Option B is the answer.
As per the question every machine works at a different constant rate so, lets assume Rate of M1=1, M2=2, M3=3,...M20=20.
The question also tells us that each day exactly 2 unique pair of machines work together to do the job so as per this information M1 will work with 19 other machines, similarly M2 will work with 18 and so on.
So from here we can calculate the daily production rate of M1 with each of the other machines for every single day: 3+4+5+6+7...21 = 228
Similarly, for M2 = 5+6+7+8...22 = 243
M3 = 7+8+9+10...23 = 255 and so on till M19 = 39.
So from here if we check the number of days for each machine is getting decreased by 1 and if you will calculate you will also get to know that the average for each machine will be increasing by 1.5 .
And from here we can get the amount of work done by these machines during that period: Like for M1 (12*19) + M2 (13.5*18) + M3 (15*17)...M19 (39*1) = 3990.
Also, from the question we know that all the machines worked together for last 6 days to complete the work so from here we will get the amount of work done by all the machies together: 6*210(total rate of all machine) = 1260.
So the total work will be: 1260+3990 = 5250.
From here we can easily calculate the total number of days it would take to complete the work if all machines work together: Total Work/ Rate Which will be,
5250/210 = 25 days.
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?
A. 19
B. 25
C. 26
D. 190
E. 196