ 1 day ------------{1/(32*24) + 1/(24*16)} portion work = 1(/24)*(1/16 + 1/32) = (1/24)*(3/32) = (1/8)*(1/32)
Now,
16 man & 16 woman ------------ 1 day ------------ 16* (1/8)*(1/32) portion work = 2*(1/32) = 1/16
16 man & 16 woman ------------ 12 day ------------ 12*(1/16) = 3/4
Remaining work - 1/4

Now, extra work in next 2 days: 1/4 - 2*(1/16) = 1/8
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 .

Answer B.

This is not a SUB-600 level question.
User avatar
Chemerical71
Joined: 09 Jan 2016
Last visit: 01 Sep 2020
Posts: 76
Own Kudos:
Given Kudos: 61
GPA: 3.4
WE:General Management (Human Resources)
Posts: 76
Kudos: 468
Kudos
Add Kudos
Bookmarks
Bookmark this Post
saswata4s
24 men ----------- 16 days ------------ 1 complete work
1 man ------------ 1 day ------------1/(24*16) portion work

32 women ----------- 24 days ------------ 1 complete work
1 woman ------------ 1 day ------------1/(32*24) portion work

Hence,
1 man &1 woman ------------ 1 day ------------{1/(32*24) + 1/(24*16)} portion work = 1(/24)*(1/16 + 1/32) = (1/24)*(3/32) = (1/8)*(1/32)
Now,
16 man & 16 woman ------------ 1 day ------------ 16* (1/8)*(1/32) portion work = 2*(1/32) = 1/16
16 man & 16 woman ------------ 12 day ------------ 12*(1/16) = 3/4
Remaining work - 1/4

Now, extra work in next 2 days: 1/4 - 2*(1/16) = 1/8
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 .

Answer B.

This is not a SUB-600 level question.
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 . please explain this step again. :-D
User avatar
BillyZ
User avatar
Current Student
Joined: 14 Nov 2016
Last visit: 03 May 2025
Posts: 1,143
Own Kudos:
Given Kudos: 926
Location: Malaysia
Concentration: General Management, Strategy
GMAT 1: 750 Q51 V40 (Online)
GPA: 3.53
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
VeritasPrepKarishma
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)

Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).
User avatar
KrishnakumarKA1
Joined: 05 Jan 2017
Last visit: 13 Oct 2020
Posts: 403
Own Kudos:
310
 [10]
Given Kudos: 15
Location: India
Posts: 403
Kudos: 310
 [10]
6
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

let the work be z rate of doing work for man and woman be x and y respectively

According to question
24*16*x = z
32*24*y = z

therefore 24*16*x = 32*24*y or x = 2y

work done in 12 days = (16x +16y)12 = (32y + 16y) 12 = 48*12y = 24*24y

work left = 32*24y-24*24y = 8*24y

work left = (no of men added rate+ current workers rate)*2

or 8*24y = (N*x +16x+16y)*2

putting x = 2y

4*24y = 2Ny+48y
2Ny = 48y

or N = 24.

Option B
User avatar
warriorguy
User avatar
Retired Moderator
Joined: 04 Aug 2016
Last visit: 08 Feb 2023
Posts: 378
Own Kudos:
357
 [1]
Given Kudos: 144
Location: India
Concentration: Leadership, Strategy
GPA: 4
WE:Engineering (Telecommunications)
Posts: 378
Kudos: 357
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
ziyuen
VeritasPrepKarishma
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)

Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).

Total Work completed = Rate of work of each man * total # of man * total time

Rate of work of each man = Total Work completed / (total # of man * total time) = 1/ (24*16)
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,265
Own Kudos:
76,982
 [4]
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,265
Kudos: 76,982
 [4]
2
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
ziyuen
VeritasPrepKarishma
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)

Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).


The relation between no. of workers and no of days is inversely proportional.
If there are fewer women, no of days taken will be more.

No of women * No of days = Constant

32 women * 24 days = 24 women * ?? days

?? days = 24 days * (32 women/24 women)

?? days = 24 days

Check out this blog post on work rate: https://anaprep.com/arithmetic-work-rat ... variation/
User avatar
gmatexam439
User avatar
Moderator
Joined: 28 Mar 2017
Last visit: 18 Oct 2024
Posts: 1,064
Own Kudos:
2,159
 [3]
Given Kudos: 200
Location: India
Concentration: Finance, Technology
GMAT 1: 730 Q49 V41
GPA: 4
Products:
GMAT 1: 730 Q49 V41
Posts: 1,064
Kudos: 2,159
 [3]
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Bunuel
Twenty-four men can complete a job in sixteen days. Thirty-two women can complete the same job in twenty-four days. Sixteen men and sixteen women started working on the job for twelve days. How many more men must be added to complete the job in 2 days?

(A) 16

(B) 24

(C) 36

(D) 48

(E) 54

1M 1D work=1/(16*24)
1W 1D work=1/(24*32)

16M 1D work=1/24=2/48
16W 1D work=1/48

16M&W 1D work=3/48=1/16
16M&W 12D work=12/16

Hence remaining work=4/16=1/4 -------> this work should be completed by the additional men

1M 1D work=1/(16*24)
1M 2D work=1/(16*12)
xM 2D work=x/(16*12), this must be equal to 1/4

x/(16*12)=1/4
=> x=48

Answer: D
avatar
ashudhall
Joined: 27 Mar 2016
Last visit: 26 Jan 2021
Posts: 73
Own Kudos:
69
 [2]
Given Kudos: 4
GMAT 1: 590 Q44 V22
GMAT 1: 590 Q44 V22
Posts: 73
Kudos: 69
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Lets take lcm of 16,24 and 32 i.e 96. So let the work job be 96.
Now for men let their one day effort be x. So x*24*16= 96, hence x= 1/4
Similary for women let their one day effort per person be y . So y*32*24=96
Y= 1/8.
Now (1/4+1/8)*16*12=72. So 24 units of work is left. Now let no of men be z 1/4*2*z= 24.
Hence z =48

Sent from my ONEPLUS A3003 using GMAT Club Forum mobile app
avatar
gmathopeful19
Joined: 09 Oct 2016
Last visit: 27 Jun 2018
Posts: 66
Own Kudos:
Given Kudos: 8
Location: United States
GMAT 1: 740 Q49 V42
GPA: 3.49
Products:
GMAT 1: 740 Q49 V42
Posts: 66
Kudos: 34
Kudos
Add Kudos
Bookmarks
Bookmark this Post
This one took a while to do simply bc of all the calculations (if there is a quick way please let me know)

I ended up with 48, D.

Men rate = 1/384
Women rate = 1/768

Combined and through 14 days = 336/384, 48 being the difference

Edit: upon further review, I made a mistake and didn't account for the two days. It should be 24 additional men, making the total 48 on day 12. This would produce the additional 96 units needed
Posted from my mobile device
User avatar
stonecold
Joined: 12 Aug 2015
Last visit: 09 Apr 2024
Posts: 2,244
Own Kudos:
3,549
 [1]
Given Kudos: 893
GRE 1: Q169 V154
GRE 1: Q169 V154
Posts: 2,244
Kudos: 3,549
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Excellent question.
700 level for sure ..
Here is what I did on this question---->


Let us decode the statements ==>
Let the complete work be designated by W.

Twenty-four men can complete a job in sixteen day.
Speed of each men => W/(16*24) per day

Thirty-two women can complete the same job in twenty-four days.
Speed of each women => W/(32*24) per day

16 men and 16 women stated working

Combined speed of 16 men and 16 women => W/(16*24) * 16 + W/(32*24) *16 => W/24+W/48 => W/16 per day
Now combining they work for 12 Days =>

Work done => 12*W/16 => 3W/4
Left over work => W-3W/4 => W/4

Now let more men =x

Hence-->
2* [(x+16) W/(16*24) + 16*W/(32*24)] = W/4

Solving this we get => x=24

Hence B.



SMASH THAT B.

Looking forward to the OE.
User avatar
stonecold
Joined: 12 Aug 2015
Last visit: 09 Apr 2024
Posts: 2,244
Own Kudos:
3,549
 [4]
Given Kudos: 893
GRE 1: Q169 V154
GRE 1: Q169 V154
Posts: 2,244
Kudos: 3,549
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
gmatexam439
Bunuel
Twenty-four men can complete a job in sixteen days. Thirty-two women can complete the same job in twenty-four days. Sixteen men and sixteen women started working on the job for twelve days. How many more men must be added to complete the job in 2 days?

(A) 16

(B) 24

(C) 36

(D) 48

(E) 54

1M 1D work=1/(16*24)
1W 1D work=1/(24*32)

16M 1D work=1/24=2/48
16W 1D work=1/48

16M&W 1D work=3/48=1/16
16M&W 12D work=12/16

Hence remaining work=4/16=1/4 -------> this work should be completed by the additional men

1M 1D work=1/(16*24)
1M 2D work=1/(16*12)
xM 2D work=x/(16*12), this must be equal to 1/4

x/(16*12)=1/4
=> x=48

Answer: D

You did all the hard work.
But missed out just at the very end.

The highlighted portion is incorrect.

Here is the corrected version -->

The work 1/4 would be done by both x men and 16 women.
You forgot to take 16 women into account.
NOTE -> You have taken the entire men's number as x.

So work done by x men and 16 women in 2 days => 2[x/24*16 +16/24*32] =1/4
x=40
Hence additional men required => 40-16 => 24

Smash that B.
User avatar
Abhishek009
User avatar
Board of Directors
Joined: 11 Jun 2011
Last visit: 18 Jul 2025
Posts: 5,937
Own Kudos:
5,327
 [2]
Given Kudos: 463
Status:QA & VA Forum Moderator
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Posts: 5,937
Kudos: 5,327
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

Quote:
Twenty-four men can complete a work in sixteen days.

So, Total mandays = 24*16 => 384

Quote:
Thirty-two women can complete the same work in twenty-four days.

So, Total womandays = 32*24 => 768

Now, total work = LCM( 384,768 ) => 768

So, Efficiency of men = 2 & Efficiency of women = 1

Quote:
Sixteen men and sixteen women started working for twelve days.

Work completed = (16*2 + 16*1 )12 => 576 units , Work left = 768 - 576 => 192

Quote:
How many more men are to be added to complete the work remaining work in 2 days?

\({(16+m)*2 + 16*1 }*2 = 192\)

Or, \((16+m)*2 + 16 = 96\)

Or, \((16+m) = 40\)

Or, \(m = 24\)

Thus, we need to add , 24 more men workers, answer must be (B) 24 men...
User avatar
hanyhamdani
User avatar
Current Student
Joined: 30 Dec 2013
Last visit: 04 Jan 2019
Posts: 28
Own Kudos:
28
 [1]
Given Kudos: 26
Status:preparing
Location: United Arab Emirates
Concentration: Technology, Entrepreneurship
GMAT 1: 660 Q45 V35
GMAT 2: 640 Q49 V28
GPA: 2.84
WE:General Management (Consumer Packaged Goods)
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
the question is done in two parts:

1) work rate comparison bw men and women
24 men ---- 16 days
1 man ----- 24x16
16 man ----- 24 days

32 women ---- 24 days
16 women --- 48 days

so men : women = 2 : 1
men will do double the work done by women

2) work remaining after 12 days, that needs to be done in 2 days

men need 24 days to finish the work. so in 12 days they will do half the job
m ---- 1/2

women need 48 days to finish the job, and in 12 days they will do 12/48 = 1/4 th of the work

w----- 1/4

total work done in 12 days = m+w = 1/2 + 1/4 = 3/4
balance = 1/4 of work

In other words 1/4 * 24 =6 days of work for 16 men and 16 women

how many additional men required to finish in two days :
1/2 of work is done by 16 men
so 1/4 of work will be done by 8 men
total = 16+8= 24 men
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 18 Nov 2025
Posts: 21,712
Own Kudos:
26,990
 [1]
Given Kudos: 300
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 21,712
Kudos: 26,990
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54

We are given that the rate of 24 men is 1/16, so the rate of each man is (1/16)/24 = 1/(16 x 24). Similarly, we are given that the rate of 32 women is 1/24, so the rate of each woman is (1/24)/(32) = 1/(24 x 32). Now we can find the fraction of the job that is completed by 16 men and 16 women in one day.

16 x 1/(16 x 24) + 16 x 1/(24 x 32)

1/24 + 1/(24 x 2)

2/48 + 1/48

3/48 = 1/16

We see that 16 men and 16 women can complete 1/16 of the job in one day, so they can complete 12 x 1/16 = 12/16 = 3/4 of the job in 12 days.

We can let m be the number of additional men who must be added to complete the job in two more days. Since we have 1 - 3/4 = 1/4 of the job left and it needs to be completed in two2 more days, each day they need to complete (1/4)/2 = 1/8 of the job. Thus, we can create the following equation to solve for m:

(16 + m) x 1/(16 x 24) + 16 x 1/(24 x 32) = 1/8

1/24 + m/(16 x 24) + 1/48 = 1/8

Multiplying the above equation by 48, we have:

2 + m/8 + 1 = 6

m/8 = 3

m = 24

Answer: B
User avatar
amanvermagmat
User avatar
Retired Moderator
Joined: 22 Aug 2013
Last visit: 28 Mar 2025
Posts: 1,148
Own Kudos:
Given Kudos: 480
Location: India
Posts: 1,148
Kudos: 2,854
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I will attempt this in a similar way as Ashudhall.

In these kind of questions, its a good idea sometimes to take total units of work as the LCM of all the days and number of people given. Because we need a number which is divisible by all of those. Let me explain.

LCM of 24, 16, 32 and 24 is 96. So lets assume total work to be done as 96 units.
24 men can do 96 units work in 16 days
So 24 men can do in 1 day = 96/16 = 6 units of work.
So 1 man can do in 1 day = 6/24 = 1/4 units of work

Also, 32 women can do 96 units of work in 24 days
So 32 women can do in 1 day = 96/24 = 4 units of work
So 1 woman can do in 1 day = 4/32 = 1/8 units of work

Thus, 16 men and 16 women can do in 1 day = 16*1/4 + 16*1/8 = 6 units of work
As per the question, the work has to be completed in 14 total days
In 14 days, these 16 men and 16 women would have completed = 14*6 = 84 units of work

Remember that total units of work are 96.
Remaining work units = 96-84 = 12 units

If 'n' extra men are employed to finish off these 12 units in 2 days, it means these 'n' men finish 6 units in 1 day
We know that 1 man does 1/4 units work in 1 day
Therefore, no of men required 'n' = 6/(1/4) = 24

So 24 extra men are required. Answer is B
User avatar
SVaidyaraman
Joined: 17 Dec 2012
Last visit: 11 Jul 2025
Posts: 576
Own Kudos:
Given Kudos: 20
Location: India
Expert
Expert reply
Posts: 576
Kudos: 1,795
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Chemerical71
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54
1. 1 man takes 384 days and 1 woman takes 768 days
2. (no.of days worked by men* no.of men)/(time taken for a man working alone) +
(no.of days worked by additional men * no.of additional men )/(time taken for a man working alone)+
(no.of days worked by women* no.of women)/(time taken for a woman working alone) = 1
3. (14*16)/384 + (2*x)/384 + (14*16)/768=1
We get x=24
User avatar
EMPOWERgmatRichC
User avatar
Major Poster
Joined: 19 Dec 2014
Last visit: 31 Dec 2023
Posts: 21,785
Own Kudos:
12,804
 [1]
Given Kudos: 450
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Expert
Expert reply
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Posts: 21,785
Kudos: 12,804
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Hi All,

Before we get into this question, you've been posting a variety of 'tougher' prompts lately - so unless you're already scoring above 700 in your practice Exams (or on the Official GMAT), then you might be focusing on the wrong things.

In these types of 'rate' questions, it often helps to think in terms of the TOTAL work that must be done to complete the task. If a 24-man crew can complete the job in 16 days, then that means that (24)(16) = 384 man-days of effort are required to complete the job. If a 32-woman crew can complete the job in 24 days, then that means that (32)(24) = 768 woman-days of effort are required to complete the job.

Before we do anything else, it's important to compare these numbers: 384 and 768. Since 384 is exactly HALF of 768, in this question that means that the work that a woman does in 1 day = 1/2 of the work that a man does in 1 day.

We're told that 16 men and 16 women work for 12 days each. That means they complete....

(16 men)(12 days) = 192 man-days of work = 1/2 of the job gets done
(16 women)(12 days) 192 woman-days of work = 1/4 of the job gets done

1/2 + 1/4 = 3/4... so after 12 days, 3/4 of the job is done - and 1/4 of the job remains

We're going to add a certain number of men, so that the job is completed in 2 more days. First though, we have to figure out how much more of the job gets completed with the existing people during that time...

(16 men)(2 days) = 32 man-days of work = 1/12 of the job gets done
(16 women)(2 days) 32 woman-days of work = 1/24 of the job gets done

During the next 2 days, the existing people will complete 1/12 + 1/24 = 3/24 of the job gets done

That leaves us with 1/4 - 3/24 = 3/24 of the job remains. 3/24 of 384 man-days = 48 man-days of work. The extra men that will be added will work for 2 days each, so....

(X men)(2 days each) = 48 days of man-work
X = 24

Final Answer: