Last visit was: 18 Nov 2025, 23:00 It is currently 18 Nov 2025, 23:00
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
LastHero
Joined: 15 Dec 2024
Last visit: 11 Nov 2025
Posts: 134
Own Kudos:
147
 [1]
Given Kudos: 1
Posts: 134
Kudos: 147
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ODST117
Joined: 15 Aug 2024
Last visit: 29 Oct 2025
Posts: 173
Own Kudos:
85
 [1]
Given Kudos: 149
Posts: 173
Kudos: 85
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
VagueMap
Joined: 28 Jun 2025
Last visit: 02 Jul 2025
Posts: 24
Own Kudos:
Given Kudos: 2
Posts: 24
Kudos: 17
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
31120170423
Joined: 21 Jul 2020
Last visit: 19 Jul 2025
Posts: 33
Own Kudos:
Given Kudos: 4
Posts: 33
Kudos: 26
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Must be true: A team member identified the need for the software for the project.
Must be false: The project manager submitted a license request after a team member had already started using the software for the project.

As per the information provided in the passage, let's eliminate the options:

1)The project manager submitted a license request after a team member had already started using the software for the project. Must be false.
Since the project manager ensured that everyone complied with all policy requirements, and any employee cannot be using the software before the request is submitted because it will not be available.

2)The project manager’s team used the software for the project only during the official project timeline.
We cannot say this for sure without the usage log.
3)The project manager submitted the usage logs exactly 10 days after the project ended.
Can be true or cannot be true. we don't know.
4)A team member identified the need for the software for the project. Must be True.
As someone has to identify the need before the project manager submits the request.

5)The majority of the project-related expenses were related to licensing the software.
We do not have any iformation about what other expenses are.
User avatar
DataGuyX
Joined: 23 Apr 2023
Last visit: 06 Nov 2025
Posts: 107
Own Kudos:
77
 [1]
Given Kudos: 161
Location: Brazil
Concentration: Entrepreneurship, Technology
Posts: 107
Kudos: 77
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The rules:

First: Manager Requires License AND get approval
Then: Employee could use the software

First: software license is assigned to employees
Then: software available

First: Software available
Then: project can begins

Restrictions:
1. employee can use software only during project duration.
2. Project logs must be submitted within 15 days after the project concludes.

“ A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.”

Ok, let’s evaluate the options:

First option: The project manager submitted a license request after a team member had already started using the software for the project.
This MUST BE FALSE, because of the first rule mapped.

Second option: The project manager's team used the software for the project only during the official project timeline.
This MUST BE TRUE, because of our first restriction.

Third option: The project manager submitted the usage logs exactly 10 days after the project ended.
We don’t know, only know that need to submit within 15 days. It could be 10 days but could not be. This does not must be MUST TRUE neither MUST FALSE. Ignore this option.

Fourth option: A team member identified the need for the software for the project.
We don’t know and it’s not relevant. Could be true and could be false. Ignore this option.

Fifth option: The majority of the project-related expenses were related to licensing the software.
We don’t know and it’s not relevant. Could be true and could be false. Ignore this option.
User avatar
sayan640
Joined: 29 Oct 2015
Last visit: 10 Nov 2025
Posts: 1,179
Own Kudos:
Given Kudos: 783
GMAT 1: 570 Q42 V28
Products:
GMAT 1: 570 Q42 V28
Posts: 1,179
Kudos: 813
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The answer :-
Must be true :- The project manager’s team used the software for the project only during the official project timeline.
Must be false :- The project manager submitted a license request after a team member had already started using the software for the project.

Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­
User avatar
SumnerSCB
Joined: 27 Apr 2025
Last visit: 08 Sep 2025
Posts: 36
Own Kudos:
22
 [1]
Posts: 36
Kudos: 22
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­
A key word is in the last part. They complied with all policy requirements. Going through we see that they must submit a license request before any employees use the software. That means the first line must be false. The next line says it was only used within the project timeline this must be true because it is stated as the requirements. When we go further down we see things that were never stated 10 days nope said 15. Largest expense, maybe.
User avatar
Aashimabhatia
Joined: 29 Aug 2024
Last visit: 15 Nov 2025
Posts: 46
Own Kudos:
25
 [1]
Given Kudos: 655
Posts: 46
Kudos: 25
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The company’s policy states that software can only be used after a license request has been submitted and approved, and that employees may use the software only during the official project timeline, which begins after the software is made available. We're told that the project manager obtained the license and ensured full compliance with all policy requirements. This means that all actions followed the correct sequence. So, it must be true that the team used the software only during the official project timeline, because using it outside that period would violate the policy.

On the other hand, the statement saying the license request was submitted after a team member had already started using the software directly contradicts the required order of steps and the claim that the policy was fully followed. Therefore, this scenario must be false.
User avatar
tgsankar10
Joined: 27 Mar 2024
Last visit: 18 Nov 2025
Posts: 281
Own Kudos:
390
 [1]
Given Kudos: 83
Location: India
Posts: 281
Kudos: 390
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Option C: The project manager submitted the usage logs exactly 10 days after the project ended.

Since the usage logs must be submitted within 15 days after the project concludes, the manager might have submitted after or before 10 days. Eliminated

Option D: A team member identified the need for the software for the project

There is no supporting statement in the policy related to who identifies the need for software. Eliminated

Option E: The majority of the project-related expenses were related to licensing the software.

The policy does not concern about the project-related expenses. Eliminated

Option A: The project manager submitted a license request after a team member had already started using the software for the project

Th licenses will be assigned to employees, only after the approval of license request by project manager. Must be false

Option B: The project manager’s team used the software for the project only during the official project timeline.

The policy clearly states that the employees may use the software only during the official project timeline. Must be true


Must be true: B
Must be false: A
User avatar
Manu1995
Joined: 30 Aug 2021
Last visit: 11 Nov 2025
Posts: 81
Own Kudos:
55
 [1]
Given Kudos: 18
Posts: 81
Kudos: 55
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
let's evaluate each statement:

1. "The project manager submitted a license request after a team member had already started using the software for the project."
Policy Point : "a project manager must submit a license request and receive approval before any employee may use the software."
This statement must be false

2)"The project manager's team used the software for the project only during the official project timeline."
Policy Point : "Employees may use the software only during the official project timeline."
Therefore statement must be true

3)"The project manager submitted the usage logs exactly 10 days after the project ended."
Policy Point : "usage logs must be submitted within 15 days after the project concludes."
Therefore, this statement Cannot be determined / Not necessarily true or false.

4)"A team member identified the need for the software for the project.
The policy outlines how a license is obtained and used (PM requests, employees use, logs submitted). It doesn't specify who identifies the initial need for the software.
Therefore, this statement Cannot be determined / Not necessarily true or false.

5) "The majority of the project-related expenses were related to licensing the software."
The policy concerns the process of obtaining and using software licenses. It does not provide any information about project budgets, costs, or the relative proportion of expenses.
Therefore, this statement Cannot be determined / Not necessarily true or false.
User avatar
Mardee
Joined: 22 Nov 2022
Last visit: 16 Oct 2025
Posts: 127
Own Kudos:
110
 [1]
Given Kudos: 17
Products:
Posts: 127
Kudos: 110
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The given scenario is,

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

To solve this lets go over each statement 1 by 1

The project manager submitted a license request after a team member had already started using the software for the project.
This must be false because the policy specifically requires that “a project manager must submit a license request and receive approval before any employee may use the software.”
If the license was submitted after a team member started using the software, it would violate the policy which means this scenario couldnt have happened

The project manager’s team used the software for the project only during the official project timeline.
This must be true as it is directly in line with the policy that "Employees may use the software only during the official project timeline." Considering the project manager has done the required compliance, this must be true

The project manager submitted the usage logs exactly 10 days after the project ended.
This is allowed as the deadline is 15 days but it’s not something that must be true

A team member identified the need for the software for the project.
The policy doesent restrict who can identify the need, it just restricts who can submit the license request. So it can be false or true

The majority of the project-related expenses were related to licensing the software.
The policy doesent say anything about costs or expenses. So this statement doesent matter

Must be true: The project manager’s team used the software for the project only during the official project timeline.
Must be false: The project manager submitted a license request after a team member had already started using the software for the project.
User avatar
jkkamau
Joined: 25 May 2020
Last visit: 18 Nov 2025
Posts: 132
Own Kudos:
Given Kudos: 122
Location: Kenya
Schools: Haas '25
GMAT 1: 730 Q50 V46
GPA: 3.5
Products:
Schools: Haas '25
GMAT 1: 730 Q50 V46
Posts: 132
Kudos: 107
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Choice A must be false because there is no way a team member can use the software before licensing and approval
Choice B must be true as it is indicated that " Employees may use the software only during the official project timeline"

ANS BA
Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­
User avatar
RedYellow
Joined: 28 Jun 2025
Last visit: 09 Nov 2025
Posts: 80
Own Kudos:
74
 [1]
Posts: 80
Kudos: 74
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Correct answers are:
Must be true = "The project manager’s team used the software for the project only during the official project timeline." as in the text it is said that employees may use the software only during the official project timeline.

Must be false = "The project manager submitted a license request after a team member had already started using the software for the project." as in the text it is said that a project manager must submit a license request and receive approval before any employee may use the software.

In the others:
"exactly 10 days" is incorrect, "who identifies the need" and "project-related expenses" are not mencioned.
User avatar
UfuomaOh
Joined: 14 Sep 2023
Last visit: 17 Nov 2025
Posts: 83
Own Kudos:
Given Kudos: 14
Products:
Posts: 83
Kudos: 50
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The project manager submitted a license request after a team member had already started using the software for the project.

this clearly negates this: According to the policy, a project manager must submit a license request and receive approval before any employee may use the software.

If project manager and the team members complied with all policy requirements then it is impossible that the license request was submitted after a team member had already started using the software for the project.

The project manager’s team used the software for the project only during the official project timeline

This must be true to support this Employees may use the software only during the official project timeline

This does not necessarily have to be true The project manager submitted the usage logs exactly 10 days after the project ended

as the project allows usage logs to be submitted within 15 days after the project concludes.
User avatar
Jarvis07
Joined: 06 Sep 2017
Last visit: 18 Nov 2025
Posts: 295
Own Kudos:
236
 [1]
Given Kudos: 160
GMAT 1: 750 Q50 V41
GMAT 1: 750 Q50 V41
Posts: 295
Kudos: 236
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Because the project manager secured approval before anyone ever accessed the software and strictly followed the official start and end dates, it follows that the team could only use the software during the sanctioned project timeline, making that statement necessarily true. Also, since no one was allowed to use the software until after the license request was approved, it’s impossible that the manager requested the license only after a team member had already begun using the software, so that statement must be false.

Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­
User avatar
Lemniscate
Joined: 28 Jun 2025
Last visit: 09 Nov 2025
Posts: 80
Own Kudos:
72
 [1]
Posts: 80
Kudos: 72
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
From the text we can deduce that the answers are:

Must be true: The project manager’s team used the software for the project only during the official project timeline.
The text says that "Employees may use the software only during the official project timeline"

Must be false: The project manager submitted a license request after a team member had already started using the software for the project.
The text says that "According to the policy, a project manager must submit a license request and receive approval before any employee may use the software"

Incorrect:
"The project manager submitted the usage logs exactly 10 days after the project ended.". The text says within 15 days, no exactly 10, so this can be true or false.
"A team member identified the need for the software for the project.". The text does not say who identifies the need.
"The majority of the project-related expenses were related to licensing the software.". The text does not talk about expenses.
User avatar
harishg
Joined: 18 Dec 2018
Last visit: 18 Nov 2025
Posts: 85
Own Kudos:
100
 [1]
Given Kudos: 27
Products:
Posts: 85
Kudos: 100
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
As per the given conditions and scanning the answer choices, we find that

The project manager submitted a license request after a team member had already started using the software for the project - This is a must be false statement since the project manager adhered to all the rules. He must have definitely submitted the request before the usage of the software.

Similarly, The project manager’s team used the software for the project only during the official project timeline - is a must true statement. One of the conditions to be followed is that [color=#0f0f0f]Employees only use the software during the official project timeline.[/color]

Other statements provided may be true or may be false.

Therefore,

Must be True - [color=#000000]The project manager’s team used the software for the project only during the official project timeline.[/color]
[color=#000000]Must be False - The project manager submitted a license request after a team member had already started using the software for the project.[/color]
avatar
ManifestDreamMBA
Joined: 17 Sep 2024
Last visit: 18 Nov 2025
Posts: 1,282
Own Kudos:
784
 [1]
Given Kudos: 236
Products:
Posts: 1,282
Kudos: 784
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
According to the policy, a project manager must submit a license request and receive approval before any employee may use the software.
Once the request is approved, licenses may be assigned to employees, and the software is made available.
A project officially begins only after the software has been made available.
Employees may use the software only during the official project timeline, and
usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Evaluating the options:

The project manager submitted a license request after a team member had already started using the software for the project. If the project manager and the team members complied with all policy requirements, this must be FALSE, as license request needs to be submitted before the team starts using the software

The project manager’s team used the software for the project only during the official project timeline. If the project manager and the team members complied with all policy requirements, this must be TRUE, as this is aligned with the policy

The project manager submitted the usage logs exactly 10 days after the project ended. We don't know if the usage logs were submitted exactly after 1 day, 5 day or 10 days after the project ended. We don't know enough to comment this is TRUE

A team member identified the need for the software for the project. We don't know who identified the need for the software for the project, it could be manager or team member or someone else

The majority of the project-related expenses were related to licensing the software. We don't know the split of project-related expenses to comment on that
Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­
User avatar
Aarushi100
Joined: 17 Jul 2024
Last visit: 18 Nov 2025
Posts: 56
Own Kudos:
44
 [1]
Given Kudos: 88
Products:
Posts: 56
Kudos: 44
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­

Must be true: The statement must hold true throughout, under any circumstances.
Must be false: The statement must hold false throughout, under any circumstances.
Here no question of maybe or could be arises.

1. The project manager submitted a license request after a team member had already started using the software for the project.

This statement MUST BE FALSE.
It is clearly stated under the company's policy that any employee must use the software only after getting approval, after which the licenses are assigned.

2. The project manager’s team used the software for the project only during the official project timeline.
This statement MUST BE TRUE.
According to the company's policies, the software must only be used during the project's timeline.

3. The project manager submitted the usage logs exactly 10 days after the project ended.
Can be true or cannot be true. As the project manager had 15 days to submit. So the PM can submit the logs at any time within this time frame.

4. A team member identified the need for the software for the project.
Again, can be true or cannot be true. Maybe the Project Manager identified the need for it. No specific info provided for it.

5. The majority of the project-related expenses were related to licensing the software.
No info regarding this is given. It can or cannot be true.

ANSWER:
MUST BE TRUE: 2
MUST BE FALSE: 1
User avatar
Aishna1034
Joined: 21 Feb 2023
Last visit: 18 Nov 2025
Posts: 218
Own Kudos:
64
 [1]
Given Kudos: 150
Products:
Posts: 218
Kudos: 64
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Going through the options , after reading the q stem, it MUST BE TRUE that project manager's team used the software only during the projects timeline as given in the Q text, not after, and for MUST BE FALSE, he cant send request after team started working on the project. It can not be true. Bunuel
 


This question was provided by GMAT Club
for the GMAT Club Olympics Competition

Win over $30,000 in prizes such as Courses, Tests, Private Tutoring, and more

 



A company has a policy governing the use of software licenses and the reporting of software usage for internal projects. According to the policy, a project manager must submit a license request and receive approval before any employee may use the software. Once the request is approved, licenses may be assigned to employees, and the software is made available. A project officially begins only after the software has been made available. Employees may use the software only during the official project timeline, and usage logs must be submitted within 15 days after the project concludes.

A project manager obtained a software license for the project and ensured that both the project manager and the team members complied with all policy requirements.

Select for Must be true the statement that must be true given the information provided and select for Must be false the statement that must be false given the information provided. Make only two selections, one in each column.­