Last visit was: 21 Apr 2026, 12:04 It is currently 21 Apr 2026, 12:04
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 21 Apr 2026
Posts: 109,729
Own Kudos:
Given Kudos: 105,798
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,729
Kudos: 810,446
 [144]
17
Kudos
Add Kudos
126
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
GMATinsight
User avatar
Major Poster
Joined: 08 Jul 2010
Last visit: 21 Apr 2026
Posts: 6,976
Own Kudos:
16,891
 [62]
Given Kudos: 128
Status:GMAT/GRE Tutor l Admission Consultant l On-Demand Course creator
Location: India
GMAT: QUANT+DI EXPERT
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
WE:Education (Education)
Products:
Expert
Expert reply
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
Posts: 6,976
Kudos: 16,891
 [62]
26
Kudos
Add Kudos
34
Bookmarks
Bookmark this Post
User avatar
anudeep133
Joined: 10 Aug 2015
Last visit: 14 Dec 2018
Posts: 94
Own Kudos:
282
 [26]
Given Kudos: 20
Posts: 94
Kudos: 282
 [26]
20
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
General Discussion
User avatar
KS15
Joined: 21 May 2013
Last visit: 25 Jul 2019
Posts: 531
Own Kudos:
259
 [9]
Given Kudos: 608
Posts: 531
Kudos: 259
 [9]
5
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Kudos for a correct solution.

(10 people*20 days)/1/4=(8*x)/3/4
Solving for x, x=75
Answer C
User avatar
santorasantu
Joined: 27 Aug 2014
Last visit: 06 Apr 2023
Posts: 242
Own Kudos:
461
 [12]
Given Kudos: 76
Location: Netherlands
Concentration: Finance, Strategy
Schools: ISB '21 LBS '22
GPA: 3.9
WE:Analyst (Energy)
Schools: ISB '21 LBS '22
Posts: 242
Kudos: 461
 [12]
8
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Kudos for a correct solution.


Answer is C.

Total work content = 100*10 = 1000[units]

work done in 20 days by 10 people = 250[units]
20 days --- 250[units] ---10[people]
x days ---- 750[units] ---- 8[people]

x = 20*(750/250)*(10/8) = 75[days]

C
User avatar
aimtoteach
Joined: 17 Jul 2014
Last visit: 02 Feb 2016
Posts: 73
Own Kudos:
120
 [9]
Given Kudos: 62
Status:GMAT Date: 10/08/15
Location: United States (MA)
Concentration: Human Resources, Strategy
GMAT 1: 640 Q48 V35
GPA: 3.5
WE:Human Resources (Consumer Packaged Goods)
GMAT 1: 640 Q48 V35
Posts: 73
Kudos: 120
 [9]
8
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Step 1:

1/4 of the work was done in 20 days

So, complete work will be done in 20*4 = 80 days.

From the question stem - 10 people are hired to complete a job within 100 days - now we know they will finish this in 80 days.

Step 2:

As 20 day's work is already done, only 60 days of work remains. We know that 2 people have been fired, so we can use unitary method to solve the number of days required:

People working --------- days required to complete 3/4 of the work

10 -------------------------- 60
1 ----------------------------- 60/10
8 ------------------------------------ 60*8/10 = 75


Option C
User avatar
kunal555
Joined: 29 Jul 2015
Last visit: 17 Jun 2019
Posts: 143
Own Kudos:
779
 [2]
Given Kudos: 59
Posts: 143
Kudos: 779
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Kudos for a correct solution.

Work done by 10 people in 10 days = 1/4
Work to be completed by 8 people = 3/4
Let x be the time taken by 8 people to complete 3/4 work.
Then, at constant rate R
\(\frac{M_1RT_1}{W1}\) = \(\frac{M_2RT_2}{W2}\)

or \(\frac{20*10*R}{\frac{1}{4}} = \frac{x*8*R}{\frac{3}{4}}\)

or x= 75
Answer:- C
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 21 Apr 2026
Posts: 109,729
Own Kudos:
810,446
 [6]
Given Kudos: 105,798
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,729
Kudos: 810,446
 [6]
2
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Kudos for a correct solution.

VERITAS PREP OFFICIAL SOLUTION:

Can we say that 10 people can finish the work in 100 days? No. If that were the case, after 20 days, only 1/5th of the work would have been over. But actually 1/4th of the work is over. This means that ‘10 people can complete the work in 100 days’ was just the contractor’s estimate (which turned out to be incorrect). Actually 10 people can do 1/4th of the work in 20 days. The contractor fires 2 people. So the question is how many days are needed to complete 3/4th of the work if 8 people are working?

We need to find the number of days. How is ‘no. of days’ related to ‘no. of people’ and ‘work done’?

If we have more ‘no. of days’ available, we need fewer people. So ‘no. of days’ varies inversely with ‘no. of people’.

If we have more ‘no. of days’ available, ‘work done’ will be more too. So ‘no. of days’ varies directly with ‘work done’.

Therefore,
‘no. of days’ * ‘no. of people’/’work done’ = constant

\(20*\frac{10}{(\frac{1}{4})} =\) ‘no. of days’*\(\frac{8}{(\frac{3}{4})}\)

No. of days = 75

So, the work will get done in 75 days if 8 people are working.

We can also do this question using simpler logic. The concept used is joint variation only. Just the thought process is simpler.

10 people can do 1/4th of the work in 20 days.

8 people can do 3/4th of the work in x days.

Start with the no. of days since you want to find the no of days:

\(x = 20*(\frac{10}{8})*(\frac{3}{1}) = 75\)

From where do we get 10/8? No. of people decreases from 10 to 8. If no. of people is lower, the no of days taken to do the work will be more. So 20 (the initial no. of days) is multiplied by 10/8, a number greater than 1, to increase the number of days.

From where do we get (3/1)? Amount of work increases from 1/4 to 3/4. If more work has to be done, no. of days required will be more. So we further multiply by (3/4)/(1/4) i.e. 3/1, a number greater than 1 to further increase the number of days.

This gives us the expression \(20*(\frac{10}{8})*(\frac{3}{1})\)

We get that the work will be complete in another 75 days.

Answer (C)
avatar
ojas
Joined: 27 Feb 2015
Last visit: 01 Oct 2017
Posts: 2
Own Kudos:
5
 [2]
Posts: 2
Kudos: 5
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
We can also use the concept of man-days here

100 days -->10men so the job includes 100*10=1000 man-days

After 20 days

1/4 of Job is completed so 1/4 X 1000 man-days=250 man-days Job is done

Now the Balance Job=1000-250=750 man-days worth of Job
Since 2 men are fired so B/L men=8

Therefore Total no. of days of Job=750 man-day/8 days = 375/4=94 days (approx.)

Now since this is total and Ques. is asking for additional no. of days,
So 94-20=74 days
The nearest approx. to answer is 75

Ans: C (75 days)
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 18 Apr 2026
Posts: 11,230
Own Kudos:
44,982
 [10]
Given Kudos: 335
Status:Math and DI Expert
Location: India
Concentration: Human Resources, General Management
GMAT Focus 1: 735 Q90 V89 DI81
Products:
Expert
Expert reply
GMAT Focus 1: 735 Q90 V89 DI81
Posts: 11,230
Kudos: 44,982
 [10]
8
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Kudos for a correct solution.

Hi,
Just a POINT on wordings..
It would have been better, if it mentioned that all worked with same and constant speed

A quick approach could be..
so we assume that all have same capabilities to work..

1/4 work done in 20 days..
so remaining work can be done in 60 days with 10 person..
in the same ratio, the work can be done by 1 person in 60*10 days=600..
and 8 will do it in= 600/8= 75 days

C
avatar
sq01
Joined: 14 Dec 2014
Last visit: 07 May 2016
Posts: 18
Own Kudos:
23
 [11]
Given Kudos: 30
Concentration: Technology
Posts: 18
Kudos: 23
 [11]
8
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
Rate = Work/ Time

10 person team:
Work = 1/4 total
Time = 20 days
Rate = (1/4)/ 20 days = 1/4 *1/20 = 1/80

Rate of 1 person --> 1/80 * 1/10 = 1/800

8 person team:
Work = 3/4 total
Rate = 1/ 800 * 8 = 1/100
Time = (3/4) / (1/100) = 3/4 *100 = 75 days
avatar
Sachin07
Joined: 07 Jan 2017
Last visit: 14 Nov 2017
Posts: 13
Own Kudos:
14
 [2]
Given Kudos: 21
Location: India
Concentration: Other, Other
Schools: UConn"19
WE:Medicine and Health (Pharmaceuticals and Biotech)
Products:
Schools: UConn"19
Posts: 13
Kudos: 14
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Estimated rate by contractor is 1/1000 (10 workers *100 days)
As per this rate,the amount of work completed after 20 days should have been 20% which is not the case as 25 % work was done after 20 days by 10 workers
Thus the actual rate of workers would be 1/x*10*20=1/4————1/x=1/800
At the rate of 1/800, 8 workers would require 'y' days to complete the rest of the 75% work
1/800*8*y=3/4
y=3/4*800/8
y=75
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,974
Own Kudos:
8,708
 [5]
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,974
Kudos: 8,708
 [5]
3
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

The rate of 10 people is (1/4)/20 = 1/80.

After firing 2 people, 8 people are left. We can use the following proportion to determine the rate of 8 people:

10/(1/80) = 8/x

800 = 8/x

800x = 8

x = 1/100

Thus, it will take (3/4)/(1/100) = 300/4 = 75 days more to complete the job.

Answer: C
User avatar
Blackishmamba
Joined: 02 Aug 2017
Last visit: 19 Dec 2022
Posts: 34
Own Kudos:
204
 [6]
Given Kudos: 144
Concentration: Strategy, Nonprofit
Schools: ISB '20
GPA: 3.71
Schools: ISB '20
Posts: 34
Kudos: 204
 [6]
6
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The approach below is detailed for the understanding purposes, however once you know the logic behind it, you'd be able to solve the question faster.

Consider giving Kudos if it helps :D

Posted from my mobile device
Attachments

15351740000946689347440359215639.jpg
15351740000946689347440359215639.jpg [ 2.07 MiB | Viewed 35620 times ]

User avatar
nigina93
Joined: 31 Jul 2017
Last visit: 23 Jul 2025
Posts: 162
Own Kudos:
342
 [1]
Given Kudos: 347
Location: Tajikistan
Posts: 162
Kudos: 342
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?
(A) 60
(B) 70
(C) 75
(D) 80
(E) 100


A,D,E are out for obvious reasons. Now, we are left with B and C. If contractor doesn't fire any worker, then it will take them 60 days, but since he is firing 2 workers (or 20%), the work will be slowed down by 20% as well. So 60 days is 80%, 75 days is 100%
User avatar
MathRevolution
User avatar
Math Revolution GMAT Instructor
Joined: 16 Aug 2015
Last visit: 27 Sep 2022
Posts: 10,063
Own Kudos:
19,999
 [1]
Given Kudos: 4
GMAT 1: 760 Q51 V42
GPA: 3.82
Expert
Expert reply
GMAT 1: 760 Q51 V42
Posts: 10,063
Kudos: 19,999
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Rate * Time = Work done => r * t =w

=> \(\frac{(r * t) }{ w}\) = constant

10 people work for 20 days to complete \((\frac{1}{4})^{th}\) work:\(\frac{10 * 20}{\frac{1}{4}}\)

10-2 = 8 people work for 't' days to complete \((\frac{3}{4})^{th}\) work:\(\frac{8 * t}{\frac{3}{4}}\)


=> \(\frac{10 * 20}{\frac{1}{4}}\) = \(\frac{8 * t}{\frac{3}{4}}\)

=> 10 * 20 * 4 = \(\frac{(8 * t * 4) }{ 3}\)

=> 25 * 3 = t

=> 75

Answer C
User avatar
GMATGuruNY
Joined: 04 Aug 2010
Last visit: 02 Apr 2026
Posts: 1,347
Own Kudos:
Given Kudos: 9
Schools:Dartmouth College
Expert
Expert reply
Posts: 1,347
Kudos: 3,904
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100

Let the job = the product of the blue values above = 10*20*4 = 800 widgets.
Since 1/4 of the 800 widgets -- in other words, 200 widgets -- are produced in 20 days, the combined rate for 10 workers \(= \frac{work}{time} = \frac{200}{20} = 10\) widgets per day.
Since 10 workers produce 10 widgets per day, the rate per worker = 1 widget per day.

Since the rate per worker = 1 widget per day, the daily rate for 8 workers after 2 workers are fired = 8 widgets per day.
Time to produce the remaining 600 widgets at a rate of 8 widgets per day \(= \frac{work}{rate} = \frac{600}{8}\) = 75 days.

User avatar
SubaitaS
Joined: 17 Mar 2025
Last visit: 20 Apr 2026
Posts: 7
Given Kudos: 125
Posts: 7
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I did get 75 but I'm confused if that's correct, the question asked us to calculate *how many more days* then, why isn't it 75-20=55 days more?
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 21 Apr 2026
Posts: 109,729
Own Kudos:
Given Kudos: 105,798
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,729
Kudos: 810,446
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100­

In 20 days, 10 people complete 1/4 of the job.

So 10 * 20 = 200 person-days correspond to 1/4 of the work.
Therefore the full job requires 800 person-days.

Remaining work after 20 days = 3/4 of the job = 600 person-days.

After firing 2 people, 8 people remain.
So time needed for the remaining work = 600/8 = 75 days.

Answer: C.

SubaitaS
I did get 75 but I'm confused if that's correct, the question asked us to calculate *how many more days* then, why isn't it 75-20=55 days more?

75 is already the number of additional days after the first 20 days. At that point, 3/4 of the work is still left, and with 8 people it takes 75 more days to finish that remaining work. Subtracting 20 again would be double-counting the 20 days that have already passed.
User avatar
sakshimalps
Joined: 23 Feb 2026
Last visit: 20 Apr 2026
Posts: 1
Given Kudos: 1
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
10 persons able to finish 1/4th job in 20 days, cumulative rate= 1/80. assuming all workers work at same rate (unless otherwise specified), rate per person would be 1/800. applying it to 8 remaining, they will finish 1 job at the rate of 8 x 1/800 = 1/100. So, 100 days for 1 job, means 75 days for 3/4th remaining job. answer C.
Bunuel
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

(A) 60
(B) 70
(C) 75
(D) 80
(E) 100­