In the table below, projects planned projects A through G are given alongside their cost, time of completion, and projected revenues. A company xyz plans to complete some of these projects during the month of March. The company cannot work on two projects at once (including the preparation time), and cannot start any project that will not be finished by the end of the month. Preparation time is the time required before starting each project, and is not factored into the duration. For each small project (cost less than $19,000), the preparation time is 1 day, and for all other projects, preparation time is 2 days.