Last visit was: 22 Apr 2026, 19:16 It is currently 22 Apr 2026, 19:16
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [64]
4
Kudos
Add Kudos
60
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [21]
12
Kudos
Add Kudos
9
Bookmarks
Bookmark this Post
avatar
aabougabal
Joined: 07 Dec 2016
Last visit: 08 May 2021
Posts: 2
Own Kudos:
38
 [17]
Given Kudos: 195
Posts: 2
Kudos: 38
 [17]
15
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
41
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
Hi Bunnuel,

Kindly check my approach to this problem and pls comment on it:

Total Work = 10 persons X 110 days = 1100 person-days
Work completed till it rained for 5 days = 10 person X 55 days = 550 person-days.

Pending Work = 1100 - 550 = 550 person-days.
Ideally, from 61st day to 100th day, the manpower rose to 16, which means they can do a work of = 16 person X 40 days = 640 person-days.

But remaining work is only 550 person-days, so the difference is 640-550 = 90 person-days.
Therefore it rained for = 90/16 = 5.625 person-days.
Hence Work happened = 40-5.6 = 34.4 days

Hence it rained for 5 more days.

If u liked my detailed solution, a kudos will help :)
User avatar
gracie
Joined: 07 Dec 2014
Last visit: 11 Oct 2020
Posts: 1,028
Own Kudos:
2,021
 [5]
Given Kudos: 27
Posts: 1,028
Kudos: 2,021
 [5]
4
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
one man completes 1/1100 of total job in one day
(10)(55)/1100=1/2 of job
d=days to complete remaining 1/2 of job,
16d/1100=1/2
d=34.4 working days
40 total days taken-34.4 working days=5.6 rain days
can't round rain days up to 6 without exceeding 100 total days for job
answer is 5 days
User avatar
Senthil7
Joined: 31 Mar 2016
Last visit: 05 Mar 2017
Posts: 322
Own Kudos:
Given Kudos: 197
Location: India
Concentration: Operations, Finance
GMAT 1: 670 Q48 V34
GPA: 3.8
WE:Operations (Commercial Banking)
GMAT 1: 670 Q48 V34
Posts: 322
Kudos: 218
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I think this is a high-quality question and I agree with explanation.
avatar
nickimonckom
Joined: 17 May 2016
Last visit: 07 Jan 2022
Posts: 17
Own Kudos:
71
 [1]
Given Kudos: 38
GMAT 1: 740 Q46 V46
Products:
GMAT 1: 740 Q46 V46
Posts: 17
Kudos: 71
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hi,

It may sound idiot and I apologies first for it,

How do you quickly calculate that \(\frac{550}{16} = 34,4\) ?

In GMAT there are lot of intermediate calculus like this one that makes me lose lot of time and I do not know how to go fast on them

Many thanks in advance for your kind help,
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
810,672
 [1]
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
nickimonckom
Hi,

It may sound idiot and I apologies first for it,

How do you quickly calculate that \(\frac{550}{16} = 34,4\) ?

In GMAT there are lot of intermediate calculus like this one that makes me lose lot of time and I do not know how to go fast on them

Many thanks in advance for your kind help,

\(\frac{550}{16}\)

Reduce by 2: \(\frac{275}{8}\). Next you should simply divide 275 by 8.
User avatar
BillyZ
User avatar
Current Student
Joined: 14 Nov 2016
Last visit: 24 Jan 2026
Posts: 1,135
Own Kudos:
Given Kudos: 926
Location: Malaysia
Concentration: General Management, Strategy
GMAT 1: 750 Q51 V40 (Online)
GPA: 3.53
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Official Solution:

A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

A. 4
B. 5
C. 6
D. 7
E. 8


Given: 10-man crew needs 110 days to complete the construction.

"On the 61-st day, after 5 days of rain ...": as it was raining for 5 days then they must have been working for 55 days thus completed \(\frac{1}{2}\) of the job, \(\frac{1}{2}\) is left (55 days of work for 10 men).

Then contractor "hired 6 more people": speed of construction increased 1.6 times, so the new 16-men crew needed \(\frac{55}{1.6} \approx 34.4\) days to complete the construction, but after they were hired job was done in \(100-60=40\) days. Therefore it rained for 5 days. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100 (40) days.)


Answer: B

Dear Bunuel, How could we relate the people hired to the speed of construction?

\(Rate = \frac{1}{Time}\)
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
810,672
 [3]
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [3]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
AustinKL
Bunuel
Official Solution:

A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

A. 4
B. 5
C. 6
D. 7
E. 8


Given: 10-man crew needs 110 days to complete the construction.

"On the 61-st day, after 5 days of rain ...": as it was raining for 5 days then they must have been working for 55 days thus completed \(\frac{1}{2}\) of the job, \(\frac{1}{2}\) is left (55 days of work for 10 men).

Then contractor "hired 6 more people": speed of construction increased 1.6 times, so the new 16-men crew needed \(\frac{55}{1.6} \approx 34.4\) days to complete the construction, but after they were hired job was done in \(100-60=40\) days. Therefore it rained for 5 days. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100 (40) days.)


Answer: B

Dear Bunuel, How could we relate the people hired to the speed of construction?

\(Rate = \frac{1}{Time}\)

Let me ask you: say 1 man can do a certain job in 10 hours. In how many hours can the job be done by 2 men? In 5 hours, right. So, increasing the number of men twice we reduce the time need by the same rate.
avatar
Manoraaju
Joined: 10 May 2017
Last visit: 22 Aug 2021
Posts: 9
Own Kudos:
13
 [2]
Posts: 9
Kudos: 13
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I did it this way and i derived at the right answer as well.

Total work done 110x10=1110

55 days work= 55x10=550.

5 days rain=zero work done

61st day 16 works are working. Work is completed in 100 days. So remaining work done in days is 550/16 is approximaterly 34.xx and round off to the next largest integer 35. So 100-55-5-35=5 days.
User avatar
VAKRATUNDA
Joined: 27 Apr 2011
Last visit: 13 Oct 2022
Posts: 38
Own Kudos:
55
 [1]
Given Kudos: 201
Location: India
GMAT Date: 06-13-2017
Products:
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Short and logical Approach:

(10 man-crew X 110 Days) = 1100 Man-days
Less: (10 man-crew X 55 days (On 61st day, 5 rainy days are already passed.)) = 550 Man-days
Balance Work = 550 Mandays

Total man-crew from 61st day=10+6=16
Hence, Balance work after 60 days will be divided by 16 man-crew to arrive at no of days worked after 60th day.
=550/16 = Appx. 35 days worked appx. (Remember we need to consider part of the day as full day)
Hence, 100 days-60 days = 40 days
40 days-35 days worked=5 rainy days after 60th day.
User avatar
tirthshah2013
Joined: 16 Sep 2022
Last visit: 27 Jul 2025
Posts: 18
Own Kudos:
Given Kudos: 4
Location: India
Concentration: General Management, Technology
Schools: ISB '23 (S)
GPA: 4
Schools: ISB '23 (S)
Posts: 18
Kudos: 4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

A. 4
B. 5
C. 6
D. 7
E. 8


The answer for this question will be 5.

We know that 10 man can complete the work in 110 days, so total work done would be 1100. We know that no one works on days in which it rains. After 55 days the work completed would be 550.

So the remaining work = 1100-550= 550.

After 55th day, there was 5 day rain and from 61st day the workers increased from 10 to 16.

New number of workers = 16.

The question says the work was completed in 100 days after the 61st day.

Therefore, total number of days the 16 workers worked for including the rainy days = 40.

We are told work is completed in 100 days, and total work remaining was 550. Therefore they completed the work in 550/16=34.4 days.

Normally in 40 days the 16 workers should have completed 640 work. But only 550 was remaining hence the extra 90 work will be the days when they didn't work.

Therefore total number of days it rained after 61st day = 90/16 = 5.625 but since days cannot be in decimal we select 5 as if we select 6, the work will be completed in 34 days but the work was completed in more than 34 days, so we round down 5.625 to 5

Posted from my mobile device
User avatar
adewale223
Joined: 07 Oct 2022
Last visit: 14 Apr 2026
Posts: 113
Own Kudos:
Given Kudos: 45
Location: Nigeria
Posts: 113
Kudos: 76
Kudos
Add Kudos
Bookmarks
Bookmark this Post
From the question 10 men have done work for 55 days.

To calculate how much of work done within that period

55/110 which is 1/2. That means1/2 of work left.

If it took 55 days for 10 men to do half of the work then 16 men will take 10/16 x 55 = 34 days.

Since they started work on day 61, 34 + 61 = 95.

Since work was completed within 100 days that means it rained for 5 days.

Posted from my mobile device
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I have edited the question and the solution by adding more details to enhance its clarity. I hope it is now easier to understand.
User avatar
ShaunakSawant
Joined: 21 Apr 2022
Last visit: 09 Aug 2025
Posts: 40
Own Kudos:
Given Kudos: 49
Location: India
Posts: 40
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I calculated the number of days when it rained, and thus the answer came down to 5.6, which is approximately 6 days. This is why I chose 6 days/ option C

Can some expert help me why option B is right answer and why we need to round down the count to 5?
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
810,672
 [1]
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
ShaunakSawant
I calculated the number of days when it rained, and thus the answer came down to 5.6, which is approximately 6 days. This is why I chose 6 days/ option C

Can some expert help me why option B is right answer and why we need to round down the count to 5?

The crew needed MORE than 34 days to finish the job, so if there had been 6 rainy days, they wouldn't have been able to complete the project within 100 (40) days.
User avatar
A_
Joined: 24 May 2023
Last visit: 29 Nov 2025
Posts: 14
Own Kudos:
Given Kudos: 1,884
Posts: 14
Kudos: 2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I like the solution - it’s helpful.
User avatar
Sushi_545
Joined: 25 Jan 2024
Last visit: 22 Apr 2026
Posts: 69
Own Kudos:
Given Kudos: 44
Posts: 69
Kudos: 15
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hi @gracie/@Bunuel

i followed similar approach got 5.6 days as answer so rounded to 6 why we have rounded to 5?
gracie
one man completes 1/1100 of total job in one day
(10)(55)/1100=1/2 of job
d=days to complete remaining 1/2 of job,
16d/1100=1/2
d=34.4 working days
40 total days taken-34.4 working days=5.6 rain days
can't round rain days up to 6 without exceeding 100 total days for job
answer is 5 days
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
810,672
 [1]
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,672
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Sushi_545
Hi @gracie/@Bunuel

i followed similar approach got 5.6 days as answer so rounded to 6 why we have rounded to 5?


I addressed this doubt here: https://gmatclub.com/forum/m07-183740.html#p3201553 Hope it helps.
Moderators:
Math Expert
109754 posts
Founder
43153 posts