Last visit was: 19 Nov 2025, 12:42 It is currently 19 Nov 2025, 12:42
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
rahulgmat17
Joined: 14 Jul 2024
Last visit: 19 Nov 2025
Posts: 10
Own Kudos:
9
 [1]
Given Kudos: 3
Products:
Posts: 10
Kudos: 9
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
harshnaicker
Joined: 13 May 2024
Last visit: 25 Sep 2025
Posts: 84
Own Kudos:
Given Kudos: 35
Posts: 84
Kudos: 60
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Sketchitesh
Joined: 29 Nov 2024
Last visit: 07 Nov 2025
Posts: 141
Own Kudos:
106
 [1]
Given Kudos: 19
Concentration: Operations, Finance
GPA: 7.2
WE:Operations (Other)
Products:
Posts: 141
Kudos: 106
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
MBAChaser123
Joined: 19 Nov 2024
Last visit: 14 Nov 2025
Posts: 86
Own Kudos:
74
 [1]
Given Kudos: 7
Location: United States
GMAT Focus 1: 695 Q88 V83 DI82
GPA: 3
GMAT Focus 1: 695 Q88 V83 DI82
Posts: 86
Kudos: 74
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
For the first part of the job:
Each machine works with each of the other machines, only once. Since the total number of machines is 20, we can say that each machine works only 19 days, and is off work for the rest of the days. We can assume that, if all the machines were working together, they would have done the first part in 19 days.

For the second part of the job:
All of the machines are working for 6 days. After the first part (no matter how many days it actually took) and these 6 days, the whole job is done.

So
If all the machines were working the whole time, the job would be done in:

19+6=25 days

So B is correct.
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
NilayMaheshwari
Joined: 20 Dec 2023
Last visit: 12 Oct 2025
Posts: 42
Own Kudos:
44
 [1]
Given Kudos: 26
Location: India
GMAT Focus 1: 595 Q80 V82 DI76
Products:
GMAT Focus 1: 595 Q80 V82 DI76
Posts: 42
Kudos: 44
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total number of arrangements = \(20_C_2\) = 190
2 machines work each day for 190 days = 380 machine days.
All 20 machines work for 6 days = 120 machine days.
Total machine days = 500.
Now if 20 machines worked each day, each day would have 20 machine days.
Number of days required to complete 500 machine days = \(\frac{500}{20}\) = 25 days.
User avatar
anshhh2705
Joined: 08 Jun 2025
Last visit: 07 Sep 2025
Posts: 19
Own Kudos:
8
 [1]
Given Kudos: 53
Location: India
Concentration: General Management, Marketing
GMAT Focus 1: 695 Q84 V86 DI84
GPA: 9.0
GMAT Focus 1: 695 Q84 V86 DI84
Posts: 19
Kudos: 8
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total Number of Days the pair of 2 machines work = Individual pairs of 2 selected from 20 using Combination Formula.

This is = 20! / 2! * (20-2)! = 20 * 19 / 2 = 190 Pairs who worked for 190 days (One pair worked one day)

So it would have taken 1 Machine = 190 * 2 days to complete the work that the pairs of machines did.

For 20 Machines working instead of the pairs = 190 * 2 / 20 days = 19 days

Now adding the 6 days additionally that the 20 machines took together,

Total Days it would have taken them to complete = 19 days + 6 days = 25 days (B)



Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
GarvitGoel
Joined: 06 Aug 2024
Last visit: 17 Nov 2025
Posts: 69
Own Kudos:
54
 [1]
Posts: 69
Kudos: 54
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Option B is the answer.

As per the question every machine works at a different constant rate so, lets assume Rate of M1=1, M2=2, M3=3,...M20=20.

The question also tells us that each day exactly 2 unique pair of machines work together to do the job so as per this information M1 will work with 19 other machines, similarly M2 will work with 18 and so on.

So from here we can calculate the daily production rate of M1 with each of the other machines for every single day: 3+4+5+6+7...21 = 228
Similarly, for M2 = 5+6+7+8...22 = 243
M3 = 7+8+9+10...23 = 255 and so on till M19 = 39.

So from here if we check the number of days for each machine is getting decreased by 1 and if you will calculate you will also get to know that the average for each machine will be increasing by 1.5 .

And from here we can get the amount of work done by these machines during that period: Like for M1 (12*19) + M2 (13.5*18) + M3 (15*17)...M19 (39*1) = 3990.

Also, from the question we know that all the machines worked together for last 6 days to complete the work so from here we will get the amount of work done by all the machies together: 6*210(total rate of all machine) = 1260.

So the total work will be: 1260+3990 = 5250.

From here we can easily calculate the total number of days it would take to complete the work if all machines work together: Total Work/ Rate Which will be,
5250/210 = 25 days.





Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
_sahuji_
Joined: 27 Jun 2022
Last visit: 19 Nov 2025
Posts: 11
Own Kudos:
10
 [1]
Given Kudos: 5
Location: India
Posts: 11
Kudos: 10
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
So, now suppose there are 20 machines a1, a2,....,a20
since we want to make unique pairs, so machine a1 can pair with 19 others. So it will work for 19 days as we can form 19 unique combinations with others.
so work done by a1 will be:
(a1 + a2) + (a1 + a3) + ....... + (a1 + a20)

for machine a2 it will be:
(a2 + a3) + ....... + (a2 + a20)

and so on...

It will be same for every other machines. So we can sum up the total work as:
19 * a1 + ....... + 19 * a20
=> 19 * ( work done by 20 machines)

for six more days it will be : 6 * ( work done by 20 machines)

summing up both we will get: 25 * ( work done by 20 machines)

So, if 20 machines worked together we would complete it in 25 days.

So answer is B
User avatar
garhwalchinmay
Joined: 06 Jun 2025
Last visit: 17 Jul 2025
Posts: 11
Own Kudos:
3
 [1]
Posts: 11
Kudos: 3
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

Its B - 25, initally each pair working only 2 days is (20,2) = (20x19)/2 = 190 days
each machine appears in 19 pairs , so for 190 days each machine worked 19 times in a unique pair, after that they all work for 6 days so total work done is 19+6=25
6days.
User avatar
ReenaM0
Joined: 08 Mar 2025
Last visit: 13 Sep 2025
Posts: 12
Own Kudos:
3
 [1]
Given Kudos: 32
Posts: 12
Kudos: 3
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let r1+r2+r3.....+r20=R
19R=W1
6R=W2
19R+6R=1 (1 job completed)
25R=1
25/T=1
T=25 days
User avatar
abhimaster
Joined: 30 May 2025
Last visit: 30 Oct 2025
Posts: 36
Own Kudos:
16
 [1]
Given Kudos: 16
Products:
Posts: 36
Kudos: 16
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

Nice, this was new and i loved this.

So, we have 20 machines which we want to arrange in pairs but unique. So, it can be done with

[20]C[2] which is 190. This means we can make 190 unique pairs.

Now if we think about the pairs each machine is appearing 19 times in the pairs. so we can write

{a1+a2, a1+a3, ..... } = 19 x (a1 + a2 + .... + a19)


this is nothing but 19 times the amount of work they can do together. So , accrodign to question machine took 190 Days (as each pair took 1 day and we have 190 pairs) + 6 Days when they worked together.

So if they work together from start, lets say R is amount of work done per day when they start together. then Total work from previous queation can be written as 19R + 6R = 25R

so this means they need to work for 25 days together to complete work.
User avatar
nevaan9
Joined: 08 Jan 2025
Last visit: 14 Oct 2025
Posts: 8
Own Kudos:
6
 [1]
Given Kudos: 6
Posts: 8
Kudos: 6
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
To find the number of unique pairs from 20 we apply the formula 20Choose2 = (20*19)/2! = 190
So the pairs worked for 190 days --> Lets call this pair-days
Since there were 2 machines in each pair, it took 190*2 = 380 machine-days to complete the work in pairs

Now additionally it took 20*6 = 120 machine-days for the additional 6 days of work with 20 machines.

Total machine-days = 380 + 120 = 500

Now to find how long 20 machines would have taken for 20 machine-days worth of work: 500/20 = 25 days
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
andreagonzalez2k
Joined: 15 Feb 2021
Last visit: 26 Jul 2025
Posts: 308
Own Kudos:
497
 [1]
Given Kudos: 14
Posts: 308
Kudos: 497
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Since each machine pairs with every other machine exactly once, each machine​ appears in 19 pairs (since there are 19 other machines to pair with).
ri=work rate of each machine

Total work Pair Phase = 19 * sum from i=1 to i=20 of ri

Total work Group Phase = 6 * sum from i=1 to i=20 of ri

Total work = (19+6) * sum from i=1 to i=20 of ri = 25 * sum from i=1 to i=20 of ri

So, if If all 20 machines had worked together, the job have been completed in 25 days

IMO B
User avatar
twinkle2311
Joined: 05 Nov 2021
Last visit: 18 Nov 2025
Posts: 150
Own Kudos:
167
 [1]
Given Kudos: 10
Location: India
Concentration: Finance, Real Estate
GPA: 9.041
Posts: 150
Kudos: 167
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
There are 20 machines, and every day a different pair works.

Total number of unique 2-machine pairs => 20C2 = 190. So for 190 days, two machines work each day.

Now, each machine appears in 19 different pairs, so over 190 days, each machine works 19 times. That means each machine has done 19 days worth of work.

Then, all 20 machines work together for 6 more days. So in total, each machine does 19 + 6 = 25 days of its own work.

If all 20 machines had just worked together from the beginning, they would have finished the same job in 25 days.

Answer : B (25 Days)
User avatar
SumnerSCB
Joined: 27 Apr 2025
Last visit: 08 Sep 2025
Posts: 36
Own Kudos:
22
 [1]
Posts: 36
Kudos: 22
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

I first assumed you needed to know the number of pairs, which while I could rationalize my way through it is a slow process. I found the combination formula N!/K!(N-K)!. This is more info needed but could be useful. it results in 20*19/2 which is 190. So 190 pairs. What we really need out of that is that each number shows up in 19 pairs. Which honestly could have been done by just looking at 20 machines - 1. With that each machine worked for 19 days, so that would be equivalent to all the machines working for 19 days. We needed 6 additional days so 19+6= 25
User avatar
Semshov
Joined: 08 Aug 2024
Last visit: 01 Oct 2025
Posts: 13
Own Kudos:
9
 [1]
Given Kudos: 1
Schools: IMD'26 (S)
GMAT Focus 1: 485 Q70 V80 DI72
Schools: IMD'26 (S)
GMAT Focus 1: 485 Q70 V80 DI72
Posts: 13
Kudos: 9
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

The total numbers of days in which 2 machines are assigned to work until all machines have worked once is 20C2 = 190 days.

Let us consider that all 20 machines had worked together from the begining.
Day 1 : Machine 1 & Machine 2 // Machine 3 & Machine 4...
Day 2 : Machine 1 & Machine 3 // Machine 2 & Machine 4...
Each individual can be paired with the 19 others machines. As we have unique pairs witch have worked once each day, we can say that the work is done in 19 days. The additional 6 days give us a total of 25 days.
User avatar
vnar12
Joined: 03 Jun 2024
Last visit: 26 Aug 2025
Posts: 51
Own Kudos:
32
 [1]
Given Kudos: 4
Posts: 51
Kudos: 32
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

The correct answer is (B).
To solve this question, I first calculated approximately how many unique pairs of machines are possible on day 1. With 20 machines, that number would be how many other machines one particular machine is able to pair with, so 19. Then if the machines are paired differently the next day, the possible combinations would be one less, so 18. Then each subsequent day would be 17, 16, and so on until 1.

That indicates 19 days of unique combinations. If we add the 6 extra days from the question, the answer should be 19 + 6 = 25 days (answer choice B).
User avatar
Luiz_Salves
Joined: 29 Jun 2024
Last visit: 29 Sep 2025
Posts: 13
Own Kudos:
9
 [1]
Given Kudos: 20
GMAT Focus 1: 585 Q79 V80 DI78
GMAT Focus 1: 585 Q79 V80 DI78
Posts: 13
Kudos: 9
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines worked in 2 pair, and only unique pairs at each time. So we need to find how many combinations are possible to reach this pairs.

C(20,2)= 190 pairs or 190 work days.

After this they worked more 6 days together to finish the work. Thus this situation delivered the work in 196 days in total.

To find all 20 machines working together since the beginning:

190 days with just 2 machines working each days, if we put 10 times the number of machines (20) we can reduce this time to 190/10=10, plus 6 days that all machines worked together, we can find 25 days.
User avatar
tgsankar10
Joined: 27 Mar 2024
Last visit: 19 Nov 2025
Posts: 281
Own Kudos:
390
 [1]
Given Kudos: 83
Location: India
Posts: 281
Kudos: 390
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
No of unique pairs from 20 machines, \(20C2=\frac{20!}{2!*18!}=\frac{19*20}{2}=190\)

Machines worked as pairs for 190 days.

Each machine is paired with 19 other machines. Each machine will work for 19 days. This is equivalent to all machines working together for 19 days.

Additionally 20 machines work together for 6 more days.

Days taken to complete the job if all 20 machines worked together \(= 19+6=25\)

Answer: B
User avatar
iAkku
Joined: 25 Aug 2023
Last visit: 16 Aug 2025
Posts: 28
Own Kudos:
19
 [1]
Given Kudos: 11
Location: India
Products:
Posts: 28
Kudos: 19
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The trap for this question is to avoid 20C2 calculation.


Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

Attachment:
GMAT-Club-Forum-gv76j5hk.png
GMAT-Club-Forum-gv76j5hk.png [ 301.95 KiB | Viewed 124 times ]
   1   2   3   4   5   6   7   8   
Moderators:
Math Expert
105390 posts
Tuck School Moderator
805 posts