Last visit was: 23 Apr 2026, 06:42 It is currently 23 Apr 2026, 06:42
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 23 Apr 2026
Posts: 109,778
Own Kudos:
Given Kudos: 105,853
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,778
Kudos: 810,778
 [18]
1
Kudos
Add Kudos
17
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
sumitkrocks
Joined: 02 Jul 2017
Last visit: 22 Aug 2023
Posts: 637
Own Kudos:
879
 [5]
Given Kudos: 333
Location: India
Concentration: Strategy, Technology
GMAT 1: 730 Q50 V39
GMAT 2: 710 Q50 V36
Products:
GMAT 2: 710 Q50 V36
Posts: 637
Kudos: 879
 [5]
1
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
General Discussion
User avatar
rajatchopra1994
Joined: 16 Feb 2015
Last visit: 22 Jun 2024
Posts: 1,052
Own Kudos:
1,307
 [3]
Given Kudos: 30
Location: United States
Posts: 1,052
Kudos: 1,307
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
samarpan.g28
Joined: 08 Dec 2023
Last visit: 18 Feb 2026
Posts: 315
Own Kudos:
136
 [1]
Given Kudos: 1,236
Location: India
Concentration: General Management, Human Resources
GPA: 8.88
WE:Engineering (Technology)
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
A group of 20 software engineers can finish a development project in 30 days. They got a project with the deadline of 35 days. After how many days should 5 engineers be released so that the project completes on time?

(A) 5
(B) 8
(C) 10
(D) 12
(E) 15
The total time is 35 days and the total workers is 20. Say for the first t days, all 20 workers will work. Finally, for (35-t) days, only (20-5)=15 people will work.
Let us calculate the individual rate first.

20 workers' 1-day work (i.e. Rate) = 1/30 work/day
1 worker's 1-day work (i.e. Rate) = 1/600 work/day
15 workers' 1-day work (i.e. Rate) = 15/600 = 1/40 work/day

We know, Rate*Time = Work

t*(1/30) + (35-t)*(1/40) = 1
or, t/30 + (35-t)/40 = 1
Upon solving, we will get t=120-105=15 days, i.e. after 15 days, only 15 workers will work. Option (E) is correct.
User avatar
pavanhra
Joined: 20 Dec 2022
Last visit: 12 Sep 2025
Posts: 33
Own Kudos:
7
 [2]
Given Kudos: 12
Posts: 33
Kudos: 7
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Existing total Mandays 20*30 = 600

Project days extended to 35 days, New Mandays = 20*35 = 700

Excess mandays avaialble = 700-600 = 100

Total 5 people to be released 100 mandays/5 = 20 days

No of days engineers can be release 35-20 = 15 days