Last visit was: 26 Apr 2024, 07:45 It is currently 26 Apr 2024, 07:45

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Kudos
Tags:
Show Tags
Hide Tags
Manager
Manager
Joined: 09 Jan 2016
Posts: 78
Own Kudos [?]: 387 [137]
Given Kudos: 61
GPA: 3.4
WE:General Management (Human Resources)
Most Helpful Reply
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64933 [60]
Given Kudos: 427
Location: Pune, India
Send PM
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18761
Own Kudos [?]: 22056 [18]
Given Kudos: 283
Location: United States (CA)
Send PM
General Discussion
Current Student
Joined: 28 May 2014
Posts: 425
Own Kudos [?]: 1085 [15]
Given Kudos: 103
GMAT 1: 730 Q49 V41
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
6
Kudos
9
Bookmarks
24 men ----------- 16 days ------------ 1 complete work
1 man ------------ 1 day ------------1/(24*16) portion work

32 women ----------- 24 days ------------ 1 complete work
1 woman ------------ 1 day ------------1/(32*24) portion work

Hence,
1 man &1 woman ------------ 1 day ------------{1/(32*24) + 1/(24*16)} portion work = 1(/24)*(1/16 + 1/32) = (1/24)*(3/32) = (1/8)*(1/32)
Now,
16 man & 16 woman ------------ 1 day ------------ 16* (1/8)*(1/32) portion work = 2*(1/32) = 1/16
16 man & 16 woman ------------ 12 day ------------ 12*(1/16) = 3/4
Remaining work - 1/4

Now, extra work in next 2 days: 1/4 - 2*(1/16) = 1/8
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 .

Answer B.

This is not a SUB-600 level question.
Senior Manager
Senior Manager
Joined: 05 Jan 2017
Posts: 416
Own Kudos [?]: 284 [10]
Given Kudos: 15
Location: India
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
6
Kudos
3
Bookmarks
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


let the work be z rate of doing work for man and woman be x and y respectively

According to question
24*16*x = z
32*24*y = z

therefore 24*16*x = 32*24*y or x = 2y

work done in 12 days = (16x +16y)12 = (32y + 16y) 12 = 48*12y = 24*24y

work left = 32*24y-24*24y = 8*24y

work left = (no of men added rate+ current workers rate)*2

or 8*24y = (N*x +16x+16y)*2

putting x = 2y

4*24y = 2Ny+48y
2Ny = 48y

or N = 24.

Option B
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64933 [4]
Given Kudos: 427
Location: Pune, India
Send PM
Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
2
Kudos
2
Bookmarks
Expert Reply
ziyuen wrote:
VeritasPrepKarishma wrote:
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)


Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).



The relation between no. of workers and no of days is inversely proportional.
If there are fewer women, no of days taken will be more.

No of women * No of days = Constant

32 women * 24 days = 24 women * ?? days

?? days = 24 days * (32 women/24 women)

?? days = 24 days

Check out this blog post on work rate: https://anaprep.com/arithmetic-work-rat ... variation/

Originally posted by KarishmaB on 18 Mar 2017, 11:58.
Last edited by KarishmaB on 09 Aug 2023, 03:29, edited 2 times in total.
Alum
Joined: 12 Aug 2015
Posts: 2282
Own Kudos [?]: 3131 [4]
Given Kudos: 893
GRE 1: Q169 V154
Send PM
Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
4
Kudos
gmatexam439 wrote:
Bunuel wrote:
Twenty-four men can complete a job in sixteen days. Thirty-two women can complete the same job in twenty-four days. Sixteen men and sixteen women started working on the job for twelve days. How many more men must be added to complete the job in 2 days?

(A) 16

(B) 24

(C) 36

(D) 48

(E) 54


1M 1D work=1/(16*24)
1W 1D work=1/(24*32)

16M 1D work=1/24=2/48
16W 1D work=1/48

16M&W 1D work=3/48=1/16
16M&W 12D work=12/16

Hence remaining work=4/16=1/4 -------> this work should be completed by the additional men

1M 1D work=1/(16*24)
1M 2D work=1/(16*12)
xM 2D work=x/(16*12), this must be equal to 1/4

x/(16*12)=1/4
=> x=48

Answer: D


You did all the hard work.
But missed out just at the very end.

The highlighted portion is incorrect.

Here is the corrected version -->

The work 1/4 would be done by both x men and 16 women.
You forgot to take 16 women into account.
NOTE -> You have taken the entire men's number as x.

So work done by x men and 16 women in 2 days => 2[x/24*16 +16/24*32] =1/4
x=40
Hence additional men required => 40-16 => 24

Smash that B.
Moderator
Joined: 28 Mar 2017
Posts: 1090
Own Kudos [?]: 1970 [3]
Given Kudos: 200
Location: India
Concentration: Finance, Technology
GMAT 1: 730 Q49 V41
GPA: 4
Send PM
Re: Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
2
Kudos
1
Bookmarks
Bunuel wrote:
Twenty-four men can complete a job in sixteen days. Thirty-two women can complete the same job in twenty-four days. Sixteen men and sixteen women started working on the job for twelve days. How many more men must be added to complete the job in 2 days?

(A) 16

(B) 24

(C) 36

(D) 48

(E) 54


1M 1D work=1/(16*24)
1W 1D work=1/(24*32)

16M 1D work=1/24=2/48
16W 1D work=1/48

16M&W 1D work=3/48=1/16
16M&W 12D work=12/16

Hence remaining work=4/16=1/4 -------> this work should be completed by the additional men

1M 1D work=1/(16*24)
1M 2D work=1/(16*12)
xM 2D work=x/(16*12), this must be equal to 1/4

x/(16*12)=1/4
=> x=48

Answer: D
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6072
Own Kudos [?]: 4690 [2]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Kudos
1
Bookmarks
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


Quote:
Twenty-four men can complete a work in sixteen days.


So, Total mandays = 24*16 => 384

Quote:
Thirty-two women can complete the same work in twenty-four days.


So, Total womandays = 32*24 => 768

Now, total work = LCM( 384,768 ) => 768

So, Efficiency of men = 2 & Efficiency of women = 1

Quote:
Sixteen men and sixteen women started working for twelve days.


Work completed = (16*2 + 16*1 )12 => 576 units , Work left = 768 - 576 => 192

Quote:
How many more men are to be added to complete the work remaining work in 2 days?


\({(16+m)*2 + 16*1 }*2 = 192\)

Or, \((16+m)*2 + 16 = 96\)

Or, \((16+m) = 40\)

Or, \(m = 24\)

Thus, we need to add , 24 more men workers, answer must be (B) 24 men...
Retired Moderator
Joined: 04 Aug 2016
Posts: 391
Own Kudos [?]: 337 [1]
Given Kudos: 144
Location: India
Concentration: Leadership, Strategy
GPA: 4
WE:Engineering (Telecommunications)
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Kudos
ziyuen wrote:
VeritasPrepKarishma wrote:
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)


Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).


Total Work completed = Rate of work of each man * total # of man * total time

Rate of work of each man = Total Work completed / (total # of man * total time) = 1/ (24*16)
Manager
Manager
Joined: 27 Mar 2016
Posts: 74
Own Kudos [?]: 61 [1]
Given Kudos: 4
GMAT 1: 590 Q44 V22
Send PM
Re: Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
1
Bookmarks
Lets take lcm of 16,24 and 32 i.e 96. So let the work job be 96.
Now for men let their one day effort be x. So x*24*16= 96, hence x= 1/4
Similary for women let their one day effort per person be y . So y*32*24=96
Y= 1/8.
Now (1/4+1/8)*16*12=72. So 24 units of work is left. Now let no of men be z 1/4*2*z= 24.
Hence z =48

Sent from my ONEPLUS A3003 using GMAT Club Forum mobile app
Alum
Joined: 12 Aug 2015
Posts: 2282
Own Kudos [?]: 3131 [1]
Given Kudos: 893
GRE 1: Q169 V154
Send PM
Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
1
Kudos
Excellent question.
700 level for sure ..
Here is what I did on this question---->


Let us decode the statements ==>
Let the complete work be designated by W.

Twenty-four men can complete a job in sixteen day.
Speed of each men => W/(16*24) per day

Thirty-two women can complete the same job in twenty-four days.
Speed of each women => W/(32*24) per day

16 men and 16 women stated working

Combined speed of 16 men and 16 women => W/(16*24) * 16 + W/(32*24) *16 => W/24+W/48 => W/16 per day
Now combining they work for 12 Days =>

Work done => 12*W/16 => 3W/4
Left over work => W-3W/4 => W/4

Now let more men =x

Hence-->
2* [(x+16) W/(16*24) + 16*W/(32*24)] = W/4

Solving this we get => x=24

Hence B.



SMASH THAT B.

Looking forward to the OE.
Current Student
Joined: 30 Dec 2013
Status:preparing
Posts: 28
Own Kudos [?]: 26 [1]
Given Kudos: 26
Location: United Arab Emirates
Concentration: Technology, Entrepreneurship
GMAT 1: 660 Q45 V35
GMAT 2: 640 Q49 V28
GPA: 2.84
WE:General Management (Consumer Products)
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Bookmarks
the question is done in two parts:

1) work rate comparison bw men and women
24 men ---- 16 days
1 man ----- 24x16
16 man ----- 24 days

32 women ---- 24 days
16 women --- 48 days

so men : women = 2 : 1
men will do double the work done by women

2) work remaining after 12 days, that needs to be done in 2 days

men need 24 days to finish the work. so in 12 days they will do half the job
m ---- 1/2

women need 48 days to finish the job, and in 12 days they will do 12/48 = 1/4 th of the work

w----- 1/4

total work done in 12 days = m+w = 1/2 + 1/4 = 3/4
balance = 1/4 of work

In other words 1/4 * 24 =6 days of work for 16 men and 16 women

how many additional men required to finish in two days :
1/2 of work is done by 16 men
so 1/4 of work will be done by 8 men
total = 16+8= 24 men
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18761
Own Kudos [?]: 22056 [1]
Given Kudos: 283
Location: United States (CA)
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Bookmarks
Expert Reply
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


We are given that the rate of 24 men is 1/16, so the rate of each man is (1/16)/24 = 1/(16 x 24). Similarly, we are given that the rate of 32 women is 1/24, so the rate of each woman is (1/24)/(32) = 1/(24 x 32). Now we can find the fraction of the job that is completed by 16 men and 16 women in one day.

16 x 1/(16 x 24) + 16 x 1/(24 x 32)

1/24 + 1/(24 x 2)

2/48 + 1/48

3/48 = 1/16

We see that 16 men and 16 women can complete 1/16 of the job in one day, so they can complete 12 x 1/16 = 12/16 = 3/4 of the job in 12 days.

We can let m be the number of additional men who must be added to complete the job in two more days. Since we have 1 - 3/4 = 1/4 of the job left and it needs to be completed in two2 more days, each day they need to complete (1/4)/2 = 1/8 of the job. Thus, we can create the following equation to solve for m:

(16 + m) x 1/(16 x 24) + 16 x 1/(24 x 32) = 1/8

1/24 + m/(16 x 24) + 1/48 = 1/8

Multiplying the above equation by 48, we have:

2 + m/8 + 1 = 6

m/8 = 3

m = 24

Answer: B
GMAT Club Legend
GMAT Club Legend
Joined: 19 Dec 2014
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Posts: 21846
Own Kudos [?]: 11668 [1]
Given Kudos: 450
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Bookmarks
Expert Reply
Hi All,

Before we get into this question, you've been posting a variety of 'tougher' prompts lately - so unless you're already scoring above 700 in your practice Exams (or on the Official GMAT), then you might be focusing on the wrong things.

In these types of 'rate' questions, it often helps to think in terms of the TOTAL work that must be done to complete the task. If a 24-man crew can complete the job in 16 days, then that means that (24)(16) = 384 man-days of effort are required to complete the job. If a 32-woman crew can complete the job in 24 days, then that means that (32)(24) = 768 woman-days of effort are required to complete the job.

Before we do anything else, it's important to compare these numbers: 384 and 768. Since 384 is exactly HALF of 768, in this question that means that the work that a woman does in 1 day = 1/2 of the work that a man does in 1 day.

We're told that 16 men and 16 women work for 12 days each. That means they complete....

(16 men)(12 days) = 192 man-days of work = 1/2 of the job gets done
(16 women)(12 days) 192 woman-days of work = 1/4 of the job gets done

1/2 + 1/4 = 3/4... so after 12 days, 3/4 of the job is done - and 1/4 of the job remains

We're going to add a certain number of men, so that the job is completed in 2 more days. First though, we have to figure out how much more of the job gets completed with the existing people during that time...

(16 men)(2 days) = 32 man-days of work = 1/12 of the job gets done
(16 women)(2 days) 32 woman-days of work = 1/24 of the job gets done

During the next 2 days, the existing people will complete 1/12 + 1/24 = 3/24 of the job gets done

That leaves us with 1/4 - 3/24 = 3/24 of the job remains. 3/24 of 384 man-days = 48 man-days of work. The extra men that will be added will work for 2 days each, so....

(X men)(2 days each) = 48 days of man-work
X = 24

Final Answer:

GMAT assassins aren't born, they're made,
Rich
Intern
Intern
Joined: 31 Dec 2017
Posts: 22
Own Kudos [?]: 29 [1]
Given Kudos: 64
Concentration: Finance
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Bookmarks
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


Total work \(= 24m*16d = 384md\), or \(32w * 24d = 768wd\).

\(24m * 16d = 32w * 24d\)
\(1md = 2wd\): men are twice as efficient as women.

Work done by \(16m\) and \(16w\) in \(12\) days \(= 12(32wd + 16wd) = 576wd\).

Remaining work \(= 768-576 = 192 wd\), can be completed in \(2\) days by \(\frac{192}{2} = 96w\).

\(96w - 48w = 48w = 24m\). Ans - B.
Director
Director
Joined: 17 Dec 2012
Posts: 589
Own Kudos [?]: 1519 [1]
Given Kudos: 20
Location: India
Send PM
Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
1
Kudos
Expert Reply
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


time taken by 16 men=24 days
time taken by 16 women = 48 days

Proportion of work completed by 16 men and 16 women in 12 days= 12 /24 +12/48

In 14 days work is complete

(12+2)/24 + (12+2) /48 + 2/(16*24)/x =1 ( 16 men take 24 days . So x men take 16*24/x days. proportion of work completed by the additional men in 2 days = 2/ (16*24)/x )

7/8 + x/192 =1

x=24
Manager
Manager
Joined: 09 Jan 2016
Posts: 78
Own Kudos [?]: 387 [0]
Given Kudos: 61
GPA: 3.4
WE:General Management (Human Resources)
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
saswata4s wrote:
24 men ----------- 16 days ------------ 1 complete work
1 man ------------ 1 day ------------1/(24*16) portion work

32 women ----------- 24 days ------------ 1 complete work
1 woman ------------ 1 day ------------1/(32*24) portion work

Hence,
1 man &1 woman ------------ 1 day ------------{1/(32*24) + 1/(24*16)} portion work = 1(/24)*(1/16 + 1/32) = (1/24)*(3/32) = (1/8)*(1/32)
Now,
16 man & 16 woman ------------ 1 day ------------ 16* (1/8)*(1/32) portion work = 2*(1/32) = 1/16
16 man & 16 woman ------------ 12 day ------------ 12*(1/16) = 3/4
Remaining work - 1/4

Now, extra work in next 2 days: 1/4 - 2*(1/16) = 1/8
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 .

Answer B.

This is not a SUB-600 level question.
Then, extra men required in next 2 days: (24*16)/(2*8) = 24 . please explain this step again. :-D
Current Student
Joined: 14 Nov 2016
Posts: 1174
Own Kudos [?]: 20718 [0]
Given Kudos: 926
Location: Malaysia
Concentration: General Management, Strategy
GMAT 1: 750 Q51 V40 (Online)
GPA: 3.53
Send PM
Re: Twenty-four men can complete a work in sixteen days.Thirty-two women c [#permalink]
VeritasPrepKarishma wrote:
Chemerical71 wrote:
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working for twelve days.How many more men are to be added to complete the work remaining work in 2 days?

A .16
B. 24
C. 36
D. 48
E. 54


First find the relation of rate of work done by men vs women.

24 men complete the work in 16 days.
32 women can complete the same work in 24 days.
So 24 women will take 24 * (32/24) = 32 days to complete the work

Same number of women take twice the time (16 days vs 32 days) so their rate of work is half.
So 16 women are equivalent to 8 men work-wise.

So 16 + 8 = 24 men start working and work for 12 days. They complete the work in 16 days so they need another 4 days to complete. But if we want them to complete the work in half the time (2 days), we will need twice the work force. So we need another 24 men.

Answer (B)


Dear VeritasPrepKarishma, Does the font highlighted in red reflecting the relationship is inversely proportional instead of directly proportional?

For example, 10 apples cost $20, 5 apples will cost (5*$20/10=$10).
Manager
Manager
Joined: 09 Oct 2016
Posts: 70
Own Kudos [?]: 25 [0]
Given Kudos: 8
Location: United States
GMAT 1: 740 Q49 V42
GPA: 3.49
Send PM
Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
This one took a while to do simply bc of all the calculations (if there is a quick way please let me know)

I ended up with 48, D.

Men rate = 1/384
Women rate = 1/768

Combined and through 14 days = 336/384, 48 being the difference

Edit: upon further review, I made a mistake and didn't account for the two days. It should be 24 additional men, making the total 48 on day 12. This would produce the additional 96 units needed
Posted from my mobile device
GMAT Club Bot
Twenty-four men can complete a job in sixteen days. Thirty-two women [#permalink]
 1   2   
Moderators:
Math Expert
92933 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne