2023 project cost = 925,000,000
2024 project cost (expected 3% less) = 97% * 925,000,000 = 897,250,000
of which 42% are for materials expenses
42% * 897,250,000 = 378,845,000
of these 85% are raw materials and 15% are waste management and recycling
85% * 378,845,000 ~ 320,000,000 (322,018,250)
15% * 378,845,000 ~ 57,000,000 (56,526,750)
Hence rawmaterials = 320,000,000
waste management and recycling = 57,000,000
Bunuel
12 Days of Christmas 2024 - 2025 Competition with $40,000 of Prizes
At Skyline Construction, project materials represented 38% of its annual project costs of $925,000,000 in 2023. Due to new environmental regulations and a shift toward sustainable building, project materials will account for 42% of total project costs in 2024, while total project costs are expected to decrease by 3%. Within project materials expenses, raw materials consistently make up 85% of costs, while recycling and waste management account for the remaining 15%.
In the table, select for
Raw Materials Cost for 2024 the approximate projected cost devoted to raw materials, and select for
Recycling/Waste Management Cost for 2024 the approximate projected cost devoted to recycling and waste management. Make only two selections, one in each column.