Last visit was: 22 Apr 2026, 19:16 It is currently 22 Apr 2026, 19:16
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
anhht13
Joined: 12 Oct 2017
Last visit: 23 May 2019
Posts: 25
Own Kudos:
16
 [17]
Given Kudos: 16
Posts: 25
Kudos: 16
 [17]
3
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
amanvermagmat
User avatar
Retired Moderator
Joined: 22 Aug 2013
Last visit: 28 Mar 2025
Posts: 1,142
Own Kudos:
2,973
 [10]
Given Kudos: 480
Location: India
Posts: 1,142
Kudos: 2,973
 [10]
7
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 22 Apr 2026
Posts: 22,278
Own Kudos:
26,528
 [3]
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,278
Kudos: 26,528
 [3]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
User avatar
sasyaharry
Joined: 22 Nov 2016
Last visit: 11 Mar 2023
Posts: 199
Own Kudos:
363
 [2]
Given Kudos: 49
Concentration: Leadership, Strategy
Products:
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Even if you are completely bowled over by this question, you are chance of guessing the right answer is 33.33%
The question stem already tells us that there were 5 outages. Hence, the answer is at least 5. Given the tone of the question, if you were to guess, the answer would be more than 5, either D or E.
User avatar
gracie
Joined: 07 Dec 2014
Last visit: 11 Oct 2020
Posts: 1,028
Own Kudos:
2,021
 [1]
Given Kudos: 27
Posts: 1,028
Kudos: 2,021
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
anhht13
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8

61 total days-5 outage days=56 work days
56 work days*10 workers*1/(10*112) daily rate per worker=1/2 order completed
104-61=43 total (work+outage) days remaining
let x=outage days remaining
(43-x) days*14 workers*1/(10*112) daily rate per worker=1/2 order remaining
x=3
3+5=8 total outages
E
User avatar
Raksat
Joined: 20 Feb 2017
Last visit: 13 Feb 2025
Posts: 145
Own Kudos:
531
 [2]
Given Kudos: 489
Location: India
Concentration: Operations, Strategy
WE:Engineering (Other)
Posts: 145
Kudos: 531
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
total work-day units = 112 X 10 = 1120
In 61 days , there is loss of 5 days . So actual work done = 56 X 10 = 560 work-day units.
Remaining work = 1120-560= 560 work-day units
From 62nd day total worker strength is 14. The work is completed in another 104-61 = 43 days.
therefore the total work-units by these 14 workers = 14 X 43 = 602 work -day units. Our requirement is 560, hence there must be additional power cuts during this period.
Difference = 602- 560 = 42 work-day units.
therefore no of days of additional power cut = 42/14 = 3 days
total : 5 days + 3 days = 8 days (must be the answer)
avatar
anjaliarora
Joined: 14 May 2017
Last visit: 20 Mar 2018
Posts: 3
Own Kudos:
Given Kudos: 18
Posts: 3
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8

===========
calculate total work:
total work done by 10 workers in 112 days = 10*112
Actual:
work done by 10 workers in 56 days (61-5(outage)) = 10*56

let number of outage days from 62nd day = x

no of days worked after 62nd day = 104-62+1 = 43

work done starting from 62nd day = 14 * (43-x)

10*112 = 10*56 + 14(43-x)

=> x =3

Total outage days = 3 + 5 = 8
Answer is E.
User avatar
gmatexam439
User avatar
Moderator
Joined: 28 Mar 2017
Last visit: 18 Oct 2024
Posts: 1,054
Own Kudos:
Given Kudos: 200
Location: India
Concentration: Finance, Technology
GMAT 1: 730 Q49 V41
GPA: 4
Products:
GMAT 1: 730 Q49 V41
Posts: 1,054
Kudos: 2,194
Kudos
Add Kudos
Bookmarks
Bookmark this Post
anhht13
A certain tailor shop employs 10 workers who can normally complete an ndustrial order in 112 days; however, the shop is prone to power outages, and each outages results in the loss of a full day of work. After 61 days working on a particular industrial order, the shop has had 5 power outages. At the beginning of the 62th day of work, in order to make up for the outages, the management hired 4 new workers who work at the same pace as the other employees. In the end, the order took 104 days to complete. How many power outages did the tailor shop have in total?

A. 2
B. 3
C. 5
D. 7
E. 8

Answer: E

10 people take 112 days
1 day work of 10 people=1/112
1 day work of 1 person = 1/1120

10 people work for 56 days first.
total work completed=10/1120 * 56 = 56/112
Remaining work = 1-56/112 = 56/112

14 people 1 day work = 14/1120
total days taken by 14 people to finish remaining work = (56/112)/(14/1120) = 56/112 * 1120/14 = 40

total days on which work actually happened = 40+56=96

work was eompleted in 104 days as per the question. So no work happened on 104-96=8 days
User avatar
HarshavardhanR
Joined: 16 Mar 2023
Last visit: 22 Apr 2026
Posts: 488
Own Kudos:
Given Kudos: 67
Status:Independent GMAT Tutor
Affiliations: Ex - Director, Subject Matter Expertise at e-GMAT
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 488
Kudos: 574
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Say, each worker does "p" units of work in a day.

Work = 10 x 112 x p= 1120p

In 61 days, ideally, 10 x 61 x p = 610p amount of work should have happened.
But there were 5 power outages. 1 power outage means 1 day lost.

So,
Actual days of work = 61-5 = 56.

So,
Actual work done in 61 days = 10 x 56 x p = 560p

Remaining work as of 61 days = 1120p - 560p = 560p

From day 62 onwards, there are 10+4 = 14 workers.

Ideally, how long would the remaining work (560p) take for these 14 workers?

14 x (d) x p = 560p
d = 40

Ideally, the remaining work should have taken 40 days. This brings us to a total of 61 + 40 = 101 days of total work.

But the actual number of days taken is 104.

This means that 104 - 101 = 3 days were again lost due to power outages.

The overall number of power outages = 5 (from day 1 to day 62) + 3 (from day 62 till the end) = 8 days. Choice E.


_____
Harsha