GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 18 Feb 2019, 14:41

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel
Events & Promotions in February
PrevNext
SuMoTuWeThFrSa
272829303112
3456789
10111213141516
17181920212223
242526272812
Open Detailed Calendar
  • Valentine's day SALE is on! 25% off.

     February 18, 2019

     February 18, 2019

     10:00 PM PST

     11:00 PM PST

    We don’t care what your relationship status this year - we love you just the way you are. AND we want you to crush the GMAT!
  • Get FREE Daily Quiz for 2 months

     February 18, 2019

     February 18, 2019

     10:00 PM PST

     11:00 PM PST

    Buy "All-In-One Standard ($149)", get free Daily quiz (2 mon). Coupon code : SPECIAL

Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

 
Manager
Manager
avatar
B
Joined: 11 Jun 2018
Posts: 64
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post Updated on: 17 Jan 2019, 20:38
1
3
00:00
A
B
C
D
E

Difficulty:

  45% (medium)

Question Stats:

66% (01:56) correct 34% (01:43) wrong based on 95 sessions

HideShow timer Statistics

Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectively. If all the 3 machines work together to finish the work, then what part of the finished work does the fastest machine do?

A) 1/4
B) 1/6
C) 1/8
D) 13/6
E) 6/13

Originally posted by Manat on 17 Jan 2019, 18:09.
Last edited by Bunuel on 17 Jan 2019, 20:38, edited 1 time in total.
Renamed the topic and edited the question.
Director
Director
avatar
G
Joined: 09 Mar 2018
Posts: 986
Location: India
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 18:16
Manat wrote:
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectively. If all the 3 machines work together to finish the work, then what part of the finished work does the fastest machine do?

A) 1/4
B) 1/6
C) 1/8
D) 13/6
E) 6/13


Are you getting B ??

= 4 / 24
= 1 / 6
_________________

If you notice any discrepancy in my reasoning, please let me know. Lets improve together.

Quote which i can relate to.
Many of life's failures happen with people who do not realize how close they were to success when they gave up.

Manager
Manager
avatar
B
Joined: 11 Jun 2018
Posts: 64
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 19:07
Yes i got B. if the question had mentioned what part of the work is done in 1 hour, then i would have chosen 6/13 the OA. Confused

Posted from my mobile device
Director
Director
avatar
G
Joined: 09 Mar 2018
Posts: 986
Location: India
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 19:19
Manat wrote:
Yes i got B. if the question had mentioned what part of the work is done in 1 hour, then i would have chosen 6/13 the OA. Confused

Posted from my mobile device


IMO, the question has not asked that.

Lets see if someone else adds something to this. :)
_________________

If you notice any discrepancy in my reasoning, please let me know. Lets improve together.

Quote which i can relate to.
Many of life's failures happen with people who do not realize how close they were to success when they gave up.

Manager
Manager
avatar
B
Joined: 11 Jun 2018
Posts: 64
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 19:46
chetan2u Bunuel :-Could you please confirm if OA is correct?
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 52938
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 20:45
3
Manat wrote:
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectively. If all the 3 machines work together to finish the work, then what part of the finished work does the fastest machine do?

A) 1/4
B) 1/6
C) 1/8
D) 13/6
E) 6/13


The combined rate of the three machines is 1/4 + 1/6 + 1/8 = 13/24 work/hour. So, working together they can do the job in 24/13 hours. In this time the fastest machine, the one that can do the job in 4 hours, would have done 1/4*24/13 = 6/13 part of the job (job done = rate*time).

Answer: E.

P.S. Please name topics properly. Check rule 3 here: https://gmatclub.com/forum/rules-for-po ... 33935.html Thank you.
_________________

New to the Math Forum?
Please read this: Ultimate GMAT Quantitative Megathread | All You Need for Quant | PLEASE READ AND FOLLOW: 12 Rules for Posting!!!

Resources:
GMAT Math Book | Triangles | Polygons | Coordinate Geometry | Factorials | Circles | Number Theory | Remainders; 8. Overlapping Sets | PDF of Math Book; 10. Remainders | GMAT Prep Software Analysis | SEVEN SAMURAI OF 2012 (BEST DISCUSSIONS) | Tricky questions from previous years.

Collection of Questions:
PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. ,11 Mixed Questions, 12 Fresh Meat

DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS; 9 Devil's Dozen!!!; 10 Number Properties set., 11 New DS set.


What are GMAT Club Tests?
Extra-hard Quant Tests with Brilliant Analytics

Math Expert
User avatar
V
Joined: 02 Aug 2009
Posts: 7334
Premium Member Reviews Badge
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 17 Jan 2019, 20:51
1
Manat wrote:
chetan2u Bunuel :-Could you please confirm if OA is correct?

The OA is correct..

Each working together, the work can be done in
(1/4)+(1/6)+(1/8)=13/24th work in one hour, so complete work in 24/13 hour..
Now the fastest machine can do the work in 4 hours so in 24/13 hours he can do (1 hour work)*(number of hours)=(1/4)*(24/13)=6/13..

Also how can fastest machine do just 1/6 of work, which means someone will do more than 1/6 of work. But fastest should do the maximum portion of work...
_________________

1) Absolute modulus : http://gmatclub.com/forum/absolute-modulus-a-better-understanding-210849.html#p1622372
2)Combination of similar and dissimilar things : http://gmatclub.com/forum/topic215915.html
3) effects of arithmetic operations : https://gmatclub.com/forum/effects-of-arithmetic-operations-on-fractions-269413.html
4) Base while finding % increase and % decrease : https://gmatclub.com/forum/percentage-increase-decrease-what-should-be-the-denominator-287528.html


GMAT Expert

SVP
SVP
User avatar
G
Joined: 18 Aug 2017
Posts: 1810
Location: India
Concentration: Sustainability, Marketing
GPA: 4
WE: Marketing (Energy and Utilities)
GMAT ToolKit User Premium Member CAT Tests
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 18 Jan 2019, 03:43
1
Manat wrote:
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectively. If all the 3 machines work together to finish the work, then what part of the finished work does the fastest machine do?

A) 1/4
B) 1/6
C) 1/8
D) 13/6
E) 6/13



total rate of three machines = 1
so part of rate done by each machine = 13/24
and total time : 24/13
work done by fastest machine would be the one which has lowest hrs i.e 4 and rate : 1/4
so work of machine = rate * time = 24 /13*1/ 4= 6/13 IMO E
_________________

If you liked my solution then please give Kudos. Kudos encourage active discussions.

Intern
Intern
avatar
B
Joined: 17 Dec 2018
Posts: 21
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 18 Jan 2019, 04:13
Really you can answer this question using the provided options and logic without ever doing any math.

There are 3 machines completing 1 task, if all machines worked at the same pace they would each complete 1/3 of the task. We know that 1 of the machines is the fastest and therefore will complete more than 1/3rd of the task because it is more productive than the others. This immediately eliminates A, B, and C as all are less than 1/3. D is eliminated because a machine cannot complete more than 100% of the task. Thus E is the only possible answer.

Posted from my mobile device
Director
Director
avatar
G
Joined: 09 Mar 2018
Posts: 986
Location: India
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 18 Jan 2019, 06:35
1
Manat wrote:
Yes i got B. if the question had mentioned what part of the work is done in 1 hour, then i would have chosen 6/13 the OA. Confused

Posted from my mobile device


Afterall the OA was correct.

I again took an attempt at it, I solved it at paper this time( last time i didn't)

Work = rate * time

Total Time = 1/4 + 1/6 + 1/ 8 = 13/24

Took W as 1

Now if we take work as W, then rate = 24 / 13

Now what part of the finished work does the fastest machine do will be
rate * time
=> 24/13 * 1/4
=> 6/13
_________________

If you notice any discrepancy in my reasoning, please let me know. Lets improve together.

Quote which i can relate to.
Many of life's failures happen with people who do not realize how close they were to success when they gave up.

Intern
Intern
avatar
B
Joined: 24 Dec 2011
Posts: 28
Location: India
GPA: 4
WE: General Management (Health Care)
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 19 Jan 2019, 10:30
given that each machine completes the work in that many hours. not the rate of work done by each machine.
rate of work done by each machine
A- 1/4
B-1/6
C-1/8

TOTAL work done by three machines in one hour is equal to combined rates of work
1/4+1/6+1/8=13/24

fastest machine is the one which completes the work in shortest time i.e. 1/4

asked about the part by whole
(1/4)/(13/24)=6/13
Board of Directors
User avatar
P
Status: QA & VA Forum Moderator
Joined: 11 Jun 2011
Posts: 4383
Location: India
GPA: 3.5
WE: Business Development (Commercial Banking)
GMAT ToolKit User Premium Member CAT Tests
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 20 Jan 2019, 08:04
Manat wrote:
Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectively. If all the 3 machines work together to finish the work, then what part of the finished work does the fastest machine do?

A) 1/4
B) 1/6
C) 1/8
D) 13/6
E) 6/13


Let the total work be 24 (LCM of 4,6 & 8)

Efficiency of the 3 machines are 6 , 4 & 3

Thus, part of the finished work done by the fastest worker is \(\frac{6}{( 6+ 4 + 3)} = \frac{6}{13}\)

Fastest Worker = Worker having the highest efficiency

Thus, Answer must be (E)
_________________

Thanks and Regards

Abhishek....

PLEASE FOLLOW THE RULES FOR POSTING IN QA AND VA FORUM AND USE SEARCH FUNCTION BEFORE POSTING NEW QUESTIONS

How to use Search Function in GMAT Club | Rules for Posting in QA forum | Writing Mathematical Formulas |Rules for Posting in VA forum | Request Expert's Reply ( VA Forum Only )

Intern
Intern
avatar
B
Status: when you say,"I can or I can't", Both times you are right!
Joined: 26 Nov 2018
Posts: 9
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel  [#permalink]

Show Tags

New post 22 Jan 2019, 09:06
time is taken by machines 4, 6 & 8 hours to complete a task individuality
it means their efficiencies are 6 / 4 / 3 (Because LCM is 24 for 4,6 and 8 and 24 is further divided by 4 /6/ 8 )

Hence, 6/6+4+3 gives 6/13 (a portion of the fastest machine)
GMAT Club Bot
Re: Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel   [#permalink] 22 Jan 2019, 09:06
Display posts from previous: Sort by

Three machines can finish a work in 4 hrs, 6 hrs and 8 hrs respectivel

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  


Copyright

GMAT Club MBA Forum Home| About| Terms and Conditions and Privacy Policy| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.