Alex, Beth, Charles, and Dana, each working alone at their own constant rates, can complete a certain task in 8, 20, 40, and 80 hours, respectively. The project manager will schedule them to work on the task in a repeating four-person cycle in which each person works for exactly one hour before the next person begins.
Rate of Alex= 1/8
Rate of Beth= 1/20
Rate of Charles = 1/40
Rate of Dana= 1/80
Work done in 1 complete cycle = (1/8)+(1/20)+(1/40)+(1/80)= 17/80
Work done in 2 complete cycles = 2*(17/80)= 34/80
Work done in 4 complete cycles = 4*(17/80)= 68/80
Remaining work to be done in the 5th cycle = 1-68/80 = 12/80
If we want to minimise the time taken to do the work, we need to put the fastest working persons first in the cycle.
A is the fastest working at 1/8 rate.
Work remaining after A shift = (12/80)-(1/8)= 2/80
B is 2nd fastest working at 1/20 rate.
Time she takes to complete the remaining work= (2/80)/(1/20)=(1/2) hour or 30 minutes
Minimum time taken = 16+1+0.5= 17.5 hours
If we want to maximise the time taken, the slowest workers will do the task first in the cycle.
D is slowest working at 1/80 rate.
Work remaining after D= (12/80)-(1/80)=11/80
C is 2nd slowest working at 1/40 rate.
Work remaining after C= (11/80)-(1/40)=9/80
B is 3rd slowest working at 1/20 rate.
Work remaining after B= (9/80)-(1/20)=5/80
A is fastest working at 1/8 rate.
Time time taken to complete remaining work = (5/80)/(1/8)= (1/2) hours
Maximum time taken= 16+1+1+1+0.5= 19.5 hours
minimum number of hours required for the task to be completed = 17.5 hours
maximum number of hours required for the task to be completed = 19.5 hours