Official Solution: Andy, George, and Sally are a team of consultants working on Project Alpha. They have an eight-hour deadline to complete the project. The team members work at constant rates throughout the eight-hour period. If the team of three has to start work immediately and no one else can work on this project, will Project Alpha be completed by the deadline? (1) Sally can finish the project alone in \(4k+7\) hours, where \(k\) is a positive integer ranging from 1 to 5, inclusive.
We know Sally can finish the project in \(4k+7\) hours, but we know nothing about George's or Andy's time. If \(k = 5\), Sally can finish the work by herself in 27 hours. In this worst-case scenario, Sally alone cannot complete the project within the deadline, which means we need more information about George and Andy to determine if the team as a whole can complete the project within the deadline. Suppose Andy and George also need a considerable amount of time to finish the job by themselves, say 100 hours each. In that case, the team won't be able to complete the project by the deadline, as their combined rate of \(\frac{1}{27} + \frac{1}{100} +\frac{1}{100}\) job/hour would be less than the required rate of \(\frac{1}{8}\) job/hour. On the other hand, if Andy and George need a small amount of time to finish the job by themselves, say 1 hour each, then the team will be able to complete the project by the deadline. This is because their combined rate of \(\frac{1}{27} + \frac{1}{1} +\frac{1}{1}\) job/hour would be greater than the required rate of \(\frac{1}{8}\) job/hour. Not sufficient.
(2) Working alone, George will take \(2k+1\) hours, and Andy will take \(3+2k\) hours to complete the project, where \(k\) is a positive integer ranging from 1 to 5, inclusive.
Let's check whether George and Andy can finish the project by themselves for the greatest possible value of \(k\). We do this because if they can finish the project by themselves for the greatest possible value of \(k\), it would mean that they don't even need Sally's input to complete the project. For the maximum value of \(k = 5\), George needs \(2k+1=11\) hours and Andy needs \(3+2k=13\) hours to finish the project alone. Their combined rate is \(\frac{1}{11} + \frac{1}{13}\) job/hour. Since this is more than the required rate of \(\frac{1}{8}\) job/hour (\(\frac{1}{11} + \frac{1}{13} > (\frac{1}{16} + \frac{1}{16}=\frac{1}{8})\) ), George and Andy can complete the job by themselves irrespective of Sally's rate. Sufficient.
Answer: B