Last visit was: 18 Nov 2025, 14:03 It is currently 18 Nov 2025, 14:03
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,061
 [15]
2
Kudos
Add Kudos
13
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
778,061
 [3]
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,061
 [3]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
User avatar
Suvankar8250
Joined: 19 Nov 2022
Last visit: 15 Oct 2024
Posts: 54
Own Kudos:
73
 [3]
Given Kudos: 30
Location: India
GPA: 4
WE:Consulting (Consulting)
Posts: 54
Kudos: 73
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
wadhwakaran
Joined: 31 Mar 2022
Last visit: 22 Jul 2025
Posts: 262
Own Kudos:
241
 [2]
Given Kudos: 19
Location: India
Concentration: General Management, International Business
GMAT 1: 700 Q50 V35
GPA: 2.8
Products:
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
(1) Amy alone can complete the same task in 8 days
This statement alone is insufficient because we don't know anything about Beth. Further, we also don't know anything about the total work.

(2) Beth alone can complete the same task in 20 days
This statement is insufficient because we don't know anything about Amy. Further, we also don't know anything about the total work.

Now combining 1 and 2
Let's assume total work to be 40 units
Amy per day efficiency= 5 units
Beth per day efficiency= 2 units
Now we know that they started working alternatively
If Amy starts then
Day 1 --> 5 units
Day 2 --> 2 units
Day 3 --> 5 units
Day 4 --> 2 units
Day 5 --> 5 units
Day 6 --> 2 units
Day 7 --> 5 units
Day 8 --> 2 units
Day 9 --> 5 units
Day 10 --> 2 units
Day 11--> 5 units
Work gets completed on 11th day itself.
If Beth starts
Day 1 --> 2 units
Day 2 --> 5 units
Day 3 --> 2 units
Day 4 --> 5 units
Day 5 --> 2 units
Day 6 --> 5 units
Day 7 --> 2 units
Day 8 --> 5 units
Day 9 --> 2 units
Day 10 --> 5 units
Day 11--> 2 units
Day 12--> 3 units
work gets completed on day 12
Therefore combining 1 and 2 is also insufficient
Option E
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 18 Nov 2025
Posts: 5,793
Own Kudos:
5,508
 [1]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,793
Kudos: 5,508
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Given: Amy and Beth, both working at their respective constant rates, were assigned a task that they had to complete together. However, they decided to individually work on the task on alternate days till the task gets completed.
Asked: If they started the task from 1st of January, then on which day in January will the task get completed?

Quote:
(1) Amy alone can complete the same task in 8 days.
Since days in which Beth alone can complete the same task is unknown.
NOT SUFFICIENT

Quote:
(2) Beth alone can complete the same task in 20 days
Since days in which Amy alone can complete the same task is unknown.
NOT SUFFICIENT

(1) + (2)
Quote:
(1) Amy alone can complete the same task in 8 days.
Quote:
(2) Beth alone can complete the same task in 20 days

Case 1: Amy started on 1st of January
Task completion = 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8
Task completion requires 11 days and will be completed on 11th January.

Case 2: Beth started on 1st of January
Task completion = 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 3/40
Task completion requires 12 days and will be completed on 12th January.

NOT SUFFICIENT

IMO E
User avatar
sivatx2
Joined: 23 Oct 2015
Last visit: 27 Dec 2023
Posts: 294
Own Kudos:
277
 [1]
Given Kudos: 33
Location: United States (NH)
Concentration: Leadership, Technology
Schools: Wharton '25
WE:Information Technology (Non-Profit and Government)
Products:
Schools: Wharton '25
Posts: 294
Kudos: 277
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Condition 1:
We know Amy alone can complete within 8 days, but we don't know how long Beth can take. Then we can't find when the work will complete. Eliminate A and D.

Condition 2:
We know Beth alone can complete within 20 days, but we don't know how long Amy can take. Then we can't find when the work will complete. Eliminate B.

Condition 1 & 2:
We know amount of work both Amy and can do in a day. So,

Every 2 days, the amount of work that can complete is:
1/8 +1/20 = (5+2)/40 = 7/40


But still, we don't know who will start the work.
After 5x2= 10 days, the amount of work completed will be 5x7/40 = 35/40.
If Amy works on 11th day, then the total amount is 35/40+ 1/8 = 1. The work will be done on 11th January.
But, if Beth works on 11th day, then the total amount of work 35/40+1/20 = 37/40. The work will not complete 11th January, but will complete on 12th January.

So 2 answers are possible and we can't say when the work will complete. Eliminate option C.

Hence E is the best answer choice.
User avatar
Lizaza
Joined: 16 Jan 2021
Last visit: 17 Nov 2025
Posts: 165
Own Kudos:
219
 [1]
Given Kudos: 5
GMAT 1: 710 Q47 V40
GMAT 1: 710 Q47 V40
Posts: 165
Kudos: 219
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
When we speak about two people doing some work together, we need to know the respective speeds of both of them - otherwise, there's no way of calculating the time they need to finish the task. That being said, conditions 1 and 2 will obviously not suffice separately (options A, B and D are out).

However, will we have enough information from both conditions combined?
Amy's speed will be \(a=\frac{1}{8}=\frac{5}{40}\), and Beth's will look as follows: \(b=\frac{1}{20}=\frac{2}{40}\)

Together, in any two consecutive days, they will manage to do \(a+b=\frac{5}{40} +\frac{ 2}{40} =\frac{ 7}{40}\) of their task. Therefore, after 10 days of work, they will finish \(5*\frac{7}{40} = \frac{35}{40}\).

And here's what the trouble is: now it becomes really important, who starts to work on January 1st. If it's Amy, then on January 11th she'll finish the job.
However, if it's Beth's turn, she will only do a small part, and the task will be finished only the following day by Amy, with \(\frac{35}{40}+\frac{2}{40}+\frac{5}{40} = \frac{42}{40}\).

Therefore, even two options together aren't sufficient, so the answer is E.
User avatar
sanjitscorps18
Joined: 26 Jan 2019
Last visit: 18 Nov 2025
Posts: 635
Own Kudos:
623
 [1]
Given Kudos: 128
Location: India
Schools: IMD'26
Products:
Schools: IMD'26
Posts: 635
Kudos: 623
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas GMAT Competition with Lots of Fun

Amy and Beth, both working at their respective constant rates, were assigned a task that they had to complete together. However, they decided to individually work on the task on alternate days till the task gets completed. If they started the task from 1st of January, then on which day in January will the task get completed?

(1) Amy alone can complete the same task in 8 days
(2) Beth alone can complete the same task in 20 days

 


This question was provided by GMATWhiz
for the 12 Days of Christmas Competition.

Win $30,000 in prizes: Courses, Tests & more

 


(1) Amy alone can complete the same task in 8 days
Cannot find the days required to complete the task as the rate of work of Beth is not available

(2) Beth alone can complete the same task in 20 days
Cannot find the days required to complete the task as the rate of work of Amy is not available

Combining (1) and (2) we get the following scenarios:

a ) Amy starts on the first day and ends on the last day
Let's suppose Beth takes 'n' days to complete, hence
=> (n+1)(1/8) +n(1/20) = 1
=> n(7/40) = 7/8
=> n = 5 days

a ) Amy starts on the first day and Beth ends on the last day
Let's suppose Beth takes 'n' days to complete, hence
=> n(1/8) +n(1/20) = 1
=> n(7/40) = 1
=> n = 40/7 ≈ 6 days

a ) Beth starts on the first day and ends on the last day
Let's suppose Amy takes 'n' days to complete, hence
=> n(1/8) + (n+1)(1/20) = 1
=> n(7/40) = 19/20
=> n = (19/20)
=> n = 38/7 ≈ 6 days

Hence we get different values for the times.

Option E
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,586
Own Kudos:
Posts: 38,586
Kudos: 1,079
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
105355 posts
496 posts