Last visit was: 18 Nov 2025, 21:12 It is currently 18 Nov 2025, 21:12
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,093
 [43]
1
Kudos
Add Kudos
42
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
778,093
 [5]
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,093
 [5]
5
Kudos
Add Kudos
Bookmarks
Bookmark this Post
General Discussion
User avatar
MaxFabianKirchner
Joined: 02 Jun 2025
Last visit: 12 Jul 2025
Posts: 65
Own Kudos:
62
 [4]
Given Kudos: 122
Status:26' Applicant
Location: Denmark
Concentration: Finance, International Business
GPA: 4.0
WE:Other (Student)
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
avatar
ManifestDreamMBA
Joined: 17 Sep 2024
Last visit: 18 Nov 2025
Posts: 1,282
Own Kudos:
784
 [2]
Given Kudos: 236
Products:
Posts: 1,282
Kudos: 784
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Number of pairs = 20C2 = 190

Each day a unique pair works. So there are 10 pairs working each day.
Total days = 190/10=19 days

In addition, all 20 machines work together for 6 additional days to complete the job
This makes the total number of days = 19+6=25
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
Karanjotsingh
Joined: 18 Feb 2024
Last visit: 03 Oct 2025
Posts: 139
Own Kudos:
Given Kudos: 362
Location: India
Concentration: Finance, Entrepreneurship
Posts: 139
Kudos: 94
Kudos
Add Kudos
Bookmarks
Bookmark this Post
[size=85][size=100]Answer[/size][/size]

[size=85][size=100](B) 25[/size][/size]


Explanation

Let's break this down logically. The key is to figure out the total amount of "work" done in terms of the machines' combined daily output.

Let R be the combined rate of all 20 machines working together for one day.

Step 1: The "Pairs" Phase
  • First, how many days does this phase last? We need to find the number of unique pairs of 2 machines from a group of 20. This is a combination:
    • C(20, 2) = (20 × 19) / 2 = 190 days.
  • Now, how much work is done? Over these 190 days, each machine is paired with the other 19 machines. This means each machine works for a total of 19 days.
  • So, the total work done in this phase is equivalent to all 20 machines working together for 19 days.
    • Work in pairs phase = 19 × R.
Step 2: The "All Together" Phase
  • After the pairs phase, all 20 machines work together for 6 additional days.
  • The work done here is simply 6 × R.

Step 3: Calculate the Total Work
  • To complete the job, the total work is the sum of the work from both phases.
    • Total Work = (19 × R) + (6 × R) = 25 × R.
  • This means the entire job is equivalent to all 20 machines working together for 25 days.

Step 4: Answer the Question
  • The question asks: "If all 20 machines had worked together from the beginning, in how many days would the job have been completed?"
  • Since the total work is 25 × R, it would take exactly 25 days.
User avatar
BeachStudy
Joined: 30 Jun 2025
Last visit: 18 Aug 2025
Posts: 61
Own Kudos:
37
 [1]
Given Kudos: 4
Posts: 61
Kudos: 37
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
25 days.

20 machines. / 2 per day never the same pair.

190 unique pairs in a group a group of 20 so 190 days. (19*20 / 2)
6 days at the end needed.

(190*2 ) + (6*20) = 500 machine working days. 500/20 = 25

25 days



Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
anuraagnandi9
Joined: 25 Mar 2025
Last visit: 18 Nov 2025
Posts: 11
Own Kudos:
12
 [1]
Given Kudos: 3
Location: India
GMAT Focus 1: 705 Q87 V84 DI84
GPA: 3.34
GMAT Focus 1: 705 Q87 V84 DI84
Posts: 11
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
From 20 machines, the number of unique 2-machine combinations would be 20C2 = 190

Let x1, x2, x3 and so on be work rates per day of 20 machines
So over the 190 days, the work completed would be sum of (xi + xj) for all the pairs of i and j

Since each machine works 19 days with other machine, 19* (sum of xi, for all other 19 machines)
Let R be (sum of xi, for all other 19 machines)
So total work for 2 machines at a time would be 19*R

For 6 days, the work done was 6*R
So total work = 19*R + 6*R = 25R

but if they all began to work at same time it would have take 25 days to do so.
User avatar
AVMachine
Joined: 03 May 2024
Last visit: 26 Aug 2025
Posts: 190
Own Kudos:
154
 [1]
Given Kudos: 40
Posts: 190
Kudos: 154
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196

Each Machine would work with the other 19 machines for 19 days, and then all the machines would simultaneously work for 6 days, hence each machine would work for (19+6) = 25 days;

Hence, when all the machines work simultaneously, they have to work for 25 days.
User avatar
imAman
Joined: 23 Mar 2025
Last visit: 23 Jul 2025
Posts: 5
Own Kudos:
Given Kudos: 1
Posts: 5
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The ans is 196.
so, each pair of machines work once so total combinations = 20C2 = 190.
6 additional days extra were taken . so, 190+6 = 196 days.

ans is E
User avatar
APram
Joined: 23 Jun 2024
Last visit: 17 Nov 2025
Posts: 671
Own Kudos:
263
 [1]
Given Kudos: 240
Location: India
GMAT Focus 1: 605 Q86 V78 DI76
GPA: 3.608
Products:
GMAT Focus 1: 605 Q86 V78 DI76
Posts: 671
Kudos: 263
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let 1 machine can complete the task in x hrs
Rate of 1 machine = 1/x

Total number of pairs = 20C2 = 190

Total work done = work done by 190 machines taken 2 at a time + work done by 20 machines for 6 days
Total work = (1/x + 1/x) * 190 + (20/x)*6 = 500/x

When 20 machines work together since beginning
No of days = Total work/work done by 20 machines
No of days = (500/a)/(20/a) = 25 days

Hence B is correct
User avatar
Heix
Joined: 21 Feb 2024
Last visit: 18 Nov 2025
Posts: 361
Own Kudos:
153
 [1]
Given Kudos: 63
Location: India
Concentration: Finance, Entrepreneurship
GMAT Focus 1: 485 Q76 V74 DI77
GPA: 3.4
WE:Accounting (Finance)
Products:
GMAT Focus 1: 485 Q76 V74 DI77
Posts: 361
Kudos: 153
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
First, I need to determine how many unique pairs can be formed from 20 machines. This is a combination problem where we select 2 machines from 20:
Number of unique pairs = C(20,2) = (20 × 19)/(2 × 1) = 190 pairs
So there were 190 days where 2 machines worked together, followed by 6 days where all 20 machines worked together.
Let's denote the rate of machine i as r_i (in terms of job/day).
When 2 machines work together for a day, their combined rate is (r_i + r._]) job/day.
When all 20 machines work together, their combined rate is (r_1+r_2 + ... + r_20) job/day.
The total work done equals 1 job, which can be written as:
Sum of all pairs working for 1 day each + All 20 machines working for 6 days = 1 job
For the sum of all pairs, each machine appears in exactly 19 pairs (it can pair with each of the other 19 machines). So each machine's rate r_i appears 19 times in the sum.
Therefore:
19(г 1+ г_2+ ... + г_20) + 6(г_1+ г_2+ ... + r_20) = 1 job
(19 + 6)(г_1+r_2+.. + r_20) =1 job
25(г_1+r_2+.. + r_20) =1 job
This means that the combined rate of all 20 machines is 1/25 job/day.
Therefore, if all 20 machines had worked together from the beginning, they would have completed the job in 25 days.
The answer is B. 25.
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 18 Nov 2025
Posts: 5,793
Own Kudos:
5,509
 [1]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,793
Kudos: 5,509
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job.

If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

Let the efficiency (part of work done per day) of the machines be e1, e2, ..... e20

e1 + e2 + e1 + e3 + e1 + e4 + ... + e1 + e20 + e2 + e3 + e2 + e4 + ...+e2 + e20 + e3 + e4 + ...e3 + e20 + ... e19 + e20 + 6 (e1 + e2+ ... + e20) = 1

19 (e1 + e2+ ... + e20 ) + 6 (e1 + e2 + ... + e20) = 25 (e1 + e2 + ... + e20) = 1
e1 + e2 + .... + e20 = 1/25

Efficiency of all machines working together = 1/25

If all 20 machines had worked together from the beginning, the number of days in which the job would have been completed = 25 days

IMO B
User avatar
Gargi7777
Joined: 21 Dec 2024
Last visit: 13 Nov 2025
Posts: 13
Own Kudos:
6
 [1]
Given Kudos: 64
Posts: 13
Kudos: 6
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
You can pair 2 machines out of 20 in
(202)=20×192=190 ways
So, for 190 days, 2 machines work each day — each pair only once.

Each machine ends up working with 19 others, once each. So every machine contributes to 19 days of work.
That means, across all those 190 days, each machine works for 19 days total.
So, total work in 190 days =
Same as if all 20 machines had worked individually for 19 days each.
Which is:
19 × (sum of all machine rates)
Let’s call this total combined rate = R
So work done in first phase = 19R

6 days × R = 6R
So total work = 19R + 6R = 25R

If all machines worked together from the start (rate = R),
time needed =
Total work ÷ total rate =
25R ÷ R = 25 days

Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

User avatar
Kanika2409
Joined: 19 Feb 2025
Last visit: 17 Sep 2025
Posts: 14
Own Kudos:
11
 [1]
Given Kudos: 1
Posts: 14
Kudos: 11
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We have 20 machines and they work in pairs
So unique paris are 20C2 = 20*19/2 =190
Each machine has worked 19 days in these 190 days, so if amounts to 19 days of work for every machine working together
Then in the end all machines work together for 6 days
Total day = 19+6 =25
Hence B
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20C2 * 2t + 6* 20t = 1
t = 1/500

d*20t= 1 => d(no. days for 20 machines) = 500/20 = 25
User avatar
chasing725
Joined: 22 Jun 2025
Last visit: 17 Aug 2025
Posts: 85
Own Kudos:
81
 [1]
Given Kudos: 5
Location: United States (OR)
Schools: Stanford
Schools: Stanford
Posts: 85
Kudos: 81
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 


As we are taking unique pairs, machine 1 works for 19 days, machine 2 works for 19 days, machine 3 works for 19 days, and so on.

So, each machine works for 19 days.

After that, each machine for 6 days.

So in total each machine works for 25 days. Total work is 25 * rate of each machine

Now, if the machines are started all in one go right from the start, each day every machine will run and it will take 25 days to complete. Because the amount of work that has to be done is the same.

Option B
avatar
krutarth21
Joined: 28 May 2025
Last visit: 18 Nov 2025
Posts: 21
Own Kudos:
13
 [2]
Given Kudos: 50
Location: India
GPA: 3.82
Products:
Posts: 21
Kudos: 13
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The correct answer is 25. Below attached is the detailed solution for this.
Attachments

IMG_1888.JPG
IMG_1888.JPG [ 2.91 MiB | Viewed 3372 times ]

User avatar
Benedictng
Joined: 21 Jan 2025
Last visit: 10 Jul 2025
Posts: 18
Own Kudos:
12
 [1]
Given Kudos: 1
Posts: 18
Kudos: 12
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
20 machines, each working at a different constant rate, work to complete a certain job. Each day, exactly 2 machines are assigned to work, and no pair of machines works together more than once. After all such unique pairs have worked once, all 20 machines work together for 6 additional days to complete the job. If all 20 machines had worked together from the beginning, in how many days would the job have been completed?

A. 19
B. 25
C. 26
D. 190
E. 196


 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 

20C2 = 190
It takes 190days for all unique pairs to run

Every 10 days, each unique machine has worked one of the days.

therefore 190 days of unique pairs = 19 days of all 20 machines working together

19+6 = 25,

It would take 25 days of all machines working together
User avatar
dthaman1201
Joined: 08 Dec 2024
Last visit: 18 Nov 2025
Posts: 21
Own Kudos:
17
 [1]
Given Kudos: 151
Posts: 21
Kudos: 17
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
20 machines can form 10 unique pair but no where it is mentioned that the pair are unique which means a pair can be formed in 20C(2) ways which is 190 pair but as we know unique pairs are 10 so it means each machine shows up 19 times

work done in first 190 days is:
let rate of each machine be a, b,c and so on
the rate by 19 machine would be 19(a+b+c....)

similarly work done in 6 days is:
6(a+b+c...)

Let sum of all rates be R THEN total work = 19R + 6 R=25R

Days= Total Work/ Total Rate = 25R/R = 25 Days
avatar
DachauerDon
Joined: 19 Apr 2025
Last visit: 27 Aug 2025
Posts: 29
Own Kudos:
19
 [1]
Given Kudos: 26
Location: Germany
Schools: LBS
Schools: LBS
Posts: 29
Kudos: 19
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The number of possible unique pairings of machines can be found using the handshake formula where
(number of machines x number of other machines each machine can work with)/2 = 190

Because each pair works on one day, I know it took the first phase 190 days before the final 6 day phase begun.

Setting up the rate equation, I don't know the individual rates and have no way of finding out so I'll try and express it in terms of their combined rate = R. Because each machine works only on a day that it is paired with a new machine, it will work for 19 days (to make up a total of 19 different pairs). This is of course the case for all machines so 19 x (rate machine 1) + 19 x (rate machine 2)....... = 19 (rate machine 1 + r machine 2 +.....) = 19R

For the second phase, they all work together for 6 days so the work done = 6R

Adding the work done during both phases means that the job is worth 25R, or 25 days of all machines working together.

Answer: B) 25
 1   2   3   4   5   6   7   8   
Moderators:
Math Expert
105355 posts
Tuck School Moderator
805 posts