Last visit was: 25 Apr 2026, 19:14 It is currently 25 Apr 2026, 19:14
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Sajjad1994
User avatar
GRE Forum Moderator
Joined: 02 Nov 2016
Last visit: 25 Apr 2026
Posts: 16,771
Own Kudos:
51,924
 [4]
Given Kudos: 6,335
GPA: 3.62
Products:
Posts: 16,771
Kudos: 51,924
 [4]
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
User avatar
Abbas135
Joined: 27 Jul 2023
Last visit: 06 May 2024
Posts: 1
Given Kudos: 6
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Sajjad1994
User avatar
GRE Forum Moderator
Joined: 02 Nov 2016
Last visit: 25 Apr 2026
Posts: 16,771
Own Kudos:
51,924
 [3]
Given Kudos: 6,335
GPA: 3.62
Products:
Posts: 16,771
Kudos: 51,924
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Oppenheimer1945
Joined: 16 Jul 2019
Last visit: 21 Apr 2026
Posts: 784
Own Kudos:
664
 [2]
Given Kudos: 236
Location: India
GMAT Focus 1: 645 Q90 V76 DI80
GPA: 7.81
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
At either location, the company’s budget will permit spending a total of $30 million for labor and shipping.
Choose options that sum up to 30

(23,7).

Location B, an urban site convenient to highways and rail lines, can function with a 30% smaller budget for shipping of the same quantities

Should be 7.
User avatar
sayan640
Joined: 29 Oct 2015
Last visit: 25 Apr 2026
Posts: 1,118
Own Kudos:
Given Kudos: 790
GMAT 1: 570 Q42 V28
Products:
GMAT 1: 570 Q42 V28
Posts: 1,118
Kudos: 862
Kudos
Add Kudos
Bookmarks
Bookmark this Post
                                   Labor  Cost                           shipping cost 
Location A                       2x                                         x

3x = 30 
x= 10

                                   Labor  Cost                           shipping cost 
Location A                       20                                       10
Location B                       20(1+15/100)                       10(1-30/100)

Hence , Location B 's labor cost = 20 + 3 = 23
Location B's shipping cost = 7

GMATinsight

Sajjad1994
Data Insights (DI) Butler 2023-24 [Question #63, Date: Oct-23-2023] [[url=https://gmatclub.com/forum/data-insights-di-butler-419150.html]Click here for Details]

Two locations are available for a new facility being planned. The facility will be an assembly plant, which will receive parts shipped to it from manufacturing locations around the country. Location A can provide cheaper labor, but because of its rural location, will require a larger budget for shipping of components to the facility. Location B, an urban site convenient to highways and rail lines, can function with a 30% smaller budget for shipping of the same quantities of components but will spend 15% more for the same labor, because of higher salaries in the area. At either location, the company’s budget will permit spending a total of $30 million for labor and shipping. If it has been determined that the budget for labor costs at location A will be twice the amount budgeted for shipping costs at that location, find the shipping costs and labor costs for location B.
­
User avatar
Rickooreoisb
Joined: 18 Jul 2025
Last visit: 05 Apr 2026
Posts: 157
Own Kudos:
Given Kudos: 575
Location: India
Concentration: Finance, Marketing
GPA: 9
WE:Investment Banking (Finance: Investment Banking)
Posts: 157
Kudos: 41
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Took unnecessary time to solve this, I guess got carried away by length of passage.

ow It Works (Simple Algebra Reasoning)

Let shipping cost at location A = x (million), so labor at A = 2x.

Total budget at A = x + 2x = 3x = 30 ⇒ x = 10.

So at A: shipping = $10M, labor = $20M.

At location B:

Shipping is 30 % less → 10 × 0.7 = $7M.

Labor is 15 % more → 20 × 1.15 = $23M.

So the answer is Shipping = $7M; Labor = $23M.