Bunuel
Akshay starts working on a job and continues for 15 days and completes 36% of the work. To complete the work, he employs Monika and together they work for 20 days and completed the work. What will be the efficiency ratio of Akshay and Monika ?
(A) 7 : 5
(B) 4 : 3
(C) 5 : 3
(D) 1 : 3
(E) 3 : 1
Akshay continues to work for 15 days and completes 36% of the work.
Let the total work be 100 units.
Akshay working for 15 days finishes 36 units.
Remaining work = 100-36 = 64 units.
Monika and Akshay work for 20 days to complete 64 units .
20 A + 20 M = 64 36 unit = 15 days
? = 20 days.
In 20 days , Akshay completes 48 units.
Remaining 16 units (64-48= 16 units) is completed by Monika in 20 days.
Akshay : Monika = 48:16 =
3:1 Another Approach: Efficiency = work / time Given: Akshay does 36% work in 15 days.
Ea = 36/15 = 12/5
If Akshay does 36% in 15 days, using UNITARY METHOD, in 20 days he completes 48 % of work.
If 36% is completed, the. Remaining work is 64% . ( total work =100%)
Out of 64% , Akshay completed 48% in 20 days. Job remaining is 16%. Which is completed by Monika in 20 days.
Em = 16/20 = 4/5
Ea: Em = 12/5 :4/5 = 12:4 =
3:1.