Last visit was: 19 Nov 2025, 12:44 It is currently 19 Nov 2025, 12:44
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
ektalakra
Joined: 29 Jul 2024
Last visit: 19 Nov 2025
Posts: 27
Own Kudos:
12
 [1]
Given Kudos: 81
Products:
Posts: 27
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
jnxci
Joined: 29 Nov 2018
Last visit: 15 Nov 2025
Posts: 40
Own Kudos:
Given Kudos: 338
Posts: 40
Kudos: 17
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
bebu24
Joined: 19 May 2025
Last visit: 21 Aug 2025
Posts: 61
Own Kudos:
35
 [1]
Given Kudos: 12
Posts: 61
Kudos: 35
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
DyutiB
Joined: 21 Jul 2024
Last visit: 19 Nov 2025
Posts: 25
Own Kudos:
Given Kudos: 3
Products:
Posts: 25
Kudos: 16
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


The no. of unique combinations = 20C2 / 2 = 95 pairs

Let's suppose each machine works 1 unit per day. So in 95 days units of work done = (1+1)*95 = 190 units, then 20 units each day for 6 days. Total = 190+120 = 310 units.

If 20 machines had worked together from the beginning then 20 units per day, days required = 310/20 = 15.5 days

Where have I made mistake?
User avatar
bhanu29
Joined: 02 Oct 2024
Last visit: 19 Nov 2025
Posts: 115
Own Kudos:
50
 [1]
Given Kudos: 206
Location: India
GMAT Focus 1: 675 Q87 V85 DI79
GPA: 9.11
Products:
GMAT Focus 1: 675 Q87 V85 DI79
Posts: 115
Kudos: 50
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We have 20 machines and we pair each of them with other exactly ones
let rates be r1, r2, ... r20

so r1 will be matched with 19 others
r2 will be matched with 19 others

So total work done at the end of all pairings will be 19(r1+r2+...+r20)*1
Now they work together for 6 more days rate will be 6*(r1+r2+...+r20)
And they finish the job

so 25(r1+r2+...+r20) = 1

r1+r2+... r20 = 1/25

So if they work together they'll need 25 days to finish the job.


Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
sanya511
Joined: 25 Oct 2024
Last visit: 10 Nov 2025
Posts: 100
Own Kudos:
Given Kudos: 101
Location: India
Products:
Posts: 100
Kudos: 52
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hey Bunuel can we simply solve the question like this? Wouldnt different rates of machines come into factor? Kindly help me out. Also any way to instinctualize concepts like these?
Bunuel
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196
­

GMAT Club Official Explanation:



Each machine worked 1 day in a pair with each of the remaining 19 machines. Hence, each machine worked for 19 days in pairs.

After all unique pairs had worked once, all 20 machines worked together for 6 more days.

So, each machine worked a total of 19 + 6 = 25 days.

Thus, if all machines had worked together from the beginning, they would have completed the job in 25 days.

Answer: B.
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,390
Own Kudos:
778,343
 [1]
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,390
Kudos: 778,343
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
sanya511
Hey Bunuel can we simply solve the question like this? Wouldnt different rates of machines come into factor? Kindly help me out. Also any way to instinctualize concepts like these?
Bunuel
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196
­

GMAT Club Official Explanation:



Each machine worked 1 day in a pair with each of the remaining 19 machines. Hence, each machine worked for 19 days in pairs.

After all unique pairs had worked once, all 20 machines worked together for 6 more days.

So, each machine worked a total of 19 + 6 = 25 days.

Thus, if all machines had worked together from the beginning, they would have completed the job in 25 days.

Answer: B.

We get that each machine worked exactly 25 days in total, and the job was completed. So if all 20 machines had been working together for those same 25 days, the total work done would be the same. That's why the solution holds regardless of their individual rates.
User avatar
Akshita62
Joined: 29 Jan 2021
Last visit: 07 Aug 2025
Posts: 1
Own Kudos:
Given Kudos: 236
Posts: 1
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In question it was mentioned that every pair worked once .. so no of days taken by every pair is 190 and not 19.

So 190+6 =196 should be the answer
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,390
Own Kudos:
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,390
Kudos: 778,343
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Akshita62
In question it was mentioned that every pair worked once .. so no of days taken by every pair is 190 and not 19.

So 190+6 =196 should be the answer

Please check solution here: https://gmatclub.com/forum/gmat-club-ol ... l#p3591018 You can also check alternative solutions on the eight pages of discussion.
   1   2   3   4   5   6   7   8 
Moderators:
Math Expert
105390 posts
Tuck School Moderator
805 posts