Last visit was: 21 Apr 2026, 03:35 It is currently 21 Apr 2026, 03:35
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Elite097
Joined: 20 Apr 2022
Last visit: 04 Feb 2026
Posts: 739
Own Kudos:
568
 [1]
Given Kudos: 346
Location: India
GPA: 3.64
Posts: 739
Kudos: 568
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Rohan271
Joined: 10 Apr 2023
Last visit: 30 Jan 2026
Posts: 86
Own Kudos:
Given Kudos: 97
Location: India
Posts: 86
Kudos: 32
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Invincible_147
Joined: 29 Sep 2023
Last visit: 17 Apr 2026
Posts: 72
Own Kudos:
Given Kudos: 169
GMAT Focus 1: 575 Q77 V81 DI78
GMAT Focus 1: 575 Q77 V81 DI78
Posts: 72
Kudos: 64
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Jayesh20201
Joined: 18 Sep 2023
Last visit: 02 Dec 2025
Posts: 10
Own Kudos:
Given Kudos: 45
Posts: 10
Kudos: 8
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Th
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

This question is Tricky, especially because there are 2 common types of mistakes that you can make that can hamper your progress:
1) Not understanding the statement " Machine B stopped 15 hours before the task was completed"
2) Not being able to plot the question appropriately

I follow this method (Note: create a common denominator to solve faster) (Bold is what you have to solve for)
RateTimeWork
A1/50 (6/300) Units of Work per hour50 Hours1 Units
B1/60 (5/300) Units of Work per hour60 Hours1 Units
C1/75 (4/300) Units of Work per hour75 Hours1 Units
A+B+C(6+5+4)/300 10 Hours150/300 Work done
CMentions that C worked alone since B worked for for total -15 Hours after A left
4/300
15 Hours60/300 Work done
B+C(5+4)/300 Units of Work Per HourCalculate from Work and Rate 10 Hours 300-(150+60)/300 = 90/300 Units Pending


Therefore, total Units of work = 10+15+10 = 45 Hours (E)
User avatar
Shruuuu
Joined: 21 Nov 2023
Last visit: 19 Jan 2026
Posts: 70
Own Kudos:
Given Kudos: 99
Location: India
Schools: ISB '27 (A)
GMAT Focus 1: 655 Q83 V86 DI78
Schools: ISB '27 (A)
GMAT Focus 1: 655 Q83 V86 DI78
Posts: 70
Kudos: 95
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Time taken by each machine to complete the task :
A = 50; B = 60 & C = 75
Let the total work be 300..... (LCM of 50, 60 & 75)
Work per hour by each machine :
A = 6; B = 5 & C = 4

Let the total time taken be 't'
(6*10) + (5(t-15)) + 4t = 300
60 + 5t - 75 + 4t = 300
9t = 315
t = 45 hours

IMO E
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
tgsankar10
Joined: 27 Mar 2024
Last visit: 15 Apr 2026
Posts: 281
Own Kudos:
400
 [1]
Given Kudos: 85
Location: India
Posts: 281
Kudos: 400
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate of Machine A \(=\frac{1}{50}\)

Rate of Machine B \(= \frac{1}{60}\)

Rate of Machine C \(= \frac{1}{75}\)

Total time taken for work, t

sum of work done by individual machines = 1

Work done by \(A=\frac{10}{50}=\frac{1}{5}\)

Work done by \(B=\frac{t-15}{60}\)

Work done by \(C=\frac{t}{75}\)

\(\frac{1}{5}+\frac{t-15}{60}+\frac{t}{75}=1\)

\(\frac{5t-75+4t}{300}=\frac{4}{5}\)

\(9t=315\)

\(t=35\)

Answer: C
User avatar
Mantrix
Joined: 13 May 2023
Last visit: 20 Apr 2026
Posts: 253
Own Kudos:
132
 [1]
Given Kudos: 44
Location: India
GMAT Focus 1: 595 Q87 V75 DI77
GMAT Focus 2: 635 Q82 V82 DI80
GPA: 9
GMAT Focus 2: 635 Q82 V82 DI80
Posts: 253
Kudos: 132
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Please find the attached solution
Attachments

WhatsApp Image 2024-12-27 at 13.49.55_8b9b9191.jpg
WhatsApp Image 2024-12-27 at 13.49.55_8b9b9191.jpg [ 635.88 KiB | Viewed 754 times ]

WhatsApp Image 2024-12-27 at 13.49.55_8b9b9191.jpg
WhatsApp Image 2024-12-27 at 13.49.55_8b9b9191.jpg [ 635.88 KiB | Viewed 754 times ]

User avatar
D3N0
Joined: 21 Jan 2015
Last visit: 19 Mar 2026
Posts: 585
Own Kudos:
Given Kudos: 132
Location: India
Concentration: Operations, Technology
GMAT 1: 620 Q48 V28
GMAT 2: 690 Q49 V35
WE:Operations (Retail: E-commerce)
Products:
GMAT 2: 690 Q49 V35
Posts: 585
Kudos: 607
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Ans: 25 Hrs
Lets say total hrs required = t

then 10(A+B+C) + (B+C) * (t-15) + 15C = 1
first simplify this in ABC terms and make it in t = ###/### form

this will give t = 25

Or Another solution:

C worked for 15 hrs so completed 15/75 = 1/5 part of the work alone --> Remaining 4/5th
ABC together worked for 10 hrs so (1/50 +1/60+1/75) = 1/2 they completed half of the work --> Remaining 3/10
from this (1/60 +1/75) (t-15) = 3/10
(t-15) = 3/10 * (60*75)/135
t-15 = 10
t= 25 hrs
User avatar
prantorboni
Joined: 28 Nov 2020
Last visit: 03 Nov 2025
Posts: 147
Own Kudos:
Given Kudos: 221
Products:
Posts: 147
Kudos: 150
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A, B, C together work for 10 hours,

(1/50+1/60+1/70)10
=1/2

C works for 15 hour alone,
1/75x15=1/5

Total work completed, 1/2+1/5= 3/5, remaining= 2/5 which done by B&C.

B & C completed work in 1 hour,

1/60+1/75
=3/100

To, complete 2/5 required hours,

100/3x2/5
=40/3
=13.++++

So, entire work will be completed in 10+15+13.+++
38+++

Answer: D. 40
User avatar
jkkamau
Joined: 25 May 2020
Last visit: 21 Apr 2026
Posts: 226
Own Kudos:
190
 [1]
Given Kudos: 142
Location: Kenya
Schools: Haas '25
GMAT 1: 730 Q50 V46
GPA: 3.5
Products:
Schools: Haas '25
GMAT 1: 730 Q50 V46
Posts: 226
Kudos: 190
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate A = 1/50
Rate B= 1/60
Rate C= 1/75
In one hour the three will have completed 1/50+1/60+1/75= 1/2 of the work
Since Machine B stopped at some point leaving machine C to work alone for 15 hours, the work covered by C for the 15 hours was 15x1/75= 1/5
So the work that was done by both B&C was 1-(1/2+1/5)= 3/10
Divide the work by the combined rate of both C&B= (3/10)/3/100= 10 hours
Total time equals= 10+15+10= 35 hours
C
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
dquyen1011
Joined: 12 Sep 2024
Last visit: 24 Mar 2025
Posts: 2
Given Kudos: 2
Posts: 2
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
the answer is 35, equivalent to answer C
User avatar
LastHero
Joined: 15 Dec 2024
Last visit: 12 Dec 2025
Posts: 134
Own Kudos:
147
 [1]
Given Kudos: 1
Posts: 134
Kudos: 147
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A work=10/50
B work=(time-15)/60
C work=time/75

All together:
1/5+(time-15)/60+time/75=1

Solving:
9*time=315

time=35

Answer C
User avatar
pintukr
Joined: 03 Jul 2022
Last visit: 20 Apr 2026
Posts: 1,729
Own Kudos:
1,148
 [1]
Given Kudos: 24
GMAT 1: 680 Q49 V34
Products:
GMAT 1: 680 Q49 V34
Posts: 1,729
Kudos: 1,148
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45


Suppose, Task = 300 units

Time taken (hrs) Rate(units/hr)
Machine A -> 50 6
Machine B -> 60 5
Machine C -> 75 4

In first 10 hrs (all A, B and C work) ----> 10 * (6 + 5 + 4) = 150 units................(1)

In last 15 hrs (only C works) ----> 15 * (4) = 60 units.................(2)



thus, in middle T hrs (suppose), work completed = 300 - (150 + 60) = 90 units
in T hrs, only B & C work, so Rate = (5+4) units/hr = 9 units/hr

So, T = 90 / 9 = 10 hrs...................................................................................(3)


Using (1), (2) and (3)

Total time taken = 10 + 15 + 10 = 35 hrs


(C) is the CORRECT answer
User avatar
SunnyPoddar
Joined: 21 Nov 2020
Last visit: 09 Apr 2026
Posts: 29
Own Kudos:
24
 [1]
Given Kudos: 2
Posts: 29
Kudos: 24
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

If we consider the total unit of work to be 1.

Rate of A = 1/50
Rate of B = 1/60
Rate of C = 1/75

Given A worked for 10 hours = 10 * (1/50) = 1/5
Given B worked till 15 hours before the Total time = t-15 * (1/60)
Given C worked complete time = t * (1/75)
1/5 + (t-15)/60 + t/75 = 1

Least common denominator of 5, 60, 75 is 300.

By multiplying it to the equation and further solving it we get t=35
User avatar
Nsp10
Joined: 22 May 2023
Last visit: 30 Mar 2026
Posts: 125
Own Kudos:
91
 [1]
Given Kudos: 112
Location: India
Schools: IE Schulich
GPA: 3.0
Products:
Schools: IE Schulich
Posts: 125
Kudos: 91
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
we know work=rate*time,
so if work =1 indicates the whole completed work, then rate =1/time

Rate of Machine A=1/50
Rate of Machine B=1/60
Rate of Machine A=1/75,

we know the total work they have to do is 1,
hence
Work done by A{for 10 hours}+ Work done by B{let the total time work done by C=t hours so B would do t-15}+ Work done by C =1
10*1/50+(t-15)*1/60+t*1/75=1
so t from here will be 35 hours,

Method 2
together they can do work will be equal to the rates of A and B and C
thus Rate of all together =Rate A+Rate B+Rate C
=1/50+1/60+1/70,
now A+B+C have done 10 hours of work so work completed till first 10 hours we can calculate
which is Rate{ABC}*Time {which will come out as 1/2 after calculation} ,
now the remaining work will be 1-1/2=1/2
for this remaining work Machine C has used let T hours {as machine C is doing till last}so Machine B must have done T-15 hrs.
so
Rate{BC}*T-15+Rate C* T=1/2
this will again give us T which is 35 Hrs.
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
Karanjotsingh
Joined: 18 Feb 2024
Last visit: 03 Oct 2025
Posts: 139
Own Kudos:
95
 [1]
Given Kudos: 362
Location: India
Concentration: Finance, Entrepreneurship
Posts: 139
Kudos: 95
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Solve this step by step in simple terms.
Given:
  • Machine A: Completes the task in 50 hours.
  • Machine B: Completes the task in 60 hours.
  • Machine C: Completes the task in 75 hours.
  • Machine A stops after 10 hours.
  • Machine B stops 15 hours before the task is finished.
Let's Find:
Total time (T) to complete the task.
Step-by-Step Solution:
  1. Calculate Work Rates:
    • Machine A: 1/50 of the task per hour.
    • Machine B: 1/60 of the task per hour.
    • Machine C: 1/75 of the task per hour.
  2. Work Done in Different Periods:
    • First 10 Hours (All three machines working):
      (1/50 + 1/60 + 1/75) × 10 = 15/300 × 10 = 1/20 × 10 = 0.5 tasks
    • From 10 Hours to T−15T - 15 Hours (Machines B and C working):
      (1/60 + 1/75) × (T − 25) = 9/300 × (T − 25) = 3/100 × (T−25)
    • Last 15 Hours (Only Machine C working):
      1/75 × 15 = 0.2 tasks
  3. Total Work Done:
    0.5 + 3/100(T − 25) + 0.2 = 1 task
    0.7 + 3/100(T − 25) = 1
    3/100(T − 25) = 0.3
    3(T − 25) = 30
    T − 25 = 10
    T = 35 hours
Answer:
C. 35
User avatar
Lizaza
Joined: 16 Jan 2021
Last visit: 29 Mar 2026
Posts: 240
Own Kudos:
282
 [1]
Given Kudos: 7
GMAT 1: 710 Q47 V40
GMAT 1: 710 Q47 V40
Posts: 240
Kudos: 282
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Productivity of the machines is: \(a=1/50, b=1/60\) and \(c=1/75\)

All machines together completed the tasks, and each worked for a certain period of time:
\(1=t*c+10a+(t-15)b=t(c+b) + 1/5-1/4\)
From there, \(t(c+b)=t(1/75+1/60) = 9t/300=3t/100\)

And finally \(1+0.25-0.2=1.05=\frac{3t}{100}\)
And \(t=\frac{100*1.05}{3}=35\) and the answer is C.
User avatar
satish_sahoo
Joined: 02 Jul 2023
Last visit: 21 Jul 2025
Posts: 153
Own Kudos:
171
 [1]
Given Kudos: 162
Posts: 153
Kudos: 171
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate of A alone= \(\frac{1}{50}\)
Rate of B alone= \(\frac{1}{60}\)
Rate of C alone= \(\frac{1}{75}\)

Combined rate= \(\frac{1}{20}\)
Let the total time be \(t\)

Work done by A.B,C in 10 hours = \(10*\frac{1}{20}= \frac{1}{2}\) ...so half the task was completed

B&C together worked for a total of \(t-25\) hours, which is \((t-25)*\frac{3}{100}\)

As per question,
Work done by A,B,C in 10 hours + Work done by B&C in t-25hours + Work done by C alone in 15 hours= 1
\(\frac{1}{2} + (t-25)*\frac{3}{100} + 15*\frac{1}{75} = 1\)
\(t=35\)

IMO C
User avatar
Mardee
Joined: 22 Nov 2022
Last visit: 02 Feb 2026
Posts: 225
Own Kudos:
191
 [1]
Given Kudos: 20
Posts: 225
Kudos: 191
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Work rate of machine A/hr = 1/50
Work rate of machine B/hr = 1/60
Work rate of machine C/hr = 1/75


Work done in first 10 hrs together = 10 x (1/50+1/60+1/75) = 1/2 = 0.5
Machine A stops after 10hrs,
Combined work rate of B and C = 1/60 + 1/75 = 3/100

Now,
Total time required to finish the task = T
=> Machine B and C work together for the time = T - 10 - 15= T -25 (Since Machine C works for the final 15hrs alone)

Work done by C = 1/75 x 15 = 1/5
Total work done by B and C together = 1 - (0.5 +0.2) = 0.3
=> 3/100 x t = 3/10
=> t = 10hrs

C. Total time = 10+10+15 = 35hrs
User avatar
rns2812
Joined: 10 Nov 2024
Last visit: 28 Aug 2025
Posts: 50
Own Kudos:
51
 [1]
Given Kudos: 14
Posts: 50
Kudos: 51
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let efficiency of A, B and C be 'a', 'b', 'c' respectively
Assume work need to be done is 'W' and is completed in 'x' hrs

a * 50 = b * 60 = c * 75 = W

Given

a * 10 + b * (x - 15) + c * x = W
\(\\
\\
\frac{W}{5} + \frac{W}{60 }(x - 15) + \frac{W}{75 }* x = W\\
\\
\frac{4}{5 }= \frac{x}{60 }- \frac{1}{4} + \frac{x}{75 }\\
\\
\frac{4}{5} + \frac{1}{4} = \frac{(5x + 4x)}{300 }\\
\\
\frac{21}{20 }= \frac{(9x)}{300 }\\
\\
\)

7 * 5 = x = 35

OPTION C


Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

   1   2   3   4   
Moderators:
Math Expert
109718 posts
Tuck School Moderator
853 posts