Last visit was: 18 Nov 2025, 15:48 It is currently 18 Nov 2025, 15:48
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
Sub 505 Level|   Work and Rate Problems|                        
User avatar
Walkabout
Joined: 02 Dec 2012
Last visit: 30 Oct 2025
Posts: 172
Own Kudos:
28,184
 [43]
Given Kudos: 35
Products:
Posts: 172
Kudos: 28,184
 [43]
11
Kudos
Add Kudos
32
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,977
Own Kudos:
8,387
 [10]
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,977
Kudos: 8,387
 [10]
5
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,068
 [10]
4
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
General Discussion
User avatar
iNumbv
Joined: 02 May 2012
Last visit: 06 Jan 2016
Posts: 10
Own Kudos:
88
 [1]
Given Kudos: 5
Posts: 10
Kudos: 88
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Walkabout
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) 7/12
(B) 1 1/2
(C) 1 5/7
(D) 3 1/2
(E) 7

The rate of the first machine is 1/4 job per hour;
The rate of the second machine is 1/3 job per hour;

Thus, the combined rate of the machines is 1/4+1/3=7/12 job per hour, which means that it takes 1/(7/12)=12/7 hours both machines to do the job.

Answer: C.

Suppose we change the wording of the problem to "It would take 2 machines 4 hours together to complete a large production" How would you solve for that ? I'm trying to better understand the nature of the problem. Thanks. My logic says the rate is still the same since it still is 4 hours. If so than what does it change?
avatar
arpana10july
Joined: 19 Jan 2012
Last visit: 05 Jan 2019
Posts: 1
Given Kudos: 34
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
how can the answer be C
in options dere is no option of 12/7
User avatar
blueseas
User avatar
Current Student
Joined: 14 Dec 2012
Last visit: 15 Jan 2019
Posts: 577
Own Kudos:
4,509
 [2]
Given Kudos: 197
Location: India
Concentration: General Management, Operations
GMAT 1: 700 Q50 V34
GPA: 3.6
GMAT 1: 700 Q50 V34
Posts: 577
Kudos: 4,509
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
arpana10july
how can the answer be C
in options dere is no option of 12/7

there is a typo in choice.

machine A takes 4 hr
machine B takes 3 hr
then together they will take = product /sum =\((4*3)/(4+3)\)
avatar
runningguy
Joined: 09 Sep 2013
Last visit: 24 Feb 2014
Posts: 13
Own Kudos:
Given Kudos: 7
Posts: 13
Kudos: 11
Kudos
Add Kudos
Bookmarks
Bookmark this Post
arpana10july
how can the answer be C
in options dere is no option of 12/7

12/7 is equivalent to 1 and 5/7
User avatar
BrentGMATPrepNow
User avatar
Major Poster
Joined: 12 Sep 2015
Last visit: 31 Oct 2025
Posts: 6,739
Own Kudos:
35,331
 [2]
Given Kudos: 799
Location: Canada
Expert
Expert reply
Posts: 6,739
Kudos: 35,331
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Walkabout
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) 7/12
(B) 1 1/2
(C) 1 5/7
(D) 3 1/2
(E) 7

Another approach is to assign the ENTIRE job a certain number of units.
The least common multiple of 4 and 3 is 12.
So, let's say the ENTIRE production order consists of 12 widgets.

It would take one machine 4 hours to complete a large production...
Rate = output/time
So, this machine's rate = 12/4 = 3 widgets per hour

...and another machine 3 hours to complete the same order.
Rate = units/time
So, this machine's rate = 12/3 = 4 widgets per hour

So, their COMBINED rate = 3 + 4 = 7 widgets per hour.

Working simultaneously at their respective constant rates, to complete the order?
Time = output/rate
= 12/7 hours

Answer:
User avatar
adkikani
User avatar
IIM School Moderator
Joined: 04 Sep 2016
Last visit: 24 Dec 2023
Posts: 1,236
Own Kudos:
1,343
 [1]
Given Kudos: 1,207
Location: India
WE:Engineering (Other)
Posts: 1,236
Kudos: 1,343
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
JeffTargetTestPrep Bunuel



When we are given t as 3 and 4 hours why are we still assigning an unknown variable?
User avatar
EMPOWERgmatRichC
User avatar
Major Poster
Joined: 19 Dec 2014
Last visit: 31 Dec 2023
Posts: 21,785
Own Kudos:
Given Kudos: 450
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Expert
Expert reply
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Posts: 21,785
Kudos: 12,802
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hi boomgoesthegmat,

In "work" questions, there are 2 common ways to get to the correct answer (although there are several different ways to "do the math"):

1) When there are 2 entities (people, machines, etc.) working on a task together, use the Work Formula.
2) Convert the individual rates of the 2 (or more) entities, combine and be sure to answer the question that's asked.

In this question, here's how you could use the two options mentioned:

We're told...
Machine A = 4 hours to complete an order
Machine B = 3 hours to complete the same order

We're asked how long it would take the two machines, WORKING TOGETHER, to complete the order.

1) Using the Work Formula: (A)(B)/(A+B).....

(4)(3)/(4+3) = 12/7 hours to complete the job

2) Using the individual rates:

Machine A:
4 hours to do the entire job --> 1 hour to do 1/4 of the job
Machine B:
3 hours to do the entire job --> 1 hour to do 1/3 of the job

In 1 hour, 1/4 + 1/3 = 7/12 of the job is done

**Note: this calculation tells you the FRACTION of the JOB that is complete in 1 HOUR**

Since there is 1 job to complete.....1/(7/12) = 12/7 hours to complete the job

Either way, the Final Answer is...
GMAT assassins aren't born, they're made,
Rich
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,803
Own Kudos:
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,803
Kudos: 6,063
Kudos
Add Kudos
Bookmarks
Bookmark this Post
adkikani
JeffTargetTestPrep Bunuel



When we are given t as 3 and 4 hours why are we still assigning an unknown variable?

Hi adkikani

The reason we are assigning t(an unknown variable) for time, because we don't
know how much time will be take to complete the entire work, when working together.

When we are given 3 and 4 hours as time, it means that the individual machines
will complete the entire work(working alone) in 3 and 4 hours respectively.

Alternate approach

Since it takes one machine 4 hours to complete the order and the second machine takes
3 hours to complete the order, we can assume the work done to be 60 units.

The individual rate of the first machine to complete the work will be 15 units/hour
and the rate of the second machine is 20 units/hour. So, together they will complete 35 units in an hour.

Therefore, the time taken for both the machines(combined) is \(\frac{60}{35} = \frac{12}{7} =1\frac{5}{7}\)(Option C)

Hope that helps!
User avatar
dave13
Joined: 09 Mar 2016
Last visit: 12 Aug 2025
Posts: 1,108
Own Kudos:
Given Kudos: 3,851
Posts: 1,108
Kudos: 1,113
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Walkabout
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) \(\frac{7}{12}\)

(B) \(1 \frac{1}{2}\)

(C) \(1 \frac{5}{7}\)

(D) \(3 \frac{1}{2}\)

(E) 7

The rate of the first machine is 1/4 job per hour;
The rate of the second machine is 1/3 job per hour;

Thus, the combined rate of the machines is \(\frac{1}{4}+\frac{1}{3}=\frac{7}{12}\) job per hour, which means that it takes \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \frac{5}{7}\) hours both machines to do the job.

Answer: C.

Hi Bunuel :) can you help to understand the logic behind this \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \\
\\
why do you flip \frac{7}{12}\) in order to know how much time will it take both to complete :?
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,803
Own Kudos:
6,063
 [1]
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,803
Kudos: 6,063
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
dave13
Bunuel
Walkabout
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) \(\frac{7}{12}\)

(B) \(1 \frac{1}{2}\)

(C) \(1 \frac{5}{7}\)

(D) \(3 \frac{1}{2}\)

(E) 7

The rate of the first machine is 1/4 job per hour;
The rate of the second machine is 1/3 job per hour;

Thus, the combined rate of the machines is \(\frac{1}{4}+\frac{1}{3}=\frac{7}{12}\) job per hour, which means that it takes \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \frac{5}{7}\) hours both machines to do the job.

Answer: C.

Hi Bunuel :) can you help to understand the logic behind this \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \\
\\
why do you flip \frac{7}{12}\) in order to know how much time will it take both to complete :?

Hi dave13

Basically, If \(\frac{1}{x}\) of the work takes place in 1 hour, the time taken to complete the work will be x!

Here in this question, x = \(\frac{7}{12}\)

So, when we finish \(\frac{1}{(\frac{7}{12})}\) of the work in 1 hour, the time taken to complete the work is \(\frac{12}{7}\)

Hope that helps you!
User avatar
eakabuah
User avatar
Retired Moderator
Joined: 18 May 2019
Last visit: 15 Jun 2022
Posts: 777
Own Kudos:
Given Kudos: 101
Posts: 777
Kudos: 1,124
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Ta=4hrs, Tb=3hrs
Ra=1/Ta =1/4 and Rb=1/Tb=1/3
Rate when the two machines work together, Rab, can be gotten as follows:
1/Rab =1/Ra + 1/Rb = 1/4+1/3 = 7/12
But Tab=1/Rab = 12/7 hrs

Posted from my mobile device
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
dave13
Bunuel
Walkabout
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) \(\frac{7}{12}\)

(B) \(1 \frac{1}{2}\)

(C) \(1 \frac{5}{7}\)

(D) \(3 \frac{1}{2}\)

(E) 7

The rate of the first machine is 1/4 job per hour;
The rate of the second machine is 1/3 job per hour;

Thus, the combined rate of the machines is \(\frac{1}{4}+\frac{1}{3}=\frac{7}{12}\) job per hour, which means that it takes \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \frac{5}{7}\) hours both machines to do the job.

Answer: C.

Hi Bunuel :) can you help to understand the logic behind this \(\frac{1}{(\frac{7}{12})}=\frac{12}{7}=1 \\
\\
why do you flip \frac{7}{12}\) in order to know how much time will it take both to complete :?
dave13
In \(\frac{7}{12}\) the unit is \(\frac{job}{hour}\). You need hour (time). So, just flip it. You'll get the hour.
Thanks__
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Quote:
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) \(\frac{7}{12}\)
(B) \(1 \frac{1}{2}\)
(C) \(1 \frac{5}{7}\)
(D) \(3 \frac{1}{2}\)
(E) 7
Hello all,
We can solve this question logically that will save your time for sure!
Choice D and E:
One machine (x) takes 3 hrs to complete whole the job and another machine (y) takes 4 hrs to complete the same job. If if they do the same job simultaneously, then their total time will be less than 3 hours. So, the answer choices (D,E) which keeps more than 3 hours are crossed out.
In real life example:
You do a job by 3 hrs; i do the same job by 4 hrs. If i help you to do the SAME job (with respective constant rate), you will need LESS THAN 3 hours to complete whole the job.
Choice A, B and C:
Suppose, x takes 3 hours to take the job; and y takes 3 hours to take the same job (with respective constant rate). If they do simultaneously, then they need \(1\frac{1}{2}\) hours to complete whole the job, right? But, in the question prompt, y takes 4 hours (who is slower than x). So, they need more than \(1\frac{1}{2}\) hours if they do simultaneously. So, A and B are out. The correct choice is C.
User avatar
EMPOWERgmatRichC
User avatar
Major Poster
Joined: 19 Dec 2014
Last visit: 31 Dec 2023
Posts: 21,785
Own Kudos:
Given Kudos: 450
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Expert
Expert reply
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Posts: 21,785
Kudos: 12,802
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Asad
Quote:
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

(A) \(\frac{7}{12}\)
(B) \(1 \frac{1}{2}\)
(C) \(1 \frac{5}{7}\)
(D) \(3 \frac{1}{2}\)
(E) 7
Hello all,
We can solve this question logically that will save your time for sure!
Choice D and E:
One machine (x) takes 3 hrs to complete whole the job and another machine (y) takes 4 hrs to complete the same job. If if they do the same job simultaneously, then their total time will be less than 3 hours. So, the answer choices (D,E) which keeps more than 3 hours are crossed out.
In real life example:
You do a job by 3 hrs; i do the same job by 4 hrs. If i help you to do the SAME job (with respective constant rate), you will need LESS THAN 3 hours to complete whole the job.
Choice A, B and C:
Suppose, x takes 3 hours to take the job; and y takes 3 hours to take the same job (with respective constant rate). If they do simultaneously, then they need \(1\frac{1}{2}\) hours to complete whole the job, right? But, in the question prompt, y takes 4 hours (who is slower than x). So, they need more than \(1\frac{1}{2}\) hours if they do simultaneously. So, A and B are out. The correct choice is C.

Hi Asad,

That is a great series of deductions - and it shows how GMAT questions can almost always be approached in more than one way.

GMAT assassins aren't born, they're made,
Rich
User avatar
ArnauG
Joined: 23 Dec 2022
Last visit: 14 Oct 2023
Posts: 298
Own Kudos:
Given Kudos: 199
Posts: 298
Kudos: 42
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let's assume that the production order is 1 unit in size.

Machine 1 can complete 1/4 of the order in 1 hour, while Machine 2 can complete 1/3 of the order in 1 hour. Working together, they will complete 1/4 + 1/3 = 3/12 + 4/12 = 7/12 of the order in 1 hour.

Therefore, we can set up the equation:

(7/12) * t = 1

where "t" is the time it takes both machines working together to complete the order.

Solving for "t", we get:

t = 12/7 hours

Therefore, the answer is approximately 1.71 hours or 1 hour and 42 minutes, and the correct choice is (C) 1 5/7.
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,586
Own Kudos:
Posts: 38,586
Kudos: 1,079
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
105355 posts
Tuck School Moderator
805 posts