Last visit was: 28 Apr 2024, 09:18 It is currently 28 Apr 2024, 09:18

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92974
Own Kudos [?]: 619662 [7]
Given Kudos: 81613
Send PM
Manager
Manager
Joined: 08 Sep 2008
Posts: 105
Own Kudos [?]: 96 [2]
Given Kudos: 17
Location: India
Concentration: Operations, General Management
Schools: ISB '20
GPA: 3.8
WE:Operations (Transportation)
Send PM
Director
Director
Joined: 04 Sep 2015
Posts: 552
Own Kudos [?]: 436 [0]
Given Kudos: 123
Location: India
WE:Information Technology (Computer Software)
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 03 Jun 2019
Posts: 5345
Own Kudos [?]: 3972 [1]
Given Kudos: 160
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Send PM
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
1
Bookmarks
Bunuel wrote:
If it takes 50 workers 8 hours to build a log cabin, how long would it have taken 30 workers to build the same cabin?

(A) 9 hrs 36 min.

(B) 10 hrs 24 min.

(C) 12 hrs 24 min.

(D) 12 hrs 40 min.

(E) 13 hrs 20 min.


50 Workers take 8 hours
=> 30 workers will take = \(\frac{50}{30}*8 = \frac{40}{3} = 13 \frac{1}{3}\) hours
13 hours 20 mins

IMO E
Current Student
Joined: 16 Jan 2019
Posts: 631
Own Kudos [?]: 1444 [0]
Given Kudos: 144
Location: India
Concentration: General Management
GMAT 1: 740 Q50 V40
WE:Sales (Other)
Send PM
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
Let the total number of work be 400 logs

50W----8H----400L
50W----1H----50L
1W-----1H-----1L
30W----\(x\)H----400L

x=400/30=13.33 hours

Answer is (E)
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18769
Own Kudos [?]: 22073 [0]
Given Kudos: 283
Location: United States (CA)
Send PM
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
Expert Reply
Bunuel wrote:
If it takes 50 workers 8 hours to build a log cabin, how long would it have taken 30 workers to build the same cabin?

(A) 9 hrs 36 min.

(B) 10 hrs 24 min.

(C) 12 hrs 24 min.

(D) 12 hrs 40 min.

(E) 13 hrs 20 min.


The rate for 50 workers is 1/8. The rate for 1 worker is (1/8)/50 = 1/400, and the rate for 30 workers is 30/400 = 3/40.

Thus it takes 30 workers 1/(3/40) = 40/3 = 13 ⅓ hours = 13 hours 20 minutes.

Alternate Solution:

The total number of hours needed to build the cabin is 50 x 8 = 400 hours. So if there are 30 workers, it will take 400/30 = 13.333 hours = 13 ⅓ hours = 13 hours, 20 minutes.

Answer: E
VP
VP
Joined: 18 Dec 2017
Posts: 1169
Own Kudos [?]: 991 [0]
Given Kudos: 421
Location: United States (KS)
GMAT 1: 600 Q46 V27
Send PM
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
Bunuel wrote:
If it takes 50 workers 8 hours to build a log cabin, how long would it have taken 30 workers to build the same cabin?

(A) 9 hrs 36 min.

(B) 10 hrs 24 min.

(C) 12 hrs 24 min.

(D) 12 hrs 40 min.

(E) 13 hrs 20 min.


50*8=400 man hours. We have 30 men. 400/30 is 13.33, which is 13hours 20minutes.
Hence E
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32723
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: If it takes 50 workers 8 hours to build a log cabin, how long would it [#permalink]
Moderators:
Math Expert
92974 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne