Last visit was: 14 Jul 2025, 15:27 It is currently 14 Jul 2025, 15:27
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 14 Jul 2025
Posts: 102,570
Own Kudos:
741,407
 [4]
Given Kudos: 98,182
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 102,570
Kudos: 741,407
 [4]
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 14 Jul 2025
Posts: 102,570
Own Kudos:
Given Kudos: 98,182
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 102,570
Kudos: 741,407
Kudos
Add Kudos
Bookmarks
Bookmark this Post
General Discussion
User avatar
siddhantvarma
Joined: 12 May 2024
Last visit: 14 Jul 2025
Posts: 521
Own Kudos:
Given Kudos: 190
GMAT Focus 1: 635 Q87 V82 DI75
Products:
GMAT Focus 1: 635 Q87 V82 DI75
Posts: 521
Kudos: 579
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
GraCoder
Joined: 15 Dec 2024
Last visit: 15 Jun 2025
Posts: 75
Own Kudos:
69
 [1]
Given Kudos: 19
Posts: 75
Kudos: 69
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

Let the total time be t, therefore A has worked for 10 hours, B has worked for t - 15, and C has worked for t
10/50 + (t-15)/60 + t/75 = 1
Solving gives t = 35
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 14 Jul 2025
Posts: 5,701
Own Kudos:
5,222
 [1]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,701
Kudos: 5,222
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed.

How many total hours were required to finish the task?

Let's assume that total x hours were required to finish the task.

10/50 + (x-15)/60 + x/75 = 1

.2 + x/60 - .25 + x/75 = 1
x/60 + x/75 = 1.05 = 21/20
9x/300 = 21/20
x = 35 hours

IMO C
User avatar
Sanjay9822
Joined: 20 Dec 2024
Last visit: 26 Jan 2025
Posts: 27
Own Kudos:
Given Kudos: 6
Posts: 27
Kudos: 17
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



Step 1: Machine Work Rates
Machine A: 1 task in 50 hours → Rate = 1/50
Machine B: 1 task in 60 hours → Rate = 1/60
Machine C: 1 task in 75 hours → Rate = 1/75
Step 2: Work Done in First 10 Hours
All three machines work together for 10 hours.
Combined rate of all 3 machines:
1/50 + 1/60 + 1/75 = 1/20 (after finding the common denominator).
In 10 hours, work done = 10 * (1/20) = 1/2 of the task.
Step 3: Work Done After 10 Hours
After 10 hours, Machine A stops. Machines B and C continue.
Combined rate of B and C:
1/60 + 1/75 = 9/300 = 3/100.
Remaining work = 1/2 of the task.
Time to finish = (1/2) ÷ (3/100) = 50/3 ≈ 16.67 hours.
Step 4: When Does Machine B Stop?
Machine B stops 15 hours before the task is finished.
So, Machine B works for 16.67 - 15 = 1.67 hours after 10 hours.
Step 5: Total Time to Finish Task
Machine A worked for 10 hours.
Machine B worked for 1.67 hours.
Machine C worked for 16.67 hours.
Total time = 10 + 16.67 = 26.67 hours ≈ 30 hours.

Answer:
30 hours.
User avatar
RahulPMT
Joined: 20 Dec 2024
Last visit: 05 Jul 2025
Posts: 42
Own Kudos:
42
 [1]
Given Kudos: 3
Products:
Posts: 42
Kudos: 42
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate of A=1/50, B=1/60, C=1/75

Rate*time = work

10*(1/50) + (t-15)*(1/60) + t*(1/75) = 1

on simplification we get t=35
avatar
ManifestDreamMBA
Joined: 17 Sep 2024
Last visit: 13 Jul 2025
Posts: 977
Own Kudos:
634
 [2]
Given Kudos: 192
Products:
Posts: 977
Kudos: 634
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Rate for all 3 together = 1/50 + 1/60 + 1/75 = 1/20
Rate for B and C together = 1/60 + 1/75 = 3/100

Work by all 3 = 1/20*10 = 1/2, i.e. 50% is done by all 3 in 10hrs

Let total number of hours to complete the remaining work be x, then B and C worked together for x-15 hrs

1/2 = (x-15)*(3/100) + 15* 1/75
Solving this we get x = 25 hrs

Total therefore is 35hrs
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
hr1212
User avatar
GMAT Forum Director
Joined: 18 Apr 2019
Last visit: 14 Jul 2025
Posts: 346
Own Kudos:
511
 [1]
Given Kudos: 1,233
GMAT Focus 1: 775 Q90 V85 DI90
Products:
GMAT Focus 1: 775 Q90 V85 DI90
Posts: 346
Kudos: 511
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

Let total hours taken be T

Then,

10/50 + (T - 15)/60 + T/75 = 1
\(\frac{10 *6 + (T - 15)*5 + 4T}{300} = 1\)
60 + 5T - 75 + 4T = 300
9T = 315
T = 35

Answer: C
User avatar
miag
Joined: 10 Dec 2023
Last visit: 13 Jun 2025
Posts: 124
Own Kudos:
48
 [1]
Given Kudos: 134
Location: India
Concentration: Marketing, Sustainability
GMAT Focus 1: 675 Q87 V83 DI80
Products:
GMAT Focus 1: 675 Q87 V83 DI80
Posts: 124
Kudos: 48
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A:
w in 50 hours
R(A) = w/50 in 1 hr

B:
W in 60 hours
R(B) = w/60

C:
R(C) = w/75

Lets say the work was completed in t hours, then B worked for t-15 hours
W = 10*(w/50) + (t-15)*(w/60) + (w/75)*t
1 = 1/5 + (t-15)/60 + (t/75)

4/5 = 1/15 ((t-15)/4 + (t)/5)
4 = 1/3*20 (5t-75 +4t)
4*20*3 = 9t-75
(240+75)/9 = t
315/9 = t = 35 hours
User avatar
nousernamefine
Joined: 14 Jan 2024
Last visit: 10 Jun 2025
Posts: 34
Own Kudos:
28
 [1]
Given Kudos: 126
Location: India
GPA: 4
Posts: 34
Kudos: 28
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
better take eg of number of units= 3000

A/hr=60
B/hr= 50
C/hr=40

(A+B+C)/hr= 150

Total t hrs

A= 10*60= 600
B= (T-15)*50= 50T-750
C=T*40= 40T

600+50T-750+40T=3000
90T= 3000+150
T= 35 hrs

Ans C
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
Microice
Joined: 26 Feb 2024
Last visit: 13 Jun 2025
Posts: 1
Own Kudos:
2
 [1]
Given Kudos: 11
Posts: 1
Kudos: 2
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Time taken for completion aloneWork done in 1 hr
A501/50
B601/60
C751/75

First 10 hours all machine worked.
work completed = work completed by A + B + C
= 10(1/50 + 1/60 + 1/75)
=2(1/10 + 1/12 +1/15)
=2 (18+15+12)/180
= 0.5 = 50%
Last 15 hours, only machine C worked
work completed in last 15 hours = work done by C
= 15 (1/75) = 0.2 = 20 %
Remaining work = 30%, completed by B & C together
Work done in an hour by B & C together = 1/60 + 1/75 = 3/100 = 3 %
Time taken to complete 30% of work = 30/3% = 10 hours

Total time taken = 10 + 15 + 10 = 35 hours

Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

User avatar
aviraj1703
Joined: 27 May 2024
Last visit: 10 Mar 2025
Posts: 110
Own Kudos:
121
 [1]
Given Kudos: 6
Posts: 110
Kudos: 121
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Initial rates (per hour):
A: 1/50
B: 1/60
C: 1/75

Phase 1 (0-10h): All machines
Work done = (1/50 + 1/60 + 1/75) × 10

Phase 2: B and C only
Until B stops, rate = 1/60 + 1/75

Phase 3: C only
Last 15h at rate 1/75

Calculate total work = 1
10(1/50 + 1/60 + 1/75) + t(1/60 + 1/75) + 15(1/75) = 1
where t = time with B and C

t = 10 hours
Total time = 10 + 10 + 15 = 35 hours

Answer: C. 35
User avatar
missionmba2025
Joined: 07 May 2023
Last visit: 12 Jul 2025
Posts: 352
Own Kudos:
420
 [1]
Given Kudos: 50
Location: India
Products:
Posts: 352
Kudos: 420
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 


Total units of work = LCM (50, 60 , 75 ) = 300

A can complete 300/50 = 6 units of work in one hour
B can complete 300/60 = 5 units of work in one hour
C can complete 300/75 = 4 units of work in our hour

In 10 hours, total work completed = 60 + 50 + 40 = 150

Work remaining = 150

Let's assume it took t more hours to complete the work after machine A stopped working

5(t-15) + 4t = 150

5t - 75 + 4t = 150

t = 25

Total Hours Needed = 25 + 10 = 35

Option C
User avatar
HarshaBujji
Joined: 29 Jun 2020
Last visit: 14 Jul 2025
Posts: 657
Own Kudos:
854
 [1]
Given Kudos: 243
Location: India
Products:
Posts: 657
Kudos: 854
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

In a factory, Machine A, working alone, can complete a task in 50 hours, Machine B, working alone, can complete the same task in 60 hours, and Machine C, working alone, can complete it in 75 hours. All three machines started working together on the task. However, Machine A stopped working after 10 hours, and Machine B stopped 15 hours before the task was completed. How many total hours were required to finish the task?

A. 25
B. 30
C. 35
D. 40
E. 45

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 

Let the entire work be 300 units. (LCM of all 3)

So A can do 6 u, B can do 5 u, & C can do 4 u.

For first 10 hrs work completed = 15u * 10 = 150u.
Last 15 hrs only C worked = 4u*15 = 60u.

So for t hrs in b/w B & C worked. = 9u*t.

So we know total work is 300u=150u+60u+9tu

=> t=10 hrs.

Total hrs = 10+15+10 =35hrs.

IMO C
User avatar
AVMachine
Joined: 03 May 2024
Last visit: 14 Jul 2025
Posts: 201
Own Kudos:
152
 [1]
Given Kudos: 40
Posts: 201
Kudos: 152
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A's speed = 1/50;
B's speed = 1/60;
C's speed = 1/75;

Assume, t is the total time required to complete the task, working together.

(10 * 1/50) + (t-15)(1/60) + t * 1/75 = 1

(60 + 5t - 75 + 4t) / 300 = 1

9t = 315; t = 35;
User avatar
Yaswanth9696
Joined: 24 Sep 2024
Last visit: 22 Feb 2025
Posts: 39
Own Kudos:
28
 [1]
Given Kudos: 28
Posts: 39
Kudos: 28
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let X be the total no of hours. From the given info

A- worked for 10 hours
B - worked for X-15 hours
C- Worked for X hours

We know the rates of work of each machine as 1/50, 1/60 and 1/75 for A,B and C respectively.

Set up the equation as

10(1/50)+X(1/75)+((X-15)(1/60))=1
---> 60+4X+5X-75=300
--->9X=315---> X=35 hours.
User avatar
Heix
Joined: 21 Feb 2024
Last visit: 13 Jul 2025
Posts: 191
Own Kudos:
128
 [1]
Given Kudos: 51
Location: India
Concentration: Finance, Entrepreneurship
GMAT Focus 1: 485 Q76 V74 DI77
GPA: 3.4
WE:Accounting (Finance)
Products:
GMAT Focus 1: 485 Q76 V74 DI77
Posts: 191
Kudos: 128
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
1. First, let's calculate the rates of each machine:

Machine A: 1/50 task/hour

Machine B: 1/60 task/hour

Machine C: 1/75 task/hour

2. Let's say the total time to complete the task is x hours. We know that:

Machine A works for 10 hours

Machine B works for (x- 15) hours

Machine C works for x hours

3. Now we can set up an equation. The total work done by all machines must equal 1 task:

(1/50 × 10) + (1/60 × (x - 15)) + (175 × x) = 1

4. Let's solve this equation:

1/5 + (x - 15/60 + x/75 = 1

15/75 + (75x - 1125/4500 + 60x/4500 = 1

675 + 75x - 1125 + 60x= 4500

135x = 4500

135x= 4950

x=4950/135 = 36.67

5. The closest answer to 36.67 is 35 hours.

Therefore, the correct answer is C. 35 hours.
User avatar
A_Nishith
Joined: 29 Aug 2023
Last visit: 12 Jul 2025
Posts: 414
Own Kudos:
189
 [1]
Given Kudos: 16
Posts: 414
Kudos: 189
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Step 1: Define the rates of work for each machine
Machine A's rate of work: 1/50 tasks per hour.
Machine B's rate of work: 1/60 tasks per hour.
Machine C's rate of work: 1/75 tasks per hour.

Step 2: Work done by Machine A
Machine A works for only the first 10 hours. The work done by Machine A is:
Work by A= 10×1/50 = 10/50 = 1/5

Step 3: Represent the total work
The total task requires 1 complete unit of work.

Remaining work after Machine A stops:
Remaining work=1−1/5 = 4/5​

Step 4: Represent Machine B's working time
Machine B stops working 15 hours before the task is completed.
Let T be the total time required to finish the task.
Then Machine B works for: T−15hours.

Step 5: Express total work done by all machines
The total work is completed by:
Machine A in 10 hours (1/5)
Machine B in T−15 hours.
Machine C in T hours.
The total work equation becomes:
1/5 + (1/60)(T−15)+ (1/75)T = 1

Step 6: Solve for T
Simplify each term:
1/60 (T−15)= T/60 − 15/60 = T/60 − 1/4

1/75 * T = T/75
Substitute these into the equation:
1/5 + (T/60) − 1/4 + (T/75) =1

Thus, −(1/20) + (T/60) + (T/75) = 1

Combine terms involving
T using the least common denominator of 60 and 75 (which is 300):
T/60 + T/75 = 5T/300 + 4T/300 = 9T/300 = 3T/100

The equation becomes:
−1/20 + 3T/100 = 1

Solve for T:
T= 105/3 = 35

Step 7: Verify the answer
The total time required to complete the task is: 35hours
User avatar
Krunaal
User avatar
PS Forum Moderator
Joined: 15 Feb 2021
Last visit: 14 July 2025
Posts: 691
Own Kudos:
722
 [1]
Given Kudos: 240
Status:Under the Square and Compass
Location: India
WE:Marketing (Internet and New Media)
Products:
Posts: 691
Kudos: 722
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let the Total Work (W) be 300
Time taken by A = 50 hrs, A's rate of work = 6
Time taken by B = 60 hrs, A's rate of work = 5
Time taken by C = 75 hrs, A's rate of work = 4

Rate of work of A + B + C = 15

A stopped after 10 hours, work completed in 10 hrs = 15*10 = 150

B stopped 15 hours before the task was completed, therefore C worked alone for 15 hours, work completed by C alone = 4*15 = 60

Total work completed uptil is 150 + 60 = 210, it means B and C together completed 90 units of work. Rate of work of B and C = 9, time taken by them to complete 90 units = 10 hours.

Total time taken = Time taken by A, B and C + Time taken by B, and C + Time taken by C alone
Total time taken = 10 + 10 + 15 = 35

Answer C.
 1   2   3   4   
Moderators:
Math Expert
102570 posts
PS Forum Moderator
691 posts