Last visit was: 14 Dec 2024, 00:38 It is currently 14 Dec 2024, 00:38
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
tanu11
User avatar
Retired Moderator
Joined: 19 Apr 2019
Last visit: 12 Dec 2024
Posts: 97
Own Kudos:
156
 []
Given Kudos: 17
Location: India
2
Kudos
Add Kudos
8
Bookmarks
Bookmark this Post
User avatar
MathRevolution
User avatar
Math Revolution GMAT Instructor
Joined: 16 Aug 2015
Last visit: 27 Sep 2022
Posts: 10,114
Own Kudos:
17,806
 []
Given Kudos: 4
GMAT 1: 760 Q51 V42
GPA: 3.82
Expert reply
GMAT 1: 760 Q51 V42
Posts: 10,114
Kudos: 17,806
 []
2
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
User avatar
Abhishek009
User avatar
Board of Directors
Joined: 11 Jun 2011
Last visit: 02 Oct 2024
Posts: 6,014
Own Kudos:
Given Kudos: 463
Status:QA & VA Forum Moderator
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Posts: 6,014
Kudos: 4,952
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
QuantMadeEasy
Joined: 28 Feb 2014
Last visit: 13 Dec 2024
Posts: 502
Own Kudos:
660
 []
Given Kudos: 75
Location: India
Concentration: General Management, International Business
GPA: 3.97
WE:Engineering (Education)
Posts: 502
Kudos: 660
 []
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Quote:
The cost of digging a pit was $2694. How much will it cost approximately if the wages of workmen per day had been increased by 1/8 of the former wages and the length of the working day increased by 1/20 of the former period?
Step 1: Understanding the question
Let number of working days be n;
Wages of workmen per day be x;
Length of work per day be y

Hence, Total cost = Number of working days * wages of workmen per day = n*x
2694 = nx
Amount of work to be done = Number of working days * length per day = ny

Let number of new working day by m;
New wages of workmen per day = x+ x/8 = 9x/8;
New length of work per day = y + y/20 = 21y/20

Amount of work to be done = Number of new working days * New length per day = m * 21y/20 =21my/20
As, Amount of work is constant, 21my/20 = ny
Hence, m = 20n/21

New Total cost = Number of new working days * new wages of workmen per day = m * (9x/8)
= (20n/21) * (9x/8)
= (20/21) * (9/8) * nx
= (20/21) * (9/8) * 2694
~ 2886

IMO A
avatar
roul123
Joined: 05 Oct 2020
Last visit: 21 Oct 2020
Posts: 1
Given Kudos: 11
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Is a question like this really fair? It never says that the project takes more time... just that the days are longer. If the rate of work doesnt change and the pay is hourly, wouldn't the workers make more per day but work less days???
avatar
PelumiOgunlana
Joined: 16 Jul 2020
Last visit: 07 Dec 2022
Posts: 30
Own Kudos:
Given Kudos: 15
Location: United States (IL)
GMAT 1: 590 Q39 V31
GMAT 2: 660 Q44 V38
GMAT 3: 670 Q46 V37
GPA: 3.38
GMAT 3: 670 Q46 V37
Posts: 30
Kudos: 6
Kudos
Add Kudos
Bookmarks
Bookmark this Post
MathRevolution
The cost of digging a pit was $2694

New wage: 1 + \(\frac{1}{8}\) = \(\frac{9}{8 }\)of old wage

The new length of working hours: 1 + \(\frac{1}{20}\) = \(\frac{21}{20}\) of the old length of working hours.

Since the number of days is inversely proportional to working hours per day,

=> New number of days = \(\frac{20 }{ 21}\) * old number of days

Cost is directly proportional to wages per day
Cost is directly proportional to the number of days

New cost : 2,694 * \(\frac{9 }{ 8} * \frac{20 }{ 21}\) = 2886

Answer A


How would you do the last step within the 2 minute time limit without a calculator?
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 13 Dec 2024
Posts: 19,869
Own Kudos:
24,292
 []
Given Kudos: 288
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 19,869
Kudos: 24,292
 []
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
tanu11
The cost of digging a pit was $2694. How much will it cost approximately if the wages of workmen per day had been increased by 1/8 of the former wages and the length of the working day increased by 1/20 of the former period?

A. 2886
B. 2880
C. 2883
D. 2881
E. 2876
Solution:

We can let the old wage be $80/day and the old length of a working day is 10 hours. Therefore, the new wage is 80 x 9/8 = $90/day and the new length of a working day is 10 x 21/20 = 10.5 hours.

Assuming only 1 worker is digging the pit and since his old wage is 80/10 = $8/hr, it will take him $2694/$8 = 336.75 hours to dig the pit. Since it will still take him 336.75 hours to dig the same pit given the new wage and new length of a working day, it will take him 336.75/10.5 days to dig the pit and be paid with (336.75/10.5) x 90 = $2,886.43, or approximately $2,886.

Answer: A
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 35,817
Own Kudos:
Posts: 35,817
Kudos: 929
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderator:
Math Expert
97874 posts