Last visit was: 19 Nov 2025, 05:26 It is currently 19 Nov 2025, 05:26
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,385
Own Kudos:
778,206
 [6]
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,385
Kudos: 778,206
 [6]
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,385
Own Kudos:
778,206
 [1]
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,385
Kudos: 778,206
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
General Discussion
User avatar
hr1212
User avatar
GMAT Forum Director
Joined: 18 Apr 2019
Last visit: 17 Nov 2025
Posts: 621
Own Kudos:
924
 [1]
Given Kudos: 1,483
GMAT Focus 1: 775 Q90 V85 DI90
Products:
Expert
Expert reply
GMAT Focus 1: 775 Q90 V85 DI90
Posts: 621
Kudos: 924
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Sanjay9822
Joined: 20 Dec 2024
Last visit: 26 Jan 2025
Posts: 25
Own Kudos:
19
 [1]
Given Kudos: 6
Posts: 25
Kudos: 19
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.
We are tasked to determine the approximate projected costs for Raw Materials and Recycling/Waste Management for 2024 based on the provided information.

[*]2024 total costs:
925000000 * 0.97 = 897250000
[*]2024 project materials cost:
897250000 * 0.42 = 376845000
[*]Raw materials cost:
376845000 * 0.85 = 320318250 approximately 320000000
[*]Recycling/Waste management cost:
376845000 * 0.15 = 56526750 approximately 57000000
User avatar
aviraj1703
Joined: 27 May 2024
Last visit: 10 Mar 2025
Posts: 98
Own Kudos:
122
 [1]
Given Kudos: 6
Posts: 98
Kudos: 122
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
2024 total project costs: $925M × 0.97 = $897.25M

2024 materials costs (42%): $897.25M × 0.42 = $376.845M

Split materials costs:
Raw Materials (85%): $376.845M × 0.85 = $320.32M
Recycling/Waste (15%): $376.845M × 0.15 = $56.53M

Answer:
Raw Materials Cost 2024: $320,000,000
Recycling/Waste Management Cost 2024: $57,000,000
User avatar
miniB21
Joined: 06 Sep 2024
Last visit: 18 Nov 2025
Posts: 88
Own Kudos:
26
 [1]
Given Kudos: 55
Posts: 88
Kudos: 26
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Pretty straightforward and calculation based:
decrease 3% of $925M = $897.25M
42% of the new 2024 total project costs = $376.8M
Then simply calculate raw materials at 85%of 376.8M= $320M and recycling at 15% of $376.8M = $57M
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 18 Nov 2025
Posts: 5,794
Own Kudos:
5,509
 [1]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,794
Kudos: 5,509
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.

2023: -
Project materials cost = 38% *$925,000,000

2024: -
Project materials cost = 42% *$925,000,000*97%
Raw materials cost = 85%*42%*$925,000,000*97% = $320,318,250 = $320,000,000 approx
Recycling/Waste Management Cost = 15%*42%*$925,000,000*97% = $56,526,750 = $57,000,000 approx

Raw Materials Cost for 2024Recycling/Waste Management Cost for 2024
$320,000,000$57,000,000
User avatar
Heix
Joined: 21 Feb 2024
Last visit: 18 Nov 2025
Posts: 362
Own Kudos:
153
 [1]
Given Kudos: 63
Location: India
Concentration: Finance, Entrepreneurship
GMAT Focus 1: 485 Q76 V74 DI77
GPA: 3.4
WE:Accounting (Finance)
Products:
GMAT Focus 1: 485 Q76 V74 DI77
Posts: 362
Kudos: 153
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let's approach this problem step by step:

1. Calculate the total project costs for 2024: 2023 costs: $925,000,000 2024 costs: $925,000,000 * (1 - 0.03) = $897250,000

2. Calculate the project materials costs for 2024: 42% of $897,250,000 = 0.42 × $897,250,000 = $376,845,000

3. Calculate the raw materials costs for 2024 (85% of project materials): 85% of $376,845,000 = 0.85 x $376,845,000 = $320,318,250

4. Calculate the recycling/waste management costs for 2024(15% of project materials): 15% of $376,845,000 = 015 × $376.845,000 = $56,526,750

5. Match these calculations to the closest values in the table: - Raw Materials Cost for 2024: $320,318,250 - $320,000,000Recycling/Waste Management Cost for 2024: $56,526,750 - 57000000 (approx)

Therefore, the correct selections are:

Raw Materials Cost for 2024: $320,000,000

Recycling/Waste Management Cost for 2024: $57,000,000
User avatar
AbhiS101
Joined: 03 Jul 2024
Last visit: 28 Oct 2025
Posts: 80
Own Kudos:
85
 [1]
Given Kudos: 19
Location: India
GPA: 68%
Posts: 80
Kudos: 85
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.

The total project costs for 2024:
Total project costs in 2023 = $925,000,000
Decrease in total project costs in 2024 = 3%
Total project costs in 2024 = $925,000,000 * (1 - 0.03) = $925,000,000 * 0.97 = $897,250,000
Calculate the projected cost of project materials in 2024:
Project materials will account for 42% of total project costs in 2024.
Projected cost of project materials in 2024 = $897,250,000 * 0.42 = $376,815,000
Calculate the approximate projected cost devoted to raw materials and recycling/waste management:
Raw materials make up 85% of project materials costs.
Recycling/waste management accounts for the remaining 15% of project materials costs.
Approximate Projected Costs for 2024:
Raw Materials Cost: $376,815,000 * 0.85 = $320,577,750 (closest option is $320,000,000)
Recycling/Waste Management Cost: $376,815,000 * 0.15 = $56,522,250 (closest option is $57,000,000)
Therefore, the approximate projected costs for 2024 are:
Raw Materials Cost: $320,000,000
Recycling/Waste Management Cost: $57,000,000
User avatar
GraCoder
Joined: 15 Dec 2024
Last visit: 15 Jun 2025
Posts: 65
Own Kudos:
70
 [1]
Given Kudos: 19
Posts: 65
Kudos: 70
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.
Total project cost = 97% * 925M => 897.25M
Project material cost = 42% * 897.25M = 376.845M

Raw material cost = 85% * 376.845M = 320M
Recycling cost = 15% * 376.845M = 57M
User avatar
nousernamefine
Joined: 14 Jan 2024
Last visit: 05 Nov 2025
Posts: 29
Own Kudos:
28
 [1]
Given Kudos: 131
Location: India
GPA: 4
Posts: 29
Kudos: 28
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total Project cost in 2024= 925000000*97%= 897250000
Material cost in 2024= 897250000*42%= 376845000

Share of RM= 376845000*85%=320318250= 320 Million
Share of recycling and waste mgmt.= 376845000*15%=56526750= 57 Million

ANs= 320000000 and 57000000
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.
User avatar
RahulPMT
Joined: 20 Dec 2024
Last visit: 05 Jul 2025
Posts: 34
Own Kudos:
42
 [1]
Given Kudos: 3
Posts: 34
Kudos: 42
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
What I have found is even in TPA questions where unique answer is possible to calculate using given data, "ratio' b/w the two values in the given columns can greatly help.

Here as well simply look col 1: col 2=85:15
i.e Raw Material Cost =(17/3) recycling cost

from the options recycling should be $57,000,000 {since should be divisible by 3}
{I know question did mention 'approx cost' but i would still try to go with this one first and see if we can find a suitable value, if not then i would use $70,000,000}

but here using recycling = $57,000,000 we get raw material =323,000,000 --> approx 320,000,000.

DONE!
User avatar
crimson_king
Joined: 21 Dec 2023
Last visit: 19 Nov 2025
Posts: 127
Own Kudos:
131
 [1]
Given Kudos: 103
GRE 1: Q170 V170
GRE 1: Q170 V170
Posts: 127
Kudos: 131
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Annual project costs of $925,000,000 in 2023 & in 2024, total project costs are expected to decrease by 3% hence the annual project costs in 2024 will be equal to $925,000,000*0.97=$897,250,000 roughly

Project materials will now account for 42% of total project costs hence 897.25 million dollars*0.42=$376,845,00 roughly

Out of these costs, 85% of the costs go towards Raw Materials Cost & the remaining goes to Recycling/Waste Management Costs:

Hence those costs in 2024 would be:
Raw Materials Cost=$376,845,000*0.85=$320,000,000 (roughly)
Recycling/Waste Management Costs=Remaing costs(Total Costs- Raw Materials Cost)=377-320 million dollars=$57,000,000
User avatar
nishantswaft
User avatar
ISB School Moderator
Joined: 17 Oct 2024
Last visit: 10 Oct 2025
Posts: 160
Own Kudos:
114
 [1]
Given Kudos: 18
Posts: 160
Kudos: 114
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In TPA questions its always better to form a strategy first before solving. Well this is a detail bulky question.

The stem tells us that;
  • At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023
  • project materials will account for 42% of total project costs in 2024
  • total project costs are expected to decrease by 3%.
  • raw materials consistently make up 85% of costs
  • recycling and waste management account for the remaining 15%.

And we have to select;

  • for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials
  • for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management

IN 2024;

Project materials = 42% of (100-3) % of $925,000,000

Hence,
raw materials recycling and waste management
85% of 42% of (100-3) % of $925,000,000 15% of 42% of (100-3) % of $925,000,000
~320,000,000~57,000,000

Hence we can fill in respective options
User avatar
A_Nishith
Joined: 29 Aug 2023
Last visit: 12 Nov 2025
Posts: 455
Own Kudos:
199
 [1]
Given Kudos: 16
Posts: 455
Kudos: 199
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Step 1: Calculate Total Project Costs for 2024
Total project costs in 2023: 925,000,000.
Total project costs are expected to decrease by 3% in 2024:
2024 Total Project Costs
2024 Total Project Costs=925,000,000×(1−0.03)=925,000,000×0.97=897,250,000.

Step 2: Calculate Project Materials Costs for 2024
Project materials will account for 42% of total project costs in 2024:
Project Materials Costs
Project Materials Costs=897,250,000×0.42=376,845,000

Step 3: Split Project Materials Costs into Raw Materials and Recycling/Waste Management
Raw materials make up 85% of project materials costs:
Raw Materials Costs=376,845,000×0.85=320,318,250≈320,000,000.

Recycling and waste management make up 15% of project materials costs:
Recycling/Waste Management Costs=376,845,000×0.15=56,526,750≈57,000,000.

Final Answer
Raw Materials Cost for 2024: $320,000,000.
Recycling/Waste Management Cost for 2024: $57,000,000.
User avatar
Akshay1298
Joined: 16 Nov 2023
Last visit: 14 Sep 2025
Posts: 36
Own Kudos:
38
 [1]
Given Kudos: 98
Posts: 36
Kudos: 38
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Calculator is mandatory for this problem.

For time-efficiency, remove all zeros.

Annual cost in 2023 = 925;
Decrease in 3% in 2024 = 925*0.97 = 897.25;

raw materials from project materials for 2024 = 0.85(0.42(897.25)) = 320(approx.); Option C
Recycling/Waste Management Cost for 2024 = 0.15(0.42(897.25)) = 57(approx.); Option E
User avatar
HarshaBujji
Joined: 29 Jun 2020
Last visit: 16 Nov 2025
Posts: 695
Own Kudos:
885
 [1]
Given Kudos: 247
Location: India
Products:
Posts: 695
Kudos: 885
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.
There is lot of info an calculations that are involved. But if you see the last line " Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15% "

So clearly our option choices has to be in the same rations 85:15 = ~5.66.

Of the options the only possible pair is 320... & 57.... Because 320/57 = ~5.61..

Hence IMO $320,000,000 & $57,000,000
User avatar
Krunaal
User avatar
Tuck School Moderator
Joined: 15 Feb 2021
Last visit: 19 Nov 2025
Posts: 805
Own Kudos:
851
 [1]
Given Kudos: 251
Status:Under the Square and Compass
Location: India
GMAT Focus 1: 755 Q90 V90 DI82
GPA: 5.78
WE:Marketing (Consulting)
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total costs in 2024 = 0.97*925,000,000 = 897,250,000

Project Materials Costs = 0.42*897,250,000 = 376,845,000

Raw materials cost = 376,845,000*0.85 = 320,318,250 which is approx. 320,000,000

Recycling and waste management cost = 376,845,000*0.15 = 57,000,000

Answer. 320,000,000 and 57,000,000
User avatar
Prakhar9802
Joined: 07 Aug 2023
Last visit: 14 Nov 2025
Posts: 63
Own Kudos:
67
 [1]
Given Kudos: 1
Posts: 63
Kudos: 67
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
2023 -
Project Cost (PC) = 925,000,000
Project Materials (PM) = 38% of 925,000,000 = 38*9,250,000

2024 -
Project Cost (PC) = 925,000,000 - 3% of 925,000,000 = 97*9,250,000
Project Materials (PM) = 42% of 97*9,250,000 = 42*97*92,500

Raw materials cost = 85% * 42*97*92,500
= 85*42*97*925
= 320,318,250
= 320,000,000 (approx)

Waste management cost = 15% 42*97*92,500
= 15*42*97*925
= 56,526,750
= 57,000,000 (approx)

Final Answer -

Raw materials cost = 320,000,000 (approx)
Waste management cost = 57,000,000 (approx)

Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes

 


This question was provided by GMAT Club
for the 12 Days of Christmas Competition

Win $40,000 in prizes: Courses, Tests & more

 



At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.

In the table, select for Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.
User avatar
MKeerthu
Joined: 12 Mar 2024
Last visit: 02 Apr 2025
Posts: 53
Own Kudos:
59
 [1]
Given Kudos: 22
Posts: 53
Kudos: 59
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The answer is 320,000,000 and 57,000,000

Project cost = 925,000,000

3% decrease in the cost = 97/100 * 925,000,000 = 897250000

42/100* 897250000 = 376845000

85/100*376845000 = 320,318,250 approximated to 320,000,000
15/100*376845000 = 56,526,750 approximated to 57,000,000