Last visit was: 17 May 2026, 18:48 It is currently 17 May 2026, 18:48
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 17 May 2026
Posts: 110,522
Own Kudos:
Given Kudos: 106,277
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 110,522
Kudos: 815,423
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Archit3110
User avatar
Major Poster
Joined: 18 Aug 2017
Last visit: 17 May 2026
Posts: 8,649
Own Kudos:
Given Kudos: 243
Status:You learn more from failure than from success.
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1: 545 Q79 V79 DI73
GMAT Focus 2: 645 Q83 V82 DI81
GPA: 4
WE:Marketing (Energy)
Products:
GMAT Focus 2: 645 Q83 V82 DI81
Posts: 8,649
Kudos: 5,198
Kudos
Add Kudos
Bookmarks
Bookmark this Post
avatar
swarnabh47
Joined: 14 Jan 2019
Last visit: 18 Feb 2021
Posts: 1
Given Kudos: 4
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ayush19
Joined: 27 Nov 2017
Last visit: 17 Mar 2026
Posts: 19
Own Kudos:
Given Kudos: 131
Location: India
GMAT 1: 580 Q47 V25
GPA: 4
GMAT 1: 580 Q47 V25
Posts: 19
Kudos: 30
Kudos
Add Kudos
Bookmarks
Bookmark this Post
swarnabh47
It asks about the number of turns since the last maintenance. It obviously has to be less than 4.09× 10^6. Hence A

Hi,

The question asks "when" and not "since" so the right answer will be till the time of the last maintenance.
So, the correct answer will be 4.09 * 10^6 * 30 = 12.27 * 10^7 = 1.2 * 10^8
Hence the correct option is C.
User avatar
EgmatQuantExpert
User avatar
e-GMAT Representative
Joined: 04 Jan 2015
Last visit: 02 Apr 2024
Posts: 3,651
Own Kudos:
21,001
 [1]
Given Kudos: 165
Expert
Expert reply
Posts: 3,651
Kudos: 21,001
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post

Solution



Given
In this question, we are given that
    • At Car Part Corporation, there is a machine that produces brake pads.
    • As the machine works, a wheel assembly turns.
    • After the wheel assembly turns 4.09× 10^6 times, the machine needs maintenance.
    • Since being installed, the machine has received maintenance 30 times.

To find
We need to determine
    • Approximately how many total turns had the wheel assembly made when the machine last received maintenance?

Approach and Working out
For each maintenance, the wheel assembly turns \(4.09 * 10^6\) times.
Hence, for 30 maintenances, total number of wheel assemble turns = \(30 * 4.09 * 10^6 = 3 * 4.09 * 10^6 * 10 = 12.27 * 10^7 = 1.227 * 10^8\)

Thus, option C is the correct answer.

Correct Answer: Option C