Last visit was: 19 Nov 2025, 05:21 It is currently 19 Nov 2025, 05:21
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
VizzyFanboy
Joined: 14 Jul 2023
Last visit: 17 Nov 2025
Posts: 32
Own Kudos:
15
 [1]
Given Kudos: 31
Location: India
GMAT Focus 1: 675 Q88 V84 DI79
GMAT Focus 1: 675 Q88 V84 DI79
Posts: 32
Kudos: 15
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ODST117
Joined: 15 Aug 2024
Last visit: 29 Oct 2025
Posts: 173
Own Kudos:
85
 [1]
Given Kudos: 149
Posts: 173
Kudos: 85
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
DataGuyX
Joined: 23 Apr 2023
Last visit: 06 Nov 2025
Posts: 107
Own Kudos:
77
 [1]
Given Kudos: 161
Location: Brazil
Concentration: Entrepreneurship, Technology
Posts: 107
Kudos: 77
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Manu1995
Joined: 30 Aug 2021
Last visit: 11 Nov 2025
Posts: 81
Own Kudos:
Given Kudos: 18
Posts: 81
Kudos: 55
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We are given:
Total unique pairs : With 20 Machines, the number of unique pairs is
C(20,2) = ( 20 × 19)/2 = 190
==>190 days passed while making unique 2-machine combinations.

Then 6 more days with all 20 machines working together.
So total actual time taken = 190 + 6 = 196 days

Let the total work done = W

Let the work done per day when all 20 machines work together = R

Then in 6 days, total work done = 6R

So the first 190 days (using pairs) did: W−6R

If all 20 had worked together from the beginning, they'd do R work per day, and to do W work:

Time = W/ R
= [( W −6R )+ 6R] / R

But we know W - 6R was done in 190 days using pairs.

So time if all 20 machines worked together:

W/R = 190 + 6 = 196

So the correct answer is (E) 196
User avatar
lvillalon
Joined: 29 Jun 2025
Last visit: 25 Aug 2025
Posts: 88
Own Kudos:
73
 [1]
Given Kudos: 14
Location: Chile
Concentration: Operations, Entrepreneurship
GPA: 3,3
WE:Consulting (Consulting)
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
B. 25

Explanation:

Total days working would be

(20*19)/2 + 6 = 196

You have to divide by 2, to avoid counting inversed order of machines (eg. A and B, then B and A)

We need the total speed R = r1 + r2 + r3 + ...

Now, sum up the speeds of the first 190 days:

Day 1: r1 + r2
Day 2: r1 + r3
and so on

Every machine works 19 days (one with each other machine):

19*r1 + 19*r2 + ...
-> 19 * ( r1 + r2 + r3 + ...) = 19R

Add the 6 remaining days working all together, to get the total work done:

19R + 6R = 25R

Finally, divide total work by total speed:

25R/R = 25
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
embellor
Joined: 26 Feb 2025
Last visit: 17 Nov 2025
Posts: 12
Own Kudos:
3
 [1]
Location: Nigeria
Posts: 12
Kudos: 3
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let us find the combination of the the 20 Machines available to work + 20Cr2 = 20!/2!(20-20)! =190

Each Machine will pair with other 19 Machines. Since the machines have constant rate, for any pair the combined rate is r1 + r2. Combined rate of all machine = r = (r1 +r2...r20).


The work done in the first 10 days by 19 pairs will be 19pair X combined rates of all the machine = 19 X R= 19R.

When all 20 machines work in the 6 days = 6 X R = 6R

Total work done = 19R + 6R = 25R.

Number of days required to do the = 25R/R = 25 days.

Therefore B is the answer.





Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
asingh22
Joined: 31 Jul 2024
Last visit: 18 Nov 2025
Posts: 68
Own Kudos:
57
 [1]
Given Kudos: 8
Location: India
GMAT Focus 1: 635 Q84 V78 DI82
GMAT Focus 2: 655 Q89 V80 DI78
GPA: 2.5
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
total cases out of 20 20C2 = 190
plus 6 days together working, then the total. = 190+6 =. 196
If each is working at a different rate, then each machine will work 19 times the same for all other machines. If they work together, then a total of 19 days will be required for each machine, and the remaining 6 days will work, then the total days will be 19+6 = 25
User avatar
naman.goswami
Joined: 11 Jun 2023
Last visit: 14 Nov 2025
Posts: 31
Own Kudos:
28
 [1]
Given Kudos: 63
Location: India
GMAT 1: 640 Q53 V25
GMAT 1: 640 Q53 V25
Posts: 31
Kudos: 28
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Each machine can be will work for 19 days (each machine can be paired with 19 other machines + all machines together worked for 6 more days. IF all the machines had worked together from the begning then they will work for 19+ 6= 25 days
User avatar
iCheetaah
Joined: 13 Nov 2021
Last visit: 17 Nov 2025
Posts: 81
Own Kudos:
72
 [1]
Given Kudos: 1
Location: India
Posts: 81
Kudos: 72
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Since, a pair (i.e. 2 machines) are working together each day, and no two machines work together more than once. We can say that out of the 20 machines we can select 2 machines in the following ways:

\(20C2\) ways, which is 190
Since, the above means that we have 190 unique pairs, and each pair is working for exactly 1 day, we can infer that the machines together in these pairs worked for a total of 190 days


Now, let's assume that each pair of these machines (even though all 20 have different rates) completes "m" units of work everyday

2 machines ----> "m" units of work every day

Or we can say,

1 pair ----> "m" units of work everyday

190 such pairs will have ----> "190m" units of work done in 190 days (equation 1)


We know that,

2 machines ----> "m" units of work everyday

thus,

20 machines ----> "10m" units of work everyday

Since, we know that the 20 machines worked together for 6 days to complete the entirety of their work, we can get the total work done by these 20 machines in those 6 days

\(10m*6 = 60m\) (equation 2)


The total work done by the pairs in 190 days and the 20 machines in 6 days is given by, adding up equations 1 and 2

\(190m + 60m = 250m\)


We are asked to find, the time taken if all of the 20 machines were working together sicne day 1.

We can apply the unitary method for the same here:

60m (work done by 20 machines) ----> 6 days
10m (work done by 20 machines) ----> 1 day
250m (work done by 20 machines) ----> 25 days


Answer is B. 25
User avatar
AD21
Joined: 12 Jan 2024
Last visit: 18 Nov 2025
Posts: 38
Own Kudos:
23
 [1]
Given Kudos: 31
Location: United States
Products:
Posts: 38
Kudos: 23
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Answer B- 25

20 machines are working at different constant rates in pairs.

10C2 or nk/2(combinations handshake formula)= 20*19/2= 190pairs
then all 20 machines work for additional 6 days

All 20 machines work for exactly 19 days with another machine and 6 days with all other 19 machines.
so total no of days in which the 20 machines would have completed the work is (19+6)=25 days
User avatar
UfuomaOh
Joined: 14 Sep 2023
Last visit: 17 Nov 2025
Posts: 83
Own Kudos:
50
 [1]
Given Kudos: 14
Products:
Posts: 83
Kudos: 50
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

To determine how many days it took the machine to complete the job, we determine the total machine days divided by the number of machines had all the machines worked together from the beginning.

First, determine the number of unique pair of days
20C2= 190

The unique pair of machines

190x2=380

The additional 6 days is

20 x 6 = 120 machine days

Total Machine days

380+120= 500

number of days the job would have been completed if all the machines had worked together from the beginning

500/20
= 25 days
User avatar
Tanish9102
Joined: 30 Jun 2025
Last visit: 19 Nov 2025
Posts: 59
Own Kudos:
49
 [1]
Posts: 59
Kudos: 49
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Correct Option: Option b
Here we have 20 machines and each machines work with 19 other machines
So Total days of working is 190 days.
each machine worked with 19 other machines
assume x is rate so total we have 19x
than for additional production we have 6 days which we multiply by rate x
Total work done= 19x+6x= 25x
For 20 machines from Total work done we will divide by x as rate
25x/x= 25 days
User avatar
adityamntr
Joined: 15 Jul 2023
Last visit: 18 Nov 2025
Posts: 12
Own Kudos:
3
 [1]
Given Kudos: 3
Location: India
Concentration: General Management, Strategy
Posts: 12
Kudos: 3
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
According to the question it is clear that each machine is working with other 19 machines , one time one day. That means each machine is effectively working 19 days. to be able to complete the combinations.
also in then end it is working 6 days.
total Work done is equivalent of work done by each machine running 25 days.
Hence our answer is 25
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
AnujSingh0147
Joined: 17 Jun 2024
Last visit: 31 Oct 2025
Posts: 38
Own Kudos:
16
 [1]
Given Kudos: 126
Location: India
GPA: 6.5
Posts: 38
Kudos: 16
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Its a steep logical question hardly any maths can be done in the given timeframe.

lets label 20 machines with 1,2,,3.....20
Therefore,
machine 1 can work with (2,3,4....20) = 19 unique pairs possible
since repetition of pairs is not allowed (i.e, (1,2) worked previously so (2,1) cannot work in future)
machine 2 can work with (3,4,5....20) = 18 unique pairs possible
and so on till,
machine 19 can work only with (20) = 1 unique pair possible

so total number of days = 19+18+...1 = 190 days

Now here the critical catch
Let say machine 1 matched with 19 other machines
(1,2),(1,3)......(1,20) = 19 pairs

Every machine appear in 19 unique 2 pair sets.
That also implies that each machine has worked for 19 whole days


In addition machine worked for 6 additional day
Total days each unique machine worked = 19+6 = 25 days

Now if all machine work together than - 25 days it will take to complete the whole work.
Option B
User avatar
AminSadr
Joined: 16 Feb 2025
Last visit: 01 Sep 2025
Posts: 12
Location: Iran (Islamic Republic of)
Schools: Sloan '27
GPA: 3.4
Schools: Sloan '27
Posts: 12
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We are given:
• There are 20 machines, each with a different constant rate.
• Each day, exactly 2 machines work, and no pair repeats.
• After all unique pairs of machines have worked, all 20 machines work together for 6 days to finish the job.
• We must find: how many days total would it take if all 20 machines worked together from the beginning to complete the job.



🔹 Step 1: How many unique pairs of machines?

From 20 machines, the number of unique pairs is:

\binom{20}{2} = \frac{20 \cdot 19}{2} = 190 \text{ pairs}

So, for the first 190 days, each day 2 machines work (no repeats), and each unique pair works once.



🔹 Step 2: Let each machine M_i have a rate r_i

The total work is fixed. Let’s call the total work = W.

Let’s compute total work done in the first 190 days.

Each day, 2 machines M_i and M_j work, contributing r_i + r_j units of work that day.

So over 190 days, the total work done is the sum over all 190 pairs of r_i + r_j

Key idea: each machine appears in exactly 19 pairs (because each machine pairs with every other machine once: 20 - 1 = 19)

So the total contribution of machine M_k over the 190 days is:

\text{Machine } M_k \text{ appears in 19 days} \Rightarrow \text{contributes } 19 \cdot r_k

Thus, total work done in first 190 days is:

\sum_{k=1}^{20} 19 \cdot r_k = 19 \cdot \sum_{k=1}^{20} r_k

Now, for the next 6 days, all 20 machines work together:

\text{Daily rate of all 20 machines together} = \sum_{k=1}^{20} r_k
\Rightarrow \text{Total work in 6 days} = 6 \cdot \sum_{k=1}^{20} r_k



🔹 Step 3: Total work = work from first phase + work from second phase

W = 19 \cdot \sum r_k + 6 \cdot \sum r_k = 25 \cdot \sum r_k

Now, if all 20 machines had worked together from the beginning, their daily rate would be \sum r_k, so:

\text{Number of days to complete work} = \frac{W}{\sum r_k} = \frac{25 \cdot \sum r_k}{\sum r_k} = \boxed{25}



✅ Final Answer: B. 25
User avatar
Mohit11111
Joined: 26 Mar 2018
Last visit: 18 Nov 2025
Posts: 11
Own Kudos:
5
 [1]
Given Kudos: 8
Location: India
Schools: ISB '27
Schools: ISB '27
Posts: 11
Kudos: 5
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
let work per machine = x
unique combination of machines = 20C2 =190
Total work done in these 190 days = 190*2*x=380x
Additional 6 days work = 6 *20*x=120x
Total work in 196 days = 500x
Had 20 machines worked together for t days, work done = 20*t*x=20tx

now 20tx=500x
thus t=25
User avatar
lemonwatermelo
Joined: 01 Aug 2021
Last visit: 17 Nov 2025
Posts: 13
Own Kudos:
6
 [1]
Given Kudos: 127
Location: India
Concentration: International Business, Strategy
GPA: 8
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
What I understand is that we need to compare two scenarios:
- Pairs of machines work daily (no repeats), then all machines together for 6 days.
- All 20 machines work together every day from the start.

First, we need to figure out how many unique 2-machine pairs exist.
That’s just:
(20 x19)/2 = 190 days of 2-machine work

So across the 190 days:
- Each of the 20 machines works 19 times.
- So total machine-days = 20 × 19 = 380

That’s the same amount of machine-work as 20 machines working for 19 full days together.

Therefore,
- All the 2-machine pairings = 19 days of full-team work
- Then 6 more full-team days are added
- Total equivalent full-team days = 19 + 6 = 25

Final Answer: 25 days (Option B)
User avatar
ccarson
Joined: 10 Nov 2024
Last visit: 16 Nov 2025
Posts: 43
Own Kudos:
Given Kudos: 62
Location: United States
GMAT Focus 1: 595 Q77 V81 DI80
GMAT Focus 2: 595 Q79 V81 DI78
GMAT Focus 3: 675 Q82 V85 DI84
GMAT Focus 3: 675 Q82 V85 DI84
Posts: 43
Kudos: 96
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines, choose 2 per day, no repeats:
20C2 = 20*19/2 -> 190
all machines work for 6 days together so add that to the total:
190+6 -> 196
User avatar
Jabeer
Joined: 02 Dec 2024
Last visit: 19 Nov 2025
Posts: 9
Own Kudos:
5
 [1]
Given Kudos: 6
Posts: 9
Kudos: 5
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
[*](20*19/2)=190 days → each day 2 machines work
→ Total work = each machine works in 19 pairs = 19R
[*]Then 20 machines work for 6 days = 6R
[*]Total work = 19R + 6R = 25R
[*]If all 20 machines worked together:
Work per day = R ⇒ Days = 25R/R=25



Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
Rishi705
Joined: 25 Apr 2024
Last visit: 19 Nov 2025
Posts: 44
Own Kudos:
32
 [1]
Given Kudos: 20
Posts: 44
Kudos: 32
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Each Machine worked once with every other machine. So each machine worked for 19 days. That is equal to all six machines working for 19 days. Plus the 6 additional days.
19+6=25.
Keep it simple.

Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

   1   2   3   4   5   6   7   8   
Moderators:
Math Expert
105385 posts
Tuck School Moderator
805 posts