Last visit was: 01 May 2026, 05:28 It is currently 01 May 2026, 05:28
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
ExpertsGlobal5
User avatar
Experts' Global Representative
Joined: 10 Jul 2017
Last visit: 01 May 2026
Posts: 6,297
Own Kudos:
Given Kudos: 45
Location: India
GMAT Date: 11-01-2019
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 6,297
Kudos: 6,256
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
rajdeep212003
Joined: 11 Dec 2024
Last visit: 01 May 2026
Posts: 74
Own Kudos:
12
 [1]
Given Kudos: 13
Location: India
Products:
Posts: 74
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Adit_
Joined: 04 Jun 2024
Last visit: 01 May 2026
Posts: 752
Own Kudos:
249
 [1]
Given Kudos: 124
Products:
Posts: 752
Kudos: 249
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
BongBideshini
Joined: 25 May 2021
Last visit: 01 May 2026
Posts: 162
Own Kudos:
Given Kudos: 81
Location: India
Concentration: Entrepreneurship, Marketing
GPA: 3.8
WE:Engineering (Government)
Products:
Posts: 162
Kudos: 125
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let's take total work = 36 units
So:
  • A = 6 units/hr
  • B = 3 units/hr
  • C = 2 units/hr
    Rate = 6 + 3 + 2 = 11 units/hr
First 2 hours: A + B + C working
Rate = 6 + 3 + 2 = 11 units/hr
Work done in 2 hours:
2 × 11 = 22 units
Remaining:
36 - 22 = 14 units

Next 1 hour: B + C working
Rate = 3 + 2 = 5 units/hr
Work done:
5 units
Remaining:
14 - 5 = 9 units

Now only C works
Rate = 2 units/hr
Time needed for 9 units:
9/2 = 4.5 hours

Total time:
2 + 1 + 4.5 = 7.5 hours
Started at 1200 hrs
After 7 hours 30 minutes = 1930 hrs

Answer: E

ExpertsGlobal5
Working alone, machines A, B, and C can complete a task in 6, 12, and 18 hours respectively. All three machines were started together to complete the task but machine A was switched off after 2 hours and machine B was also switched off after another 1 hour. Machine C completed the remaining task. If the work was started at 1200 hrs, at what time did the work get over?

A. 1630 hrs
B. 1700 hrs
C. 1730 hrs
D. 1830 hrs
E. 1930 hrs

Experts' Global
This Daily Butler Question was provided by Experts' Global
Sponsored


­
Moderators:
Math Expert
109989 posts
Tuck School Moderator
852 posts