Last visit was: 25 Apr 2026, 08:41 It is currently 25 Apr 2026, 08:41
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
avatar
cv3t3l1na
Joined: 22 Oct 2012
Last visit: 31 Dec 2012
Posts: 7
Own Kudos:
186
 [31]
Given Kudos: 1
Posts: 7
Kudos: 186
 [31]
4
Kudos
Add Kudos
26
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 25 Apr 2026
Posts: 109,827
Own Kudos:
Given Kudos: 105,878
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,827
Kudos: 811,213
 [13]
9
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
General Discussion
User avatar
GMATinsight
User avatar
Major Poster
Joined: 08 Jul 2010
Last visit: 25 Apr 2026
Posts: 6,977
Own Kudos:
16,916
 [1]
Given Kudos: 128
Status:GMAT/GRE Tutor l Admission Consultant l On-Demand Course creator
Location: India
GMAT: QUANT+DI EXPERT
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
WE:Education (Education)
Products:
Expert
Expert reply
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
Posts: 6,977
Kudos: 16,916
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
TimeTraveller
Joined: 28 Jun 2015
Last visit: 29 Jul 2017
Posts: 237
Own Kudos:
361
 [3]
Given Kudos: 47
Concentration: Finance
GPA: 3.5
Posts: 237
Kudos: 361
 [3]
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Apprentices: 50 * 4 = 200 job-hours. 1 apprentice's job-hour = 1/200.

Journeymen: 30 * 4.5 = 135 job-hours. 1 journeymen's job-hour = 1/135.

Job done by (10 apprentices + 15 journeymen) = 10/200 + 15/135 = 1/20 + 1/9 = 29/180. Ans (B).
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 25 Apr 2026
Posts: 11,229
Own Kudos:
45,018
 [2]
Given Kudos: 335
Status:Math and DI Expert
Location: India
Concentration: Human Resources, General Management
GMAT Focus 1: 735 Q90 V89 DI81
Products:
Expert
Expert reply
GMAT Focus 1: 735 Q90 V89 DI81
Posts: 11,229
Kudos: 45,018
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
If 50 apprentices can finish a job in 4 hours and 30 skilled workers can finish the same job in 9/2 hours, how much of the job should be completed by 10 apprentices and 15 skilled workers in 1 hour?

(A) 1/9
(B) 29/180
(C) 26/143
(D) 1/5
(E) 39/121


hi..

If 50 apprentices can finish a job in 4 hours, 10 apprentices will finish it in \(4*\frac{50}{10}=20\)
so 1 hour work of 10 apprentices = \(\frac{1}{20}\)

and 30 skilled workers can finish the same job in 9/2 hours, so 15 will do it in 9 h
so 1 hour work of 15 skilled workers = \(\frac{1}{9}\)

so their combined work = \(\frac{1}{20}+\frac{1}{9}=\frac{29}{180}\)

B
User avatar
sasyaharry
Joined: 22 Nov 2016
Last visit: 11 Mar 2023
Posts: 199
Own Kudos:
363
 [3]
Given Kudos: 49
Concentration: Leadership, Strategy
Products:
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
First, find individual rates.

Apprentices:

50 complete 1 job in 4 hours.
50 complete 1/4th of a job in 1 hour.
1 completes\(\frac{1}{4*50}\) or\(\frac{1}{200}\) of a job in 1 hour.

Similarly for skilled workers:

30 complete 1 job in 9/2 hours.
30 complete 2/9 of the job in 1 hour.
1 completes \(\frac{2}{9*30}\) or \(\frac{2}{270}\) or \(\frac{1}{135}\) job in 1 hour.

Work done by 10 Apprentices and 15 skilled workers in 1 hour = \(10*\frac{1}{200}+15*\frac{1}{135} = \frac{29}{180}\)
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 24 Apr 2026
Posts: 22,286
Own Kudos:
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,286
Kudos: 26,536
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
If 50 apprentices can finish a job in 4 hours and 30 skilled workers can finish the same job in 9/2 hours, how much of the job should be completed by 10 apprentices and 15 skilled workers in 1 hour?

(A) 1/9
(B) 29/180
(C) 26/143
(D) 1/5
(E) 39/121

The rate of 50 apprentices is 1/4 and the rate of 30 skilled workers is 1/(9/2) = 2/9.

We can use a proportion to determine n, the rate of 10 apprentices:

50/(1/4) = 10/n

200 = 10/n

200n = 10

n = 10/200 = 1/20

We can also use a proportion to determine m, the rate of 15 skilled workers:

30/(2/9) = 15/m

(9 x 30)/2 = 15/m

135 = 15/m

135m = 15

m = 15/135 = 1/9

Thus, the fraction of a job completed by 10 apprentices and 15 skilled workers in 1 hour is 1/20 + 1/9 = 9/180 + 20/180 = 29/180.

Answer: B
avatar
pavanbatra
Joined: 08 Feb 2021
Last visit: 17 Mar 2022
Posts: 5
Own Kudos:
Given Kudos: 219
Posts: 5
Kudos: 18
Kudos
Add Kudos
Bookmarks
Bookmark this Post
can anyone please explain what's wrong here?

50 apprentices take 4 hours.. so each hour they would complete 50/4 =25/2 of the job.

each apprentice would do 1/50 × 25/2 = 1/4 of the job.

but the actual rate of each apprentice is 1/20.

i'm unable to grasp my mistake. Bunuel VeritasKarishma please help

Posted from my mobile device
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 23 Apr 2026
Posts: 16,442
Own Kudos:
79,409
 [2]
Given Kudos: 485
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,442
Kudos: 79,409
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
pavanbatra
can anyone please explain what's wrong here?

50 apprentices take 4 hours.. so each hour they would complete 50/4 =25/2 of the job.

each apprentice would do 1/50 × 25/2 = 1/4 of the job.

but the actual rate of each apprentice is 1/20.

i'm unable to grasp my mistake. Bunuel VeritasKarishma please help

Posted from my mobile device

50 apprentices take 4 hours.. so each hour they would complete 50/4 =25/2 of the job.

This is not correct. They need to complete 1 job. They complete it in 4 hrs. It means, every hour 50 apprentices work together to complete 1/4th of the job.

50 apprentices complete 1/4th of the job every hour
So 10 apprentices must be doing (1/4)/5 = 1/20th of the job every hour

Note what is meant by 25/2 of the job. This is equal to 12.5 of the job i.e. 12.5 times the initial job.
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,985
Own Kudos:
Posts: 38,985
Kudos: 1,117
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.