A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
A. 4
B. 5
C. 6
D. 7
E. 8
- Veritas Prep has worked with over 50K students at over 90 locations worldwide. Save $350 at GMAT Club. Details!
- MBA Prep School: Essay & Resume Editing, Mock Interview & Regular Admit Consult. Full service, full savings. Use the GMAT Club code and save up to $500!
- MBA Admit Consulting: Save with 2-For-1 Gold Package Application Special. Only at GMAT Club. Learn more!
- Like our Question of the Day? Sign up for Kaplan's Free Question a Day
Verbal
Cherapunji receives more rainfalls than any other site of the world, yet the agriculture so fertile and the water reservoirs are efficient, so that the water does not overflow the land; otherwise, the level of surface water would rise unexpectedly and flood most of the state’s renowned towns.
(A)
are efficient, so that the water does not overflow on the land; otherwise,
(B)
are efficient so that the water does not overflow the land; were it to do so,
(C)
so efficient that the water does not overflow on the land, or else
(D)
efficient, so that the water does not overflow on the land, or
(E)
efficient so that the water does not only overflow the land; if it did
Correct Answer - B - (click and drag your mouse to see the answer)
Like these questions? Get the GMAT Club question collection: online at GMAT Club OR on your Kindle OR on your iPhone/iPad